109 Ct. Cl. 353 | Ct. Cl. | 1947
delivered the opinion of the court:
The plaintiff on June 27, 1938, made a contract with the Government to build some 15 miles of levee along the Illinois Biver and one of its tributaries. The price was 8y2 cents per cubic yard for the quantity of levee embankment satisfactorily placed. The work was completed on September 6, 1940, final payment was made by the Government, which the plaintiff accepted without any protest or the reservation of any claim. In this suit the plaintiff claims damages because of (1) the Government’s alleged failure to furnish skilled and semiskilled labor from relief rolls, (2) the Government’s alleged misrepresentation of the condition of certain borrow pits, as to the height to which they were filled and the nature of the materials in them, and (3) the Government’s assessment of liquidated damages for late completion of the work, which late completion the plaintiff says should have been excused under the terms of the contract.
We discuss first the question of relief labor. The invitation for bids and the contract gave the plaintiff notice that a part of the money for the project was to come from emergency relief funds and the balance from a regular appropriation for river improvements; that in order to use üp the amount allotted from emergency relief funds, the contractor would be obliged to use enough man-months of relief labor to account for the allotment on the basis of a specified number of dollars for each such man-month. Before making the plaintiff’s bid, the plaintiff’s president had, upon inquiry, been told by the Works Progress Administration that there was plenty of common labor on the relief rolls, but no skilled or semiskilled labor. After the contract was signed, the plaintiff submitted a proposed schedule for the use of labor which did not call for enough common labor to use up the
We pass to the plaintiff’s claim of misrepresentation of the contents of the borrow pits. In the construction of levees in the same area in former years, depressions had been left in the land between the levee and the river by the removal of soil to build the levees. When the contract here in question was made, another contractor under a wholly separate contract was engaged in dredging the river bottom and was placing the dredged spoil in these depressions, as a convenient place to get rid of it. When the plaintiff’s agent
It should be observed that, upon the plaintiff’s complaint, that it was put to extra expense because some of the old borrow pits had water and silt in them which made the terraim difficult to work over and the material difficult to place in the> new levee, the Government treated the situation as one in
On December 2, the contracting officer replied to the plaintiff calling attention to the lack of authority of an in
Upon these facts the plaintiff is not entitled to recover. ■ If did not take its appeal within the time specified in the contract. It did not notify the contracting officer of its claim in time for him to investigate conditions before they were disturbed, as the contract required. This last neglect was in the face of a recent and considerate request from that officer, which request again showed, as the contract itself did, why the procedure was reasonable. In spite of this negligence of the plaintiff, the contracting officer did investigate and decide, as best he could after the work was done, and he decided against the plaintiff on the merits of the claim. We cannot say that his decision was wrong, even if we should disregard the plaintiff’s failures to take the steps required by the contract.
The plaintiff’s third ground of claim is for liquidated damages withheld from its compensation. The contract provided for such damages at the rate of $20 per day for late completion. The work was completed 151 days after the completion date as postponed by suspensions of the work and extensions granted, and $3,020 was, accordingly, withheld on that account. The plaintiff says that one of the causes of its delay was that its subcontractor abandoned the work shortly after its commencement, and that it required some
The plaintiff says that lack of skilled labor from the relief rolls caused it to be delayed by having to do work by hand that could have been done more quickly by machines. We have considered this same problem above in connection with the plaintiff’s claim for increased costs, and have concluded that the plaintiff was able to get skilled labor from other than relief sources in an amount more than three times as large as it had planned to use. We, therefore, find no delay in that regard which the Government was obliged to excuse. The plaintiff’s third contention with regard to late completion is that the fact that the borrow pits were not completely filled with dredging spoil resulted.in mud holes and sloppy material which, when placed in the levee, spread out and had to be dried out and rehandled, requiring much time. We have discussed this problem above. As we have seen, the plaintiff made several requests for additional compensation because of “changed” or unforeseen conditions. In none of these did it request an extension of the contract time, but in the two change orders which resulted from these requests, additional time was’given. In our finding 34 we show that on November 1, 1939, the plaintiff asked the contracting officer for an extension of time of “about 60 days” because of several things, the first mentioned of which was the muddy condition of the borrow pits. As to none of the items mentioned in this letter was the request timely, within the requirements of Article 9 of the contract. The evidence does not show that the contracting officer considered or decided
The plaintiff’s petition will be dismissed. It is so ordered.