Judgmеnt was entered for plaintiff, a licensed general contractor, and against defendants in the sum of $12,597 for loss of profits arising from breach of an oral agreement to construct a, one-story shopping center on certain Los Angeles property belonging to defendants as co-owners (tenants in common). Three points,are made on defendants’ appeal from the judgment—first, contrary to the parties’ intentions, the agreement was never reduced to writing and henee no binding agreement resulted; second, the trial court erroneously found that defendant George Maloof while dealing with plaintiff had authority to bind his co-owners;' and finally, the trial court erred in the amount of damages awarded.
Necessarily viewed in a light most favorable to plaintiff-respondent, the evidence reveals among other things that plaintiff was first approached by defendant George Maloof (referred to hereinafter as “George”), and his mother, defendant Annie Maloof, in November of 1965; at that time plaintiff was in the midst of a construction job at a site some eight blocks from defendants’ property. During the conversation which followed, they sought plaintiff’s advice regarding the demolition of certain structures on their land where they proposed to erect a one-story shopping center. A few days *846 later, in response to an inquiry by George, plaintiff indicated he was interested in bidding on the proposed shopping center. Thereafter George delivered to plaintiff two sets' of plans and specifications, together with an “Invitation to Bid” which contained a “Bid Form.” The “Invitation to Bid,” prepared by defendants’ architect at their direction, included the following: “Selected bidder shall execute a contract for construction of the work within five days of notice of selection. ’ ’ The 1 ‘ Bid Form, ’ ’ in turn, provided in pertinent part that “The undersigned further agrees, if awarded the contract, to sign thе contract and to furnish a performance bond.
On January 14, 1966, plaintiff delivered his bid to George upon the form he had been furnished. Thereafter, at meetings held on various dates in January and February, plaintiff and George discussed certain proposed changes in the plans and specifications; revised bids were рrepared and delivered by plaintiff as a result of such meetings. Subsequently, on February 21, George delivered to plaintiff his latest revised plans which included a doughnut shop addition to the center; after reviewing them, on February 25 plaintiff submitted his latest revised bid. On February 27 plaintiff and George met at the latter’s home and agreed that there would be no further changes in the revised plans which were complete and specific as to type and grade of materials. The parties also agreed on the method of compensating plaintiff, the commencement of construction by March 4, 1966, a construction period of 120 days, and the nеcessity of securing a. construction bond.
The following morning (February 28) plaintiff recéived a telephone call from George; during the course of their conversation plaintiff stated that he could do the job for $79,453. To this statement, according to plaintiff, George replied: “If you can do the job for $79,000, you have it.” Plaintiff’s rеjoinder was: “I accept your offer and I thank you very much for the job.” George then told plaintiff to go ahead: “Let’s get on the ball. Let’s get this thing rolling.” Plaintiff replied: ‘ ‘ Fine, I will get right on the phone now and start. ’ ’ Immediately thereafter plaintiff telephoned his concrete man, telling him to come on the job the following day (Mаrch 1); a chemical toilet was also ordered, and calls made by plaintiff to the plumber, electrician, steel man and other subcontractors.
Later that same day (February 28) George telephoned plaintiff to “hold off” until he (George) “ha[d] á completion bond in hand.” Plaintiff then went to a bonding com *847 pany, obtаined the issued completion bond and delivered it to George that evening. 1 At an earlier meeting that same day, it appears that plaintiff also delivered to George a letter stating in part that " I am pleased to be awarded this work and hope to produce a structure we can both be proud to bе associated with. ’ ’
Still later on February 28, plaintiff was again at George’s house. Present for the first time were the remaining defendants. Various questions were asked of plaintiff with reference to plans and specifications. A completed and standard A.I.A. contract was presented' to plaintiff which contained аll the terms and conditions reached at previous meetings. Plaintiff signed, requesting defendants to do the same; they declined to do so. On March 3 plaintiff telephoned George, directing attention to the necessity of commencing construction by March 4; George told plaintiff not to worry as he (George) had obtainеd an extension of time, adding: “Do nothing until you hear from me. ’ ’ Shortly thereafter, while passing the site in question, plaintiff noticed a building under construction; he testified that the same plans and specifications were being followed. The court made a finding (unchallenged by defendants) that the center was eventually completed for the total sum of $77,000, materials of a lesser cost being substituted.
In support of their first contention, defendants cite the decision of this court in
Apablasa
v.
Merritt & Co.,
There is no merit to such argument, likewise rejected in
Clarke
v.
Fiedler,
Likewise unsustainable is defendаnts’ next contention that George lacked the necessary authority “to bind the other co-owners,” the remaining defendants being his mother and two sisters. In this latter regard, preliminarily, the trial court made the finding (not here challenged) that George’s mother and sisters “are inexperienced business individuals, are unfamiliar with plans and specifications, and relied upon the knowledge and experience of defendant, George Malouf [sic]. ’ ’
2
Since' this claim challenges the sufficiency of the evidence that he possessed such authority, we need only determine whether the record contains any substantial evidence to support the findings of the trial court.
(Tomerlin
v.
Canadian Indem. Co.,
Substantial evidence is contained in the record to support the finding of George’s authority, actual or ostensible. The architect (Mr. Hashem) employed by defendаnts to prepare
*850
plans and specifications testified that he was first contacted by Mrs. (Annie) Maloof; that thereafter such plans and specifications were discussed at meetings attended by some or all of the defendants. According to Hashem, “Early in discussion we thought for simplifying the correct owners I will use George’s name, and since then I start putting on the drawing board only George’s name.” Later: “When earlier they told me for simplification to use ‘ George Maloof, ’ I kept using it. That’s all I can say.” Accordingly, the plans and specifications eventually delivered to plaintiff stated that they were “For George Maloof . . . Owner,” and the same was true of the “Invitation to Bid.” Defendant Nellie Maloof testified that she never made complaint that such “Invitation” read “for George,” while defendant Jeanette Ashamalla stated: “We are a family. We know what goes on.” Finally, plaintiff testified that defendant Annie Maloof on one occasion said to him: " George is now the man in this house and he is going to do this.” From the above, and other circumstances unnecessary to set forth, the inference was reasonably deducible that George’s mother and sisters knew that by his conduct generally he was holding himself out as clothed with certain authority and yet remained silent; acсordingly such silence on their part gives rise to
liability. (Marr
v.
Pastal Union Life Ins. Co.,
There is no merit to defendants’ final point that the award of damages was erroneous because of uncertainty as to plaintiff’s cost of performance. While it is provided by section 3301, Civil Code, that “No damages can be recovered for a breach of contract which are not clearly ascеrtainable in both their nature and origin” such provisions have been liberally construed. Thus, it has been repeatedly held that where there is no uncertainty as to the fact of damage, that is, as to its nature, existence or cause, the same certainty as to its amount is not required.
(Tomlinson
v.
Wander Seed & Bulb Co.,
It is also asserted that the trial court failed to deduct the value of plaintiff’s own services on the theory that “this is a part of this cost of performance of which he was relieved by the breach.” (3 Am.Jur., Proof of Facts, p. 613.) No California case is cited for such proposition which is raised for the first time by appellate counsel; if, as it seems, defendants are relying on thе doctrine of mitigation of damages, it is inapplicable to the instant case which does not involve the breach of a contract for personal services.
(Gollaher
v.
Midwood Constr. Co.,
The judgment is affirmed.
Wood, P. J., and Fourt, J., concurred.
Notes
The superintendent of the bonding company testified that on the morning of February 28 he received a phone call from a man identifying himself as George; that George stated he would issue the contract and was being held up by the bond. This witness, when asked on cross-examination whether it was normal procedure to issue a bond for the sum in question ($79,000) “on a purported oral contract,” replied: “Yes, it is. ’ ’
George testified that he was a licensed practicing pharmacist and the holder of a doctorate in pharmacy awarded in 1962 (three years prior to the events in suit).
