189 Mo. App. 683 | Mo. Ct. App. | 1915
This is a suit for damages on account of an alleged breach of contract. At the conclusion of the evidence introduced on the part of plaintiff, the court directed a verdict for defendant. Plaintiff prosecutes the appeal, and the question for consideration relates to the propriety of the ruling mentioned.
It appears that plaintiff maintains a stone quarry near defendant’s railroad in St. Louis county and did so in 1901. A switch track owned by defendant connected with plaintiff’s stone quarry, but it became dilapidated and out of repair. Plaintiff, desiring to
The evidence tends to prove, and, indeed, is conclusive, that the parties entered into the written contract, as above stated, which will be hereafter set forth in full; that plaintiff paid to defendant the $300 cash in accordance with the terms of the contract and defendant put the spur track in proper condition for use at the time. There is no complaint with respect of this and the case concedes that both parties fully complied with the original undertaking therein — that is, that plaintiff paid the $300 and that defendant put the track in proper condition. It appears, too, that the’track was permitted to remain for about ten years — or until
Omitting the signatures of the parties, the contract sued upon in full is as follows:
4 4 This Agreement, made and entered into this 25th clay of September, 1901, by and between The Missouri Pacific Railway Company, a railway corporation owned and organized under the laws of the State of Missouri, party of the first part, and the Stolle Stone Company, a corporation organized under the laws of Missouri, party of the second part:
44"Witnesseth, That:
“Whereas, what is known as the Glendale Quarry Spur on the Carondelet Branch of the Missouri Pacific Railway is not in proper condition for the running and operating of cars over it; and
4 4 Whereas, the said party of the second part is desirous of making shipments of stone and other ma*688 terial -apon said track for a distance of about four hundred and fifty (450) feet on said spur to its connection with said Carondelet Branch:
“Now, therefore, in consideration of the undertaking by said party of the first part to put the said spur track for a distance of 450 feet from said Carondelet Branch as above stated in safe operating condition, so as to accommodate the traffic of said Stolle Stone Company, the said party of the second part, the Stolle Stone Company, hereby agrees to pay to said party of the first part before the work of repairing said track shall begin the sum of three hundred dollars ($300) to in part cover the costs of putting said track in proper condition; and the said party of the first part hereby agrees, after and in the event it shall receive one thousand dollars ($1000) in freight paid by said Stolle Stone Company in shipments originating on said Glendale Quarry Spur on the Carondelet Branch aforesaid, to refund ten (10) per cent of the amounts thereafter collected on freight bills until said $300, without interest, shall be repaid to said party of the second part. ’ ’
When we attend to the wording of the contract and consider the evidence given on the part of plaintiff, it appears that defendant performed the full measure of its obligation expressly assumed by putting the spur track in proper condition in 1901. The preamble to the contract recites, first, that the track was out of repair ; and, second, that plaintiff desired to make shipments over it. It then proceeds, “Now, therefore, in consideration of the undertaking by said party of the first part (defendant) to put the said spur track for a distance of 450 feet from said Carondelet Branch, as above stated, in safe operating condition, so as to accommodate the traffic of said Stolle Stone Company.,r The stone company (plaintiff) agreed to pay $300 in advance. The provision then follows to the effect that, in event and after plaintiff had paid defendant as
By a careful reading of the entire contract it is revealed that no covenant whatever is to be found therein through which defendant undertakes to maintain the spur track at all or to permit it to remain situate there for any definite time. The spur track and the materials of which it was constructed, though situate on plaintiff’s land, were the property of defendant, for all of the evidence shows this to be true. Although there is no express stipulation concerning the time defendant should permit the track to remain, from a reading of the contract it appears to clearly reveal an implied obligation to the effect that the track should remain for such a length of time as would be reasonably sufficient in due course considering the circumstances — that is, the business — to permit plaintiff to make sufficient shipments to yield a $300 refund to it according to the terms as by the deduction of ten per cent on shipments made after $1000 freight charges had been collected by defendant. But beyond this implied obligation, there appears to be no undertaking, either express or implied, committing defendant to maintain the track for any definite period. This being true, in the absence of some showing in the evidence concerning the shipments made and the amount of freight paid, or that plaintiff had not had a reasonable time according to the usual course of its business or in the circumstances contemplated by the parties to reimburse its outlay, no right of recovery is shown under the first count of the petition, an the ground of a
The court very properly directed a verdict for defendant under the first count of the petition.
The second count of the petition proceeds, it is said by appellant, for damages accrued as for a trespass. But we regard the second count as one sounding in contract. It sets forth the facts pertaining to the contract and the alleged rights of plaintiff thereunder. After so doing, it avers that in 1904 a freshet washed out a bridge in the spur track about sixty feet in length and defendant neglected to repair it, whereupon, it is said, plaintiff purchased the necessary timbers and employed the labor and installed a bridge in the spur track to replace the one washed out, at an expense of $195. It is averred that it was the duty of defendant under its contract — that is, the same, contract above copied — to maintain the track in suitable condition and that this duty was breached by it in failing to install the bridge above referred to. Because defendant failed to fulfill its duty in the premises, plaintiff expended $195 in rebuilding the bridge, and thereafter in 1911 defendant tore up and carried away all such materials, to plaintiff’s damage in the sum of $195. We discover no obligation, either express or implied, in the contract above set out imposing on defendant the duty of maintaining the track beyond putting it in proper repair in the first instance and this it did in 1901, and certainly no breach may be assigned in respect of that matter.
. On considering the evidence relevant to the s'econd count, it appears that plaintiff installed the bridge in quuestion on its own account voluntarily and without any request whatever from defendant to do so. It is true it had notified defendant and requested that the bridge be rebuilt, but defendant omitted to take any steps in the premises. Thereupon, plaintiff went about
The judgment should be affirmed. It is so ordered.