23 Haw. 502 | Haw. | 1916
OPINION OP THE COURT BY
The plaintiff in error was the defendant in an action of assumpsit tried in the circuit court with a jury wherein judgment, was entered against him in the sum of $57,038.76. The plaintiffs’ complaint included four counts. The first count was upon a contract in writing bearing date the 29th day of July, 1909, and alleged to have been modified by certain letters dated August 3 and 10, 1909, for the construction of a building at Portland, Oregon, a balance of $54,506 being claimed to be due and unpaid under said contract. The second count was in quantum meruit for the reasonable value of the material furnished, and the work and labor performed in the erection and completion of the building. The third count was upon an account stated wherein it was alleged that in the month of February, 1911, the parties found to be due, and the defendant promised to pay, the sum of $54,506. The fourth count was in quantum meruit for the value of additional work, including the furnishing of material and labor, upon said building not covered by the contract. The defendant, in his answer, denied that there remained an unpaid balance due the plaintiffs under the contract or otherwise, and claimed that the sum of $26,500 had been improperly charged against him, and that he had been damaged by reason of delay in the completion of the building and by defective construction, in the sum of $25,811.25. The jury returned a verdict for the plaintiffs in the sum of $38,847.63, with interest from February 3, 1911.
“2. We will erect this building on a percentage basis, you paying only the exact cost of the building with the changes made in the plans and specifications, as estimated, Four Hundred Eighty-two Thousand, Three Hundred Fourteen Dollars ($482,314.00); you paying us for our services Eight Per Cent (8%) of the actual cost of the building, or, if you prefer, we will make a fixed commission of Thirty-eight Thousand Dollars ($38,000.00) on the building erected in accordance with the changes now outlined, subject to any increase for any additional work done not now determined upon; our employment under this proposition being arranged for practically in accordance with the contract which I showed you some months ago, made between us and the owners of the First National Bank Building, Denver, which we are now erecting, which contract provides:
“That we shall furnish at our expense such machinery, tools and equipment as are necessary for the prompt erection of the building;
“That we will make every effort to adopt every practical means to reduce the cost of the building as far as possible;
“That we will keep separate accounts, files of letters, etc., for this work;
“That we will furnish monthly statements of all materials entering into the building, payrolls, and amounts due to sub-contractors;
“That we will maintain an office in Portland;
“That we will attend to the question of insurance, employer’s liability, etc.”
The defendant accepted the offer on the fixed commission basis with the modification, mutually agreed upon, to the effect that should the contractors effect a saving on the
“In order that there may be no question with Col. Spalding as to what items enter into the cost of the building in ascertaining finally what is the actual cost, and there may not be charged against our commission certain payment which really enter into the cost of the work, we desire to have added to the specifications, or to the contract a clause clearly stating this understanding, and I would suggest the following, viz:
“ ‘In calculating the cost of the building under this contract there shall be included therein the amount of all subcontracts, of all material entering into this construction, and the wages of all persons employed upon the building, also the cost of all permits, surveys, temporary office with telephone and supplies, temporary heat, light, enclosures, floors, bridges to the sidewalks, etc., temporary water closets, and other plumbing, freights on all materials, equipment and tools, liability insurance, and repairs to streets or to the adjoining property/ ”
Replying thereto on August 10 Gilbert wrote:
“As to the second and third paragraphs of your letter, I think there can be no question ‘as to what items enter into the cost of the building in ascertaining finally what is the actual cost.’ The general conditions of the specifications are clear on this subject and I find your statement of the case to be correct on the subject as follows: ‘In calculating the cost of the building under this contract there shall be included therein the amount of all sub-contracts, of all material entering into its construction and the wages of all persons employed upon the building, also the cost of all permits, surveys, temporary offices with telephone and supplies, temporary heat, light, enclosures, floors, bridges to sidewalk, etc., temporary water closets, and other plumbing, freights on all materials, equipment and tools, also*507 liability insurance and repairs to streets or adjoining property.’ ”
A contract was drawn up by the architect and the plaintiffs signed the same on August 27, and the defendant signed it on his return from Europe on September 11. A clause in the specifications which were made part of the contract provided that “The contractor is to provide derricks, hoists, machinery, scaffolding, tools and appliances of every description required for the proper execution of this work.” It was also provided in the specifications that “The general permit for the erection of the building will be obtained by the architect at contractor’s expense. The contractor shall obtain and pay for all other permits which may be required by the city laws and regulations.” Thus appeared a flat contradiction between the terms of the offer made by the plaintiffs in their letter of July 29 and the contract executed by the parties, on one hand, and. the terms of the letters of August 3 and 10, on the other. The cost of tools and equipment, permits, liability insurance, and the maintenance of a temporary office in Portland constituted a part of the plaintiffs’ claim and was admitted in evidence over the objections of the defendant. The court instructed the jury that “The burden is also upon the plaintiffs of proving by a preponderance of the evidence that the letters of Augüst 3, 1909, and August 10, 1909, between the architect and the plaintiffs were ratified by the defendant. If you find that they were so ratified, then the written contract was to that extent modified. But if you find that they were not so ratified, then I instruct you that the architect, unless specially authorized so to do, could not vary the terms of the written contract between the plaintiffs and defendant.” Counsel for the defendant conceded that if the letters in question were brought to the defendant’s attention and had been ratified by him they should be regarded as having modified the contract. ■ Their
At the close of the case for the plaintiffs the defendant moved for a directed verdict on the grounds that no evidence had been adduced to show (1) that the parties had agreed on the amount to be paid or allowed on account of alterations or changes alleged to have been directed to be made in the construction of the buildings as provided by article III of the contract; or (2) that the plaintiffs have selected or asked the defendant to select arbitrators to fix the amount to be paid for such alterations or changes; or (3) facts excusing plaintiffs from the selection or attempt to select such arbitrators; and (4) that the performance of the work, or furnishing of the materials, for or on account of alterations or changes (except in a few specified instances) was in accordance with any written agreement or by written order of the architect with the approval of the owner as provided in the specifications. The contention was that as the aggregate charge made in the plaintiffs’ account for changes made in the building during the course of construction exceeded the amount claimed by the plaintiffs in this action the plaintiffs could not recover because the extra charges had not been incurred in the manner provided in the contract and specifications. Article III of the contract provided that “No alterations shall be made in the work except upon written order of the architect; the amount to be paid by the owner or allowed by the con
A difference of opinion arose between the parties as to whether the cost of the subdivision of certain floors of the building into offices was included in the contract price or could properly be made the subject of an extra charge. The contract provided for the construction and completion of the building “as shown on the drawings and described in the specifications” which “become hereby a part of this contract.” Neither the contract itself nor the specifications mentioned the number of floors which thé building was to contain or how they were to be subdivided, but the plans showed a basement, twelve floors and an attic. The dispute concerned the second, third, fourth, fifth, tenth, eleventh and twelfth floors, the plans of which showed what were spoken of as “loft” floors, that is, floors without par
The case was submitted to the jury upon all. four counts of the complaint. The jury were instructed that should they find for the plaintiffs upon either of the quantum meruit counts no interest should be allowed, and
The agreed compensation payable to the contractors for the erection of the building under the contract was $482,314, for work and materials, and $38,000, contractors’ commission, with the further provision for an additional commission upon a saving in the cost of work and materials as above stated. The total cost of the completed building, according to the statement rendered by the plaintiffs, including all charges for alterations, additional work and commissions, was $562,267.42, upon which payments had been made amounting to $505,665.03. The contract provided that the banking room (first floor) should be completed on or before March 1, 1910, and the remainder of the building on or before July 1, 1910. From evidence adduced the jury could have found that the building had been substantially completed in the manner required by the contract and the orders for changes and additions, and that the delay in its completion resulted entirely from the alterations and additional work ordered from time to time by the defendant and the architect. On the other hand the evidence would have warranted a finding that the making of the changes and additions did not account for all of the delay. There was evidence to the effect that the first floor was completed within the time specified, and that the remainder of the work was not finally finished until January 5, 1911. The last or “final” certificate issued by the architect was dated February 6, 1911. It was pro
The plaintiff in error contends that the court erred in authorizing the jury to find for the plaintiffs upon the third count in the complaint. The court charged the jury, in substance, that if they should find from the evidence that upon the completion of the building the defendant received a final account, making objection to certain items therein and making no objection within a reasonable time to other items in the account then the law presumes that he admitted the items not objected to to be correct, and the burden would be upon the defendant to rebut the presumption, and that in determining whether or not the defendant did object to items within a reasonable time the jury could take into consideration the magnitude and complexity of the account and all other facts relative thereto. The record
The judgment of the circuit court is reversed and set aside, and a new trial is granted.