Stern v. Schlafer

12 N.W.2d 678 | Wis. | 1943

Lead Opinion

* Motion for rehearing denied, without costs, on January 21, 1944. Action commenced August 25, 1941, by plaintiff-appellant against Wilmer Schlafer and Dorothy Schlafer, his wife, defendants-respondents, for the foreclosure of a mechanic's lien based on charges made by plaintiff for work, labor, and materials furnished as extras in connection with the construction of a residence for defendants in the city of New London, Waupaca county. The defendants' counterclaim is based *184 upon alleged acts of omission in performance of the original contract, and alleged defective workmanship in both the original contract and in connection with various items of extras. The original contract price was $5,643. The plaintiff's claim for extras was $1,354.69. Defendants' counterclaim for damages was $1,728.19.

On May 11, 1942, the court below entered an order of reference and appointed Lloyd Smith, Esq., as referee to take the testimony in said action and to hear, try, and determine same, both as to law and facts. After testimony was taken and closed, Mr. Smith died without rendering a decision. Thereafter, the court appointed W. E. Atwell as referee to try the issues of law and fact. The parties stipulated that Mr. Atwell should decide the case upon the record. The referee made his report to the court, containing his findings of fact and conclusions of law, on January 30, 1943. On plaintiff's claim for extras the referee found for plaintiff in the sum of $955.88; on defendants' counterclaim the referee found for defendants in the sum of $880.65; and as conclusions of law found: (1) That plaintiff was entitled to the sum of $955.88 on his cause of action; (2) that defendants were entitled to an offset by reason of their counterclaim in the sum of $880.65; (3) that plaintiff was entitled to judgment foreclosing his lien, and the amount due plaintiff was the sum of $75.23.

Defendants moved for an order confirming the referee's report. The plaintiff moved to modify the report by allowing certain items in the plaintiff's claim for extras which the referee had disallowed, and further to set aside the award of the referee on defendants' counterclaim; or in the alternative for an order vacating and setting aside the report of the referee and directing a new trial of the issues. Plaintiff also filed certain exceptions to the findings of the referee. On March 15, 1943, the court filed its decision confirming the referee's report in all respects. From a judgment accordingly entered on April 21, 1943, plaintiff appeals. *185 The parties entered into a written contract whereby the plaintiff agreed to furnish all the labor and material necessary for the erection of a house for defendants in the city of New London, in conformity with plans and specifications prepared by defendants' architect, L. W. McCreedy, for an agreed consideration of $5,643; which amount defendants have paid. A disagreement has arisen between the parties relative to certain omissions which defendants claim were covered in the original contract price, and certain extras claimed by plaintiff and furnished by him in excess of the calls of his contract. The plaintiff's case is based solely upon his claims for extras furnished in the construction of defendants' residence. Defendants' counterclaim, as stated above, is based upon alleged omissions of certain items which the contract covered, and damages resulting by reason of alleged defective workmanship.

The referee's findings as to items allowed and disallowed in the plaintiff's claim, for extras are amply sustained by the evidence. Defendants' architect, Mr. McCreedy, on cross-examination, was asked:

"Q. In fact everything in that house met with your complete approval? A. Approximately so."

The defendant Wilmer Schlafer testified as follows in answer to questions by his own counsel:

"Q. Showing you defendants' Exhibit 3, Mr. Schlafer, are those a complete list of the items that you are willing to allow and pay for the respective amounts set after each item?A. Yes, sir.

"Q. That represents a total of $780.52? A. Yes, sir."

The items on Exhibit 3, referred to in the above questions and answers, are all taken from the list of items claimed by *186 plaintiff as extras and are all included in the allowance of $955.88 made by the referee in his findings on the plaintiff's claim. Thus there is a difference of only $175.36 between the total amount allowed plaintiff under the referee's findings and the amount which defendants admit owing and are willing to pay.

However, the referee's allowance of $880.65 on defendants' counterclaim cannot stand because it is made on a wrong rule of damages. The correct rule, which should have been applied, was the worth of defendants' house in its present condition as compared to worth if properly built. We so held in the recent case of Venzke v. Magdanz, 243 Wis. 155, 160,9 N.W.2d 604. The application of the wrong rule of damages necessitates a retrial of the action of the issues raised in the counterclaim. We see no occasion for a retrial of the issues on the plaintiff's cause of action.

It will serve no useful purpose to detail the items covered by the referee's allowance on the plaintiff's cause of action. A careful study of the testimony as to the items allowed or disallowed leads us to conclude that the finding of $955.88 is in accord with the great weight and clear preponderance of the evidence. Since the court entered judgment in form for the difference between the amount found by the referee in favor of the plaintiff and the amount found in favor of the defendants on their counterclaim, namely, for the sum of $75.23 damages, plus $54.15 disbursements and $75 attorney fees, the judgment must be vacated and set aside. Entry of judgment on the plaintiff's cause of action will be deferred until a determination of the amount due defendants on their counterclaim.

By the Court. — Judgment reversed. Cause remanded with directions to vacate and set aside the judgment; and to enter an order for a new trial on defendants' counterclaim. *186a






Addendum

The following opinion was filed January 21, 1944: The respondents have moved for a rehearing. They concede that the judgment should be reversed but contend that the new trial should be limited to certain items of the defendants' counterclaim.

The original opinion was based on the rule stated in Venzkev. Magdanz, 243 Wis. 155, 160, 9 N.W.2d 604. The rule there stated was too broadly applied in the instant case. The defendants' counterclaim for damages in that case arose out of defective workmanship. There are a number of small items in defendants' counterclaim of defects or omissions which would not require the reconstruction of a substantial part of the building. In reference to such items there is applicable the rule that "if the defect can be remedied without reconstructing a substantial part of the building or, as otherwise expressed, without great sacrifice of work or material already wrought into the building, the reasonable cost of correcting the defect should be allowed; if otherwise, the diminished value of the building, on the basis of the contract price, by reason of the defect." Buchholz v. Rosenberg, 163 Wis. 312,314, 156 N.W. 946; J. G. Jansen, Inc., v. Rilling,203 Wis. 193, 198-200, 232 N.W. 887.

What may be regarded as the principal item of defendants' counterclaim is the damages caused by plaintiff's failure to waterproof the outside of the basement walls. Defendants claimed damages in the sum of $1,300; the referee allowed this claim at $315. By reason of the failure to waterproof the outside walls of the basement, it is alleged that damage resulted to the paneling on the wall of one of the rooms in the basement. There is a further claim for damages for failure to install cinders under the basement floor.

The damages in the last three mentioned claims should have been ascertained under the rule of Venzke v. Magdanz, supra. As to all other items of defendants' counterclaim the referee *186b applied the correct rule of damages, and we are of the view that his findings both as to items allowed and disallowed are sustained by the evidence, and that the new trial on defendants' counterclaim should be limited to the claims specifically mentioned where the wrong rule of damages was applied. Respondents' motion for a rehearing is denied without costs. *187

midpage