Stoehr v. City of St. Paul

54 Minn. 549 | Minn. | 1893

Vanderburgh, J.

The defendant, during the years 1889 and 1890, in improving and grading Page street in West St. Paul, made a fill in and across a ravine by depositing therein earth from the vicinity. This ravine runs northerly to the Mississippi river, through the bluff, from the high level land above, a distance of three-quarters of a mile or more, with an average fall of more than 300 feet to the mile, and affords surface drainage for a considerable tract of land. The sides are abrupt and steep, and at the bottom its width varies from twenty-five to one hundred and fifty feet. It is so situated that large quantities of water, the result chiefly of rains and melting snow and ice, naturally flow northerly through it to the river, and in some places have worn a well-defined channel; and the evidence tends to show that there was such a channel through which the water flowed in the ravine at the place where the fill was made on Page street, and for a considerable distance below. At this place the fill for the street is about one hundred and forty feet wide at the bottom, sixty feet wide at the top, and about twenty-four feet on the upper, and thirty-six feet high on the lower, side. It was constructed in accordance with the plans and specifications therefor adopted by the city. In pursuance thereof, across and at or near the bottom of the fill, and to answer the purpose of a culvert to carry off the water, was placed a box two by three feet in size, and two hundred feet long, made of plank, and *553laid in the bed or channel of the ravine. The structure was finished early in 1890, but the culvert soon after became clogged, so as to be ineffectual to carry off the water which was gathered above the fill by the obstruction caused by it. The consequence was that in July, 1892, a large quantity of water had been collected and retained in a pond above the fill, standing 10 to 12 feet in depth against it. This was increased largely by an extraordinary rain storm occurring July 2Gth of that year, which raised the water in the pond above the embankment to within one or two feet of the level of the street. For 2,000 feet above and 1,000 feet below the reservoir the descent in the ravine was very rapid, the fall being about seventy feet to the mile. Below, along its bank, were several houses, occupied by inhabitants, including the plaintiff. On the evening of August 3, 1892, the bank or fill gave way under the pressure o'f the water, and the pent-up waters rushed in a torrent down the ravine, causing the damage and injury complained of.

The topography and the condition of the ravine, showing well-defined channels in the narrow places, indicated plainly enough the presence of streams of water from melting snows and rains, recurring at intervals during the year, and constituted a sufficient warning of the necessity of making safe provisions therefor in grading the streets; and, as respects property owners and residents’ below the embankment in question here, who might be injured by a sudden release of waters, as from a reservoir, in case the fill should be undermined or break away, the measure of care and diligence used should have been commensurate with the degree' of danger to be apprehended. The city authorities clearly recognized this obligation in the nature of the plans provided for the improvement;, and, in order to prevent the accumulation of water, a sluiceway, sufficient to drain off the water in the ravine, was expressly required therein. The embankment was constructed for street purposes only. The material- for the fill, composed of sand, gravel, and clay, taken from cuts in grading the street, without respect to the nature thereof or its capacity to resist percolation or pressure, was deposited upon the surface of the ground in its natural condition, without any preparation or clearing away of the grass, shrubbery, and small trees growing there. The embankment was therefore not built or maintained as a dam, but the city assumed the duty *554•and responsibility of maintaining a proper drain or culvert, and of keeping tbe same in order, and tbe action was brought, tried, and determined on that theory. It is very clear, also, from the evidence, that the city had constructive notice that the drain was closed and inoperative a long time before the accident, and actual notice early in July, 1S92. The evidence tended to prove that in the spring of 1892, after the snow melted, the upper end of the box drain was several feet under water, and remained so continuously thereafter, and that in the previous years there was more or less water in the pond, and no effort was made by the city to remedy the defective ■drainage until after the 9th day of July, 1892, and the futile efforts ■and inadequate means thereafter made and resorted to to get rid of the water are hardly sufficient to relieve the defendant from the ■charge of negligence.

(Opinion published 56 N. W. Rep. 250.)

The evidence also tends to show that from the nature of the material used in the fill, and the manner in which it was put in, the water would naturally work under and through it, and it would become unstable and unsafe in consequence, and that signs of percolation, saturation, and softening of the bank had appeared for a considerable time previous to the accident.

And the jury found specially that the water in the pond had already “so weakened the fill before the great storm in July, 1892, that, but for this weakening, the fill would have held all the water subsequently accumulated there.” Seasonable and proper drainage would therefore have saved the embankment. The evidence fails to show due diligence or proper and seasonable efforts after notice to open the drain or provide a new one. The plans were sufficient, and the drain probably large enough and suitable, for the purpose intended, and to have prevented the accident but for the subsequent neglect, the evidence of which we think was sufficient to establish the liability of the defendant.

Upon the state of the record, there was nothing misleading in the charge of the court, and nothing therein or in its rulings on the trial of which the defendant can properly complain.

Order affirmed.