42 P. 1072 | Cal. | 1895
This action was instituted to foreclose twelve liens for labor and materials furnished and used in the construction of a house for the defendant Riley, the several claims, including costs of recording, aggregating in amount the sum of $1,728.86. One of the said liens was for materials furnished by the plaintiff, and the others were duly assigned to the plaintiff. One Duncan also commenced an action to foreclose a lien for labor done by him on the building, of the value of $25, and the two actions were consolidated and tried together. The contract, under which the building was constructed, was executed by Riley, as owner, and J. H. Cummins, as contractor, on October 10, 1893, and was duly recorded. It provided that Cummins should do all the work and furnish all the materials necessary to complete the building according to the plans and specifications made by Charles W. Davis, architect, for the sum of $2,180. It further provides that the payments, so far as need be stated here, should be made as follows: (4) When ready for plastering, $250; (5) when first coat of plastering is finished, $250; (6) when white coat of plastering is finished, $250; (7) when whole work completed and accepted by architect, $300; balance, $530, usual thirty-five days, “provided, that in each of the said cases a certificate be obtained and signed by the said Chas. W. Davis that he has done his work so far as done to his satisfac
The principal points made for a reversal are: (1) That the court erred in deciding that the contract was valid and binding, when, by its terms, twenty-five per cent of the whole contract price was not made payable at least thirty-five days after the final completion of the contract. (2) That the court erred in deciding that the fourth, fifth and sixth payments were not made before they became due. (3) That the court erred in deciding that the plaintiff was not entitled to enforce the lien for the claim of S. C. Dodge. (4) That the court erred in allowing plaintiff only $75 as an attorney’s fee.
As to the second point: The house constructed under the contract had a bath-room, which was seven by twelve feet in size and twelve feet in height. It was wainscoted up five feet from the floor, and had a window and door and transom over the door. At the times when the three payments complained of were made the bath-room was not entirely lathed or plastered, but it was partially lathed when the fourth payment was made, and partially plastered when the fifth and sixth payments were made. It was proved that it would take one man five or six hours to complete the lathing and plastering. Mr. Davis, the architect, testified: “I issued an architect’s certificate for each payment that was made on this building before the payment was made, upon my own authority, as the architect of the building. At the time of issuing each certificate I personally examined the building, and know that the building was at each time completed to the stage authorizing the payment to be made.” There is no pretense that the certificates were obtained by fraud or collusion, but it is claimed that, because the bath-room was not fully lathed and plastered when the payments were made, the owner should be subjected to the penalty of paying the money—$750—a second time.
As to the third point: It is claimed for appellant that the bond executed by Davis was void, because not signed by Cummins, and in support of this position Sacramento v. Dunlap, 14 Cal. 421, and People v. Hartley, 21 Cal. 585, 82 Am. Dec. 758, are cited. The cases cited are not in point. In each of those cases the bond sued upon was in form the joint bond of the principal and sureties, and not joint and several, and was signed only by the sureties. It was held that under such circumstances no recovery could be had on the bond. And see Weir v. Mead, 101 Cal. 125, 40 Am. St. Rep. 46, 35 Pac. 567, where the authorities upon the subject are reviewed. Here the bond in question was in form joint and several, and in Kurtz v. Forquer, 94 Cal. 91, 29 Pac. 413, a similar bond, which was executed for a like purpose, was held valid and binding. Whether the execution of the bond by Dodge should be held to operate as an estoppel against him and his assignee from enforcing his claim against Riley, it is unnecessary to determine. The claim was assigned to and was owned by the plaintiff, and judgment against Cummins was entered in favor of plaintiff for the aggregate of all its claims. And, without
As to the fourth point: The code provides that the court must allow a reasonable attorney’s fee to the lien claimant. What is a reasonable fee is a matter to be determined by the trial court, and its action will not be disturbed on appeal unless it appears that the sum allowed is clearly unreasonable. The record only shows that the trial of the ease occupied a portion of four days, but how much of each day does not appear. While the sum allowed seems rather small, we cannot say that the court abused its discretion in determining that $75 was a reasonable fee.
Certain rulings of the court upon the admission of evidence are specified in the statement as erroneous, but they are simply referred to in appellant’s brief without argument. On examination of the record we fail to discover any material error in any of the rulings referred to, and therefore pass them by without special notice. The judgment and order appealed from should be affirmed.
We concur: Britt, C.; Haynes, C.
For the reasons given in the foregoing opinion the judgment and order appealed from are affirmed.