Steel Dynamics Columbus, LLC v. Altech Environment USA Corp.Steel Dynamics Columbus, LLC v. Altech Environment USA Corp.
MEMORANDUM OPINION
In August 2010, Steel Dynamics Columbus, LLC (under its former name, Severs-tal Columbus, LLC),
The Court held a three-day bench trial on Steel’s claims for negligence, breach of contract, breach of warranties, and contractual indemnification. At the bench trial, after Steel’s case in chief, the Court granted Altech’s motion for a judgment on partial findings as to Steel’s contractual indemnity claim only. After the presentation of all evidence at trial, the Court took under advisement Altech’s renewed motion for a judgment on Steel’s remaining claims. Upon consideration of the trial evidence and the applicable law, the Court issues this memorandum opinion as its ultimate findings of fact and conclusions of law.
I
Procedural History
On June 30, 2014, Steel filed this action against Altech in the Circuit Court of Lowndes County, Mississippi. Doc. # 2. On August 4, 2014, Altech removed the case to this Court based on 28 U.S.C. § 1332.
On November 6, 2015, Alteeh filed a “Motion for Partial Summary Judgment on the Issue of Contractual Limitation of Remedies.” Doc. # 49. Though denying liability, Alteeh limited its motion to “how ... provisions [in the parties’ purchase contract] limit recoverable damages.” Doc. # 50 at 2. The Court denied Altech’s motion without prejudice, concluding that ruling on only the issue of damages before a trial in which liability would be contested would be inefficient. Doc. # 85 at 2 n.5, 3. The Court further stated that it preferred to consider the issue of damages in view of all facts to be presented at the bench trial
The Court held a bench trial from June 20, 2016, to June 23, 2016. At the close of Steel’s case in chief, Alteeh moved for a judgment on partial findings on all of Steel’s claims, which the Court granted only as to Steel’s contractual indemnity claim.
II
Factual Findings
Steel operates a steel plant in Columbus, Mississippi, that melts scrap metal in an electric arc furnace. Tr. at 45, 90, 93.
MDEQ issued Steel a Title V permit which, among other things, required Steel to install two CEMS. CEMS provide continuous data on the level of monitored pollutants in industrial emissions. Steel’s Title V permit required the installation of the CEMS to monitor levels of four regulated pollutants—Nitrogen Oxides (NO*), Carbon Monoxide (CO), Volatile Organic Compounds (VOCs), and Sulfur Dioxide (S02). Ex. P-1 at §§ 3.B.12-B.19.
A, Alteeh Proposal
In May 2010, Steel, which had no experience with CEMS, solicited bids to pur
Altech’s proposal specified that Altech would supply CEMS that would monitor the pollutants regulated under Steel’s Title V permit. Id, at 28-30, 40.
Under Altech’s proposal, Altech would begin a “7-Day Drift Test” on the CEMS within five to seven days after “Equipment Startup” and, within a year after that, a more extensive “Relative Accuracy Test Audit” (“RATA”) required by Steel’s Title V- permit. Id. at 41, 45, 49; Tr. at 526. The proposal included a one year maintenance contract, which included quarterly maintenance, as well as support services for startup, RATA testing, and “regulatory approval.” Ex. P-2 at 29-30, 46.
The proposal also specified installation and maintenance requirements to be met by Steel and Altech. Regarding installation, the CEMS were to be mounted on a wall in a temperature-controlled room provided by Steel. Id, at 26, 41. Regarding maintenance, the proposal specified quarterly, semi-annually, and yearly maintenance, with the first year of maintenance to be performed by Altech under a proposed quarterly maintenance contract. Id. at 45. Every quarter, the CEMS were to' undergo a performance test known as a “Calibration Gas Audit” and preventative maintenance, including servicing filters in the probe assembly.
B. CEMS Purchase
On August 17, 2010, Steel issued a purchase order to Altech in the amount of $447,610.20 for two CEMS. Ex. P-3. The purchase order, which referred to Altech’s proposal both by its identifying number and by specific numbered items, included a one year quarterly maintenance contract, a DAS computer with CEMLink5™ software from Contec, and a quality assurance plan for regulatory approval. Id.; Ex. P-2 at 28-30.' When Steel ordered the two CEMS, “[Altech] understood that [Steel] intended to use the CEMS units to monitor emissions [from its steel plant] in compliance 'with the Title V Permit that MDEQ issued to [Steel].” Doc. #86 at § 9.a.(5), (6). . .
The undated “Goods and Services: Terms and Conditions of Purchase” (“Terms”) include two sections relating to liability.
The Terms include two sections pertaining to remedies. One limits Steel’s recourse for breach of the express warranty to repair and/or replacement of the CEMS at Altech’s option.
C. CEMS Operating History
The first CEMS was installed between January 25 and January 27, 2011, with Altech supplying the DAS computer loaded with software. Ex. P-9 at 1; Tr. at 479, 551. In June 2011, Altech prepared specifically for Steel an operating manual setting forth maintenance requirements for CEMS. Tr. at 394; Ex. D-7 at 21253; Ex. P -2 at 21.
The second OEMS was installed on July 22. Ex. P-9 at 13; Tr. at 496. Both of the installed CEMS included the same three basic components: (1) a probe assembly, which is an umbilical that feeds airflow sample into the analyzer, fitted at both ends with filters; (2) a flow monitor, which measures total airflow volume; and (3) an analyzer, described as the “heart” of the CEMS, which measures the concentrations of pollutants. Tr. at 392-93, 584; Ex. D-7 at 21259, 21263.
1. 2011
During installation of the first OEMS, - there were problems relating to inaccurate configuration data provided by Steel but by mid-March, the analyzers had been “re-ranged” with updated data Steel provided. Ex. P-6 at 23684; Ex. P-9 at 1-2.
By mid-October, the analyzer in the second CEMS could not measure S02 or NO*, the DAS computer was “not working,” and all three temperature controllers in the first CEMS malfunctioned and had to be replaced. Id, at 14. Similar problems continued throughout 2011. Id. at 15-16; Ex. P-6 at 24162.
2. 2012
Throughout 2012, there were multiple service visits and persistent problems with the analyzers in both CEMS and their shared DAS computer. See, e.g., Ex. P-9 at 20, 56; Ex. P-7 at 24800, 24887, 24895. Both CEMS indicated “[thousands] of alarms daily.” Ex. P-7 at 24378. By the end of June, Steel bought a new computer and prepared to install a new version of software from Contec provided by Altech. Ex. D-31 at 2718-20.
Altech conducted nine more service visits in 2012. Ex. P-9 at 20-84. Though the Altech engineers were able to calibrate the CEMS for most pollutants by the end of each visit, after the engineers left, problems would recur. By April, “[tjhings look[ed] ugly;” there were still “[m]ultiple calibration failures [and] [Repeatability ... [was] an issue.” Ex. P-7 at 24455.
By late August, the first CEMS passed part of a 7-Day Drift Test. Id. at 24820. But, performance testing of the second CEMS remained “very unstable on all calibrations.” Id. According to one Altech engineer, to “truly fix” the problems with the second CEMS, software in the analyzer had to be downloaded from the on-site CEMS, transferred to a test unit at Al-tech, repaired, and then re-loaded back onto the on-site CEMS. Id. at 24825. There is no evidence this repair was ever performed. On August 21, 2012, a vice president for Steel e-mailed Mike Church, an Altech support manager, stating, “We still have critical issues .... Time is long past when these things should be working accurately and reliably.” Id. at 24818.
3. 2013
Into 2013, Steel employees and Altech engineers struggled to identify or correct continuing problems, including recurrent issues with analyzers, temperature controllers, and the computer. Computer problems came to a head in 2013 when, on January 10, Contec notified Altech that “[t]here are major problems with the databases for 2012 [and] 2011.” Ex. P-8 at 24992. After learning from Contec about the database problems, on January 30, Church e-mailed Steel that the DAS computer was corrupted. Tr. at 479-80; Ex. P-8 at 663. Mark Chamberlin, an Altech technical support manager, described the computer as “faulty” in a February 5 email to Steel. Ex. P-8 at 25051, 25119.
In late March, Altech purchased a replacement computer and shipped it to Steel. Id. at 10; Ex. P-14 at 4974-79.
On June 28, 2013, MDEQ issued Steel a Notice of Violation. Ex. P-12 (unnumbered at 12-14). The Notice cited two violations of Steel’s Title V Permit: (1) Steel reported the CEMS were .installed but the CEMS could not function longer than twelve to seventy-two hours at a time and could not pass a RATA, and (2) Steel failed to report CEMS malfunctions. Id. After meeting with MDEQ, Steel retained a different CEMS vendor to conduct an ambient air test on the Altech CEMS. Tr. at 182-83,343. .
For the ambient air test, the CEMS were removed from the airflow of the steel plant and placed outdoors for two to three weeks and were then observed for whether they could accurately detect pollutant concentrations in calibration gasses each morning. Id. at 592-93. Regarding NOx—a regulated pollutant with which both CEMS had , often struggled—the systems “failed pretty badly.” Id. Though the CEMS worked for some pollutants, the analyzer component responsible for measuring NOx “failed about every way you could fail. The NOx wasn’t working.” Id. at 593. Steel gave up on the Altech CEMS because it considered the results of the ambient air test to be a failure. Id. at 183, 343. Steel and MDEQ subsequently negotiated a fíne of $135,000, which Steel paid, with Steel agreeing to contract with a third party to conduct monthly emissions testing until Steel installed working CEMS. Id. at 193-94.
Ill
Liability
Steel asserts three grounds for liability: (1) negligence, (2) breach of implied warranties, and (3) breach of contract.
A. Negligence
The elements of negligence are: (1) duty, (2) breach, (3) factual and proximate cause, and (4) damage. Duckworth v. Warren,
Steel, citing Montgomery v. Citi-Mortgage, Inc.,
B. Breach of Implied Warranties— Contractual Disclaimer
Turning to Steel’s claims for breach of implied warranties, Altech argues that such claims are barred by the Terms.
The express language of the Terms bars all implied warranty claims. Ex. P-4 at § 14. Absent fraud, illegality, or mutual mistake, this Court cannot “modify, add to, or subtract from the terms of a contract validly executed between two parties.” Elchos v. Haas,
As relevant here, two Mississippi statutes concern the extent to which a contract for the sale of goods may limit liability or remedies under an. implied warranty: § 11-7-18 and § 75-2-719(4) of the Mississippi Code.
Steel concedes that it is a non-consumer and that the OEMS are non-consumer goods. Doc. # 49-6 at 1. Accordingly, there is no dispute that § 11-7-18 is inapplicable in this case. Rather, Steel relies on § 75-2-719(4) for the proposition that the disclaimer of implied warranty claims is invalid. The pre-amended version of § 75-2T-719(4) applicable in this case
Any limitation of remedies which would deprive the buyer of a remedy to which he may be entitled for breach of an implied warranty of merchantability or fitness for a particular purpose shall be prohibited. The provisions ,of ¡this subsection do not apply to computer hardware, computer software, and services performed on computer- hardware and computer software, which are sold between merchants.
Miss. Code Ann. § 75-2-719(4) (2011) (emphasis added) (effective July 1,1998). Steel argues that “remedies” includes liability and that as a result, § 75-2-719(4) prohibits contract terms that bar implied warranty claims. Doc. # 58 at 4. Altech contends that “remedies” is unambiguous and does not include liability. Doc. # 50 at 15. Alternatively, Altech urges that § 75-2-719(4) must be interpreted in a way that gives effect to the words “in a sale to a consumer ... of consumer goods” in § 11-7-18, as amended. Doc. # 63 at 3.
1. Mississippi Supreme Court precedent
In Massey-Ferguson, Inc. v. Evans, the Mississippi Supreme Court held that a buyer of farm equipment could maintain a consequential damages claim for breach of implied warranty even though the purchase terms precluded incidental and consequential damages and the sale occurred on an “as is ... basis without any warranty, express or implied.”
In its analysis, the Massey-Ferguson court did not state which statute prohibited what. Both by their express terms prohibit limitation of remedies. While the court could have meant that § 11-7-18 “further emphasize[d]” a prohibition on disclaimers of liability in §. 75-2-719(4), it could have meant that § 11-7-18 emphasized § 75-2-19(4)’s express prohibition of limitations on remedies. Thus, it- is! far from clear that the' court held § 75-2-719(4) impliedly prohibited' waiver or disclaimer of implied warranties on its own when the language it quoted from § 11-7-18 expressly did the same thing. In any event, once § 11-7-18 became limited only to consumer sales of goods, Massey-Ferguson became distinguishable from non-
The Mississippi Supreme Court has never prohibited an implied warranty disclaimer in sales of goods on the basis of § 75-2-719(4) alone.
2. Erie guess
Because no holding of the Mississippi Supreme Court is on point, this Court must predict whether that court would hold that the pre-amended § 75-2-719(4) renders unenforceable contract terms barring implied warranty claims in non-consumer sales of goods. See McCaig v. Wells Fargo Bank (Tex.), N.A.,
Two Mississippi Court of Appeals cases mention § 75-2-719(4) in the context of disclaimer of implied warranties—Settlemires v. Jones,
3. Statutory construction of § 75-2-719(4)
The Court next must decide whether the Mississippi Supreme Court would hold that § 75-2-719(4), as it existed at the time of the contract here, barred implied warranty disclaimers in non-consumer sales. As this is a diversity case, the Court will interpret Mississippi statutes according to Mississippi’s rules of statutory construction. United Rentals Nw., Inc. v. Yearout Mech., Inc.,
Under Mississippi law, a court’s goal in construing a statute is to give effect to the intent of the Mississippi legislature. Lawson v. Honeywell Int’l, Inc.,
If an ambiguity exists, a court must “turn to the principles of statutory construction.” Oktibbeha Cty. Hosp. v. Miss. State Dep’t of Health,
Neither the pre-amended § 75-2-719(4) nor the definitions section of Mississippi’s U.C.C. define “remedies.” Miss. Code Ann. §§ 75-2-103, 75-2-719(4) (2010). Thus, the Court must first review the word’s ordinary meaning.
Black’s Law Dictionary defines “remedy” as “[t]he means of enforcing a right or preventing or redressing a wrong; legal or equitable relief.” Remedy, Black’s Law Dictionary (10th ed. 2014). The definition includes an action and an object. The action is “redressing” or “enforcing,” and the object is a “right” or “wrong.” There are “settled distinctions between rights accruing under contracts and remedies for their enforcement.” Coffman v. Bank of Ky.,
Other principles of statutory interpretation lead to the same result. Even supposing “remedies” is ambiguous, the Court cannot adopt Steel’s proposed interpretation. To do so would fail to give effect to all statutory language and meaning to all amending words. Steel would have this Court hold that § 11-7-18’s-2010 amendment did virtually nothing. Section 11-7-18 prohibits contract terms that bar implied warranty claims. Its 2010 amendment limited that prohibition to “a sale to a consumer ... of consumer goods.” Instead of actually limiting this prohibition to consumer sales, Steel argues that § 75-2-719(4) still preserved implied warranties in almost all non-consumer sales, except for sales between merchants of computer hardware, software, and services on such. If so, § 11-7-18’s amendment would have been largely pointless. Put differently, Steel implies that § 11-7-18’s broad amending language only affected computer-related sales between merchants. At bottom, Steel wants this Court to read the two statutes as almost entirely co-exten
Section 75-2-719(4) covers only disclaimer of remedies for beach of implied warranties and does not prohibit disclaimer of liability for such warranties. No persuasive authority indicates that the Mississippi. Supreme Court would hold otherwise—consequently, § 75-2-719(4) does not prohibit the Terms barring the implied warranty claims Steel asserts. Steel’s implied warranty claims are barred by the Terms and therefore must fail.
C. Breach of Contractual Warranty
Steel argues that Altech breached its contractual warranty in two ways: .(1) by delivering CEMS that “never became operational” and (2) by delivering CEMS that failed to comply with the express warranty in the Terms that the CEMS “shall be of good quality and free from defects ... [and] shall be suitable and sufficient for their specified purpose.”
The parties stipulated that when Steel ordered the CEMS, “[Altech] understood that [Steel] intended to use the. CEMS units to monitor emissions .[from its Columbus, Mississippi, steel plant] in compliance with the Title V permit that MDEQ issued to [Steel].” Doc. #86 at § 9.a.(5), (6). To do so is therefore the “specified purpose” of the CEMS.
From installation, the CEMS suffered recurrent malfunctions, about which Steel frequently notified Altech. Tr. at 343; see generally Exs. P-5-8. Soon after installation, both CEMS struggled to measure . NOx, a pollutant regulated under Steel’s Title V permit, which suitable and sufficient CEMS must have been able to measure consistently. Additionally, the computer—an essential component of the
While Steel improperly installed the CEMS and initially supplied Altech with inaccurate data,
Damages
Steel seeks $424,270.20 in direct damages; $307,704.97 in consequential damages; and $259,024.93 in incidental damages. Doc. # 97 at 26. As an initial matter, Altech argues that Steel can recover no damages because Steel failed to give notice to Altech of breach.
A. Notice of Breach
Section 75-2-607(3)(a) of the Mississippi U.C.C. provides that “[w]here a ténder has been accepted ... the buyer must within a reasonable time after he discovers or should have discovered any breach notify the seller of breach or be barred from any remedy.” Adequate notice need not be a “specific claim for damages or an assertion of legal rights.” Miss. Chem. Corp. v. Dresser-Rand Co.,
When, as here, a buyer is a non-consumer, adequate notice requires the buyer, through his “conduct ... taken as a whole,” to notify the seller that he claims the transaction involves a breach. Id. at 364 (quoting E. Air Lines, Inc.,
Two messages from Steel to Altech together constitute timely and adequate notice under § 2-607(3)(a): (1) the August 21, 2012, e-mail from a Steel vice president to Church, stating, “We still have critical issues .... Time is long past when these things should be working accurately and reliably;” and (2) the January 25, 2013, email from Vogel to Church and Chamber-lin, stating that Steel and Altech would have to “discuss” ending the CEMS warranty period because Steel “still [did] not have a usable system.” Each of these emails timely and reasonably communicated Steel’s dissatisfaction and put Altech on notice that Steel considered the CEMS transaction to involve a breach of Altech’s express warranty that the CEMS would be suitable and sufficient for monitoring pollutants in compliance with the Title V permit.
Even if the e-mails were insufficient on their own, they, together with Steel’s other conduct, were more than adequate to notify Altech that Steel believed the contract to have been breached;. First, Steel sent Altech numerous e-mails, fairly regularly, beginning from installation of the first CEMS, to complain about malfunctions. Second, in response to these continual complaints, Altech provided warranty parts and services; Steel’s continuing assertion of dissatisfaction therefore implied that it believed the CEMS remained in breach of their warranty. These facts would have clearly indicated to Altech that Steel’s August 2012 and January 2013 emails each amounted to an assertion of breach. Third, as noted above, the specified purpose of the CEMS was Title V compliance, and credible, unrebútted testimony at trial established that Steel made clear to Altech in numerous conversations over several years that problems with th,e CEMS were resulting in Steel’s noncompliance with its Title V permit. Tr. at 343. Under these circumstances, Steel satisfied the purpose of-notice—which, as relevant here, is to promote settlement, commercial good faith, and mitigation and cure. Steel’s 2013 e-mail came at the end of the parties’ joint efforts to cure and mitigate and invited “discussion]” on Altech’s contractual obligations, the issue Steel later raised in this action.
B. Damages Limitations
Altech alternatively argues that Steel’s recoverable damages are limited by the three damages limitations clauses in the Terms: one that limits remedies for breach of the express warranty to repair and/or .replacement of the CEMS at Al-tech’s option, a second that limits damages to the -CEMS purchase price, and the third that precludes consequential and incidental damages.
1. Limitation to purchase price
As will be explained below, Steel’s recoverable damages are $83,320.27—less than the $447,610.20 purchase price of the CEMS. Consequently, thé applicability of the provision in the Terms limiting recoverable damages to the CEMS purchase price is not at issue.
2. Limitation to repair and/or replacement
The express warranty contained in the Terms is an exclusive limited warranty, providing as a remedy only repair and/or replacement of goods at Altech’s option and only if Steel provides notice within a specified time. Steel argues that this limitation is inapplicable in this case because the exclusive repair-and/or-replace warranty failed of its essential purpose.
Under § 75-2-719(2) of the Mississippi U.C.C., “[w]here circumstances cause an exclusive or limited remedy to fail of its essential purpose, remedy may be had as provided in [the] code.” In this regard, an exclusive limited warranty “presupposes ... that the warrantor will fulfill his warranty.” Ford Motor Co. v. Fairley,
Here, the exclusive repair-and/or-replace warranty failed of its essential purpose. Despite over three years of remedial efforts by Altech, the critical malfunctions of the CEMS were never corrected, and the CEMS remained unsuitable and insufficient for their specified purpose—monitoring the pollutants in Steel’s Title V permit. Thus, Altech failed to deliver CEMS conforming to the contractual warranty within a reasonable time, depriving Steel of its bargained-for benefit. See Chatlos Sys., Inc. v. Nat’l Cash Register Corp.,
3. Preclusion of consequential and incidental damages
Altech insists that the separate consequential and incidental damages limitation in the Terms precludes such damages in this case. Yet, reading the contractual provisions as a whole—including the stipulated purpose of the CEMS appearing in the proposal which, together with the Terms, comprise the governing contract—the Court concludes that the damages • limitation “presuppose[d] .,. that the warrantor [would] fulfill his warranty” as much as the limited warranty did. See Riley v. Ford Motor Co.,
C. Calculation of Damages
“Damages recovered in any case must be shown with reasonable certainty, both as to their nature' and in respect to cause from which they proceed.” Mo. Bag Co. v. Chem. Delinting Co.,
There is no dispute that Steel accepted each CEMS at its installation and that Steel never revoked or attempted to revoke its acceptance. See Tr. at 315 (Altech CEMS remain at Steel’s Columbus, Mississippi, steel plant). Where, as here, an exclusive limited contractual warranty fails of its essential purpose and the buyer has not revoked acceptance, “the appropriate UCC remedy is found in the provisions covering damages for breach of warranty”—that is, U.C.C. § 2-714(2) and (3). Delhomme Indus., Inc. v. Houston Beechcraft, Inc.,
Under § 75-2-714(2), “[t]he measure of damages for breach of warranty is the difference at the time and place of acceptance between the value of the goods accepted and the value they would have had if they had been as warranted, unless special circumstance show proximate damages of a different amount.” The buyer bears the burden of producing evidence proving the difference in value between the goods as accepted and the goods as warranted. Gast v. Rogers-Dingus Chevrolet,
Steel does not offer any evidence of the CEMS’ value at the time of acceptance.
Steel relies on Fedders in seeking a refund of .the CEMS purchase price. Doc. # 97 at 25. However, not only does that case require a finding of worthlessness, it also held that it was “not unreasonable” for a seller to refuse to replace an “entire” malfunctioning heat pump—consisting of an outdoor condenser and an indoor evaporator—where there was evidence only that the outdoor unit was the cause of the heat pump’s malfunctions. Fedders,
Thus, it is far from clear that the CEMS were worthless. For ’ instance,1 if the CEMS’ malfunctions were caused only by one defective component, crucial but inexpensive to replace, the units would have retained significant value. Though it is clear that the CEMS were unsuitable and insufficient for their specified purpose, Steel presented no evidence attempting to explain the cause of the analyzer malfunctions or the impact of the DAS computer malfunctions op the value of the CEMS. Such evidence is particularly important here because the CEMS are a combination of subsystems that can be ‘reconfigured with other subsystems to achieve the same intended purpose.
Thus, under § 75-2-714(2), Steel failed to produce sufficient evidence showing a reasonably certain difference in value of the CEMS as accepted and as warranted; consequently, Steel cannot recover direct damages for Altech’s breach of contractual warranty. Gast,
2. Consequential and incidental damages
Section 75-2-714(3) provides for ' incidental and consequential damages under § 76-2-715 “in a proper case.” Where, as here, an exclusive limited contractual remedy fails of its essential purpose, a subsequent action is a “proper case” for recovery of incidental and consequential damages, See Mercury Marine,
a. Consequential damages
As relevant here, consequential damages include “[a]ny loss resulting from general or particular requirements and needs of which the seller at the time of contracting had reason to know and which could not reasonably be prevented by cover or otherwise.” Miss. Code Ann. § 75-2-715(2)(a). In this case, Steel seeks two categories of consequential damages: the MDEQ fine and attorney’s fees in dealing with MDEQ.
In calculating damages recoverable for a breach of contract, the plaintiff must “trace” the damages “directly to the breach of contract and make them definite enough to comply with the governing rules of law.” Ammons v. Wilson & Co.,
Steel argues that its attorney, Michael Capíes—whom Steel retained to negotiate the MDEQ fine—testified that none of the other violations cited by MDEQ other than the one for failing to operate adequate CEMS would typically have resulted in fines. Id. at 363-65. Capíes never so testified, and even if he had, such testimony would be insufficient to establish that the other violations could have had no effect on the overall fine amount in this case.
Nevertheless, Steel failed to prove the extent to which, in this case, MDEQ disregarded the other violations in assessing its fine. The Notice of Violation includes a violation for failing to report CEMS malfunctions; clearly such cannot be Altech’s fault, which Steel concedes. Id. at 364. More significant, the item in the Notice of Violation for failing to report malfunctions quotes language from Steel’s Title V permit that “if the permittee demonstrates through properly signed contemporaneous operating logs, or other relevant evidence” an operational “upset” of the CEMS and the proper response to such upset, “[t]he occurrence of an upset constitutes an affirmative defense to an'enforcement action.” Ex. P-12 (unnumbered at 13-14). Given this, even to the extent CEMS-related, the MDEQ fine may be traceable, at least in part, to Steel’s omissions. Regardless, Steel cannot trace the MDEQ fine wholly or partially to Altech’s breach in any reasonably certain amount; its damages claim for the MDEQ fine thus fails. Unable to attribute the MDEQ fine to Altech’s breach, Steel is likewise unable to so attribute its attorney’s fees in dealing with MDEQ, and its damages claim for such amount must also fail.
As relevant here, incidental damages include “any commercially reasonable charges, expenses or commissions in connection with effecting cover and any other reasonable expense incident to the delay or other breach.”
Initially, though Steel presented ample evidence that it purchased replacement CEMS, it presented no evidence of the cost of such replacement. Accordingly, Steel may not recover as incidental damages extra expenses incurred in effecting cover. That leaves only “any other reasonable expense incident to ... breach.” In this regard, Steel seeks $259,024.43 in such damages.
Steel may recover the amount it paid to a third party to conduct emissions testing that would have been accomplished by the CEMS had they been delivered as warranted. This amount includes only the cost of such testing on the two steel production lines in which an Altech CEMS was installed. Steel was invoiced for seven such tests occurring when a CEMS should have been operational, at a cost of $2,100 per test of only the four regulated pollutants. Ex. P-14 at 4899-905. Accordingly, for third party emissions testing, Steel may recover $14,700.
Steel may recover the costs it incurred contracting with Contec and its vendor of replacement CEMS to investigate and attempt to remedy the malfunctions of the Altech CEMS. For this, Steel may recover $30,513.89. Id. at 4932-33, 4935-39; Tr. at 196,199. Finally, Steel may recover all the costs it paid to Altech to fund Altech’s failed remedial efforts that Altech chose not to cover under warranty—$38,006.38. Ex. P-14 at 4956-60, 4964-72, 4981-84.
Excluded from the damages computation are three invoices from Altech introduced into evidence by Steel: one for training, another for extra monitors to go along with a replacement computer Altech provided under warranty, and a third for a “milestone payment.” Id. at 4962, 4974, 4983; Ex. P-8 at 25119. Steel has not shown by a preponderance of the evidence that any of these invoices were defect-related or defect-caused.
Also excluded are $202 listed in one invoice for two micron filters, and $96 and $224 listed in another invoice for particulate and coalescing filters, respectively, which' likely were either maintenance items or necessary because of the operating environment of Steel’s plant and not because of CEMS defects. Ex. P-14 at 4966, 4981; Tr. at 572.
Y
Conclusion
In its amended complaint, Steel asserts claims for contractual indemnity, negligence, breach of implied warranty of merchantability, breach of implied warranty of fitness for a particular purpose, and breach of contractual warranty. The contractual indemnity claim was dismissed with prejudice on Altech’s ore tenus motion for judgment on partial findings at trial. For the reasons above,' Altech’s ore tenus motion for judgment on Steel’s remaining claims is GRANTED in Part and DENIED in Part. The motion is GRANTED such that Steel’s claims for negligence, breach of implied warranty of merchantability, and breach of implied warranty of fitness for a particular purpose are DIS» MISSED with prejudice; the motion is otherwise DENIED. Steel is awarded $83,320.27 on its contractual warranty claim. A separate final judgment will issue.
SO ORDERED, this 31st day of March, 2017.
Notes
. After Severstal filed this action and Altech removed the action to this Court, Severstal changed its name to Steel Dynamics Columbus, LLC. On October 2, 2014, Severstal filed an unopposed motion to amend the style of this case to reflect its new name, which United States Magistrate Judge David A. Sanders granted on October 14, 2014. Doc. #11; Doc. # 12. For ease of reference, this opinion will refer to the plaintiff at all times as "Steel.”
. On May 31, 2016, and on June 7, 2016, the Court ordered Altech to show cause why this case should not be dismissed due to the absence of complete diversity under 28 U.S.C. § 1332. Doc. # 73; Doc. # 75. In response, on June 3, 2016, and June 8, 2016, Altech filed motions for leave to amend the jurisdictional allegations of its notice of removal. Doc. # 74; Doc. # 76. Because Altech attached to its second motion to amend evidence that this Court has jurisdiction over this case under 28 U.S.C. § 1332(a)(2), the Court granted Altech leave to amend its removal notice. Doc. #81. Altech filed a supple
. In the amended complaint, Steel's breach of contract claim is titled, “Breach of Contract/Contractual Indemnification,” consisting of a contractual warranty and a contractual indemnity claim. Doc. # 13 at ¶ 24.
. Steel never demanded a jury trial in this Court or in state court pre-removal.
. Regarding its contractual indemnity claim, Steel offered no evidence of (1) an allegation of property damage or personal or bodily injury; (2) any claim, loss, damage, or expense relating to such damage or injury; or (3) any manifest intent of the parties that the relevant indemnity provision would be so broad as to include the particular fine levied by MDEQ in this case. Without such facts, the Court could not conclude that Steel’s alleged damages were covered by the relevant indemnity provisions at issue. The Court rejected Steel's sole argument—that all regulatory penalties under the Clean Air Act constitute a third party claim for personal injury and property damage. Tr. at 353. Had the Court not dismissed the contractual indemnity claim at trial, it would not have survived. The indemnity provisions require a finding of Al-tech's negligence and, as explained below, Steel's negligence claim fails.
.The trial transcript, Doc. # 94, will be cited as "Tr.”
. Citations to pages of trial exhibits will generally be to the bates numbers on the exhibits,
. If the computer is inoperable, the CEMS cannot work properly. Tr. at 600.
. The CEMS operating manual specifies quarterly filter service. Ex. D-7 at 21272. Yet, an Altech technical support .manager, Mark Chamberlin, twice testified that he "believe[ed]” that the manual specifies a monthly “filter check.” Tr. at 394, 431-32. In this regard, Chamberlin's testimony is incredible to the extent inconsistent with the manual, which Chamberlin testified contained the relevant maintenance requirements.
.The parties do not dispute that this document represents an enforceable agreement. Altech’s proposal references "Altech’s standard terms and conditions.” Ex. P-2 at 27, 31. However, it appears the Terms may,have resulted from some negotiations of the standard terms and conditions.
.“If Supplier breaches its-warranty obligations ..,, Supplier shall, at its option, repair and/or replace (FOB Jobsite) any of the Goods which breach this Warranty if written notice of' such breach is given within twelve (12) months after startup or eighteen (18) months after delivery, -whichever occurs first.” Ex. P-4 at § 14. Steel accepted the notice period as set forth in the Terms. Doc. #78 at 14. However, a longer notice'period of the earlier of twenty-four months after startup or thirty months after delivery is spec- . ified in the proposal. Ex. P-2 at 31-. The purchase order referenced the proposal and, consistent with the longer notice period in the proposal, Altech notified Steel in December of 2013 that its warranties had expired as calculated by two years from alleged startup dates. Ex. P-3 at 1; Ex. P-8 at 25:751; Tr. at 178-79. Nevertheless, the length of the notice period in the express warranty is of no consequence here because, as explained below, the express warranty fails of it's essential purpose.
. "Except for Supplier’s, indemnity obligations, in no event shall Supplier’s liability to Buyer exceed the Purchase Price whether attributable to contract, warranty, tort (including negligence), strict liability, or otherwise. In addition, in no event shall Supplier be liable for special, indirect, incidental, consequential, or punitive damages whether attributable to contract, warranty, tort (including negligence), strict liability or otherwise.” Ex. P-4 at § 27. •
. The March 10, 2011, service report indicates that. Altech re-ranged the S02 and CO according to the updated data but not- the NOx.
. Altech stipulated to the authenticity of P-14, Steel’s exhibit collecting invoices for CEMS-related expenses, and made no objection to its admission at trial. Doc. # 86 at § 10.a; Tr. at 81.
. Steel also asserts an express warranty claim, in support of which it points only to § 14 of the Terms, which disclaims any express warranty other than the one it sets forth. Doc. # 78 at 14; Doc. # 97 at 31; Ex. P-4 at § 14. This is not a case in which Steel, relying on § 2-3:13(l)(a) of Mississippi’s Uniform Commercial Code—which describes an express warranty as “[a]ny affirmation of fact or promise made by the seller to the buyer which relates to the goods and becomes part of the basis of the bargain”—points to statements Altech made outside of the 'Terms to establish the existence of an express warranty. As such, Steel’s express warranty claim is subsumed by its claim for contractual warranty included in its breach of contract claim.
. Steel posited in- its closing arguments at trial that Altech failed to subject the CEMS to proper quality control (a claim contested at trial) and sent an inexperienced engineer to start-up the second CEMS. Tr. at 473-74, 630. However, Steel offered no evidence either of the tasks the engineer shirked or carelessly attempted or of the steps in Altech’s quality control that were missing or improperly carried out. Indeed, Steel’s entire evidence for both claims is a single e-mail too vague to support a finding even that there was any relevant issue at all. Ex. P-6 at 11. Consequently, Steel fails to establish breach even if it identified k proper duty. See, e.g., Couch v. City of D'Iberville,
. Section 75-2-719(4) is a non-standard addition to Article 2, § 719, of the Model Uniform Commercial Code. See Uniform Commercial Code § 2-719 & cmt. (Am. Law Inst. & Unif. Law Comm’n 2014). It is unique to Mississippi. Powers v. Lycoming Engines,
. Effective July 1, 2013, § 75-2-719(4) was also amended so that it now applies only to consumer sales of goods. However, Mississippi courts have “continuously followed the rule that statutes will be construed to have a prospective operation only, unless a contrary intention is manifested by the clearest and most positive expression.” Hudson v. Moon,
. See Fedders Corp. v. Boatright,
. Steel cited Patches Farms, Inc. v. Thompson Mach. Commerce Corp., No. 4:06-CV-163,
. As explained above, Steel also asserted a breach of contractual indemnity claim, which was orally dismissed by judgment on partial findings at trial.
.This conclusion is buttressed to the extent it is consistent with the prior proposal, which the purchase order specifically references, both generally and by numbered item. See Miss. Code Ann. § 75-l-303(d) ("A ... course of dealing between the parties ... is relevant in ascertaining the meaning of the parties’ agreement, may give particular meaning to specific terms of the agreement, and may supplement or qualify the terms of the agreement.”); Earman Oil Co. v. Burroughs Corp.,
. Steel was "partly responsible” for. problems relating to installation, according to Anna Chappell, Steel's, testifying corporate representative. Tr. at 271-72. These installation problems .included failing to mount the CEMS' in a properly air-conditioned room and supplying Altech with inaccurate data needed to configure the systems. Id. at 245-46. Steel was also' responsible for certain problems related to maintenance, including improperly connecting bottles of calibration gas (pollutants of known concentration used to test and calibrate the analyzers), which caused the bottles to leak. Some such maintenance problems, however, caused no damage 'to the CEMS and none involved the analyzers themselves or the DAS computer. Id. at 280-82¡ Ex. D-30 at 4471-73,
. Church testified that there was a third configuration change but he also testified that he lacked knowledge of the change or configuration matters generally, and he never testified that the first data update was inaccurate. Tr. at 515-16. To the extent Church suggests Altech’s updated data was also ■ inaccürate, such testimony is incredible. .Generally, to the extent Church's trial testimony sought to explain all problems with the CEMS—especially those related to the computer—as unavoidable or the fault of .Steel, it was not credible. See, e.g., id. at 539 ("There is [sip],always DAS issues. Q[:] Two years later? A[:] Sure.”); id. at 540-41 (“[Altech is] telling Contec, ‘We still have problems with the DAS logic ....’ So that’s not the' plant's fault, is it? A[:] Not the plant’s fault.... Well, it could be. It depends ■ on if somebody was messing with the DAS, pushing buttons. Yeah, it could be actually.”).
.The same expert, designated by Altech, credibly concluded that problems with the computer software were: Altech's responsibility and that recurring issues related to the .analyzers—especially to one of .two main analyzer components called the "CLD,” which measured NOx—were only partially related to maintenance. Tr. at 588-89, 593, 606, Regarding the computer issues, Chamberlin . admitted, at trial that the issues were "recurring," and Church, who was extensively involved with Altech’s remedial efforts, admitted that such issues were not "plant maintenance issue[s].” Id. at 488, 539. Thus, it appears the malfunctions in the originally-shipped computer were most likely caused by defective software installed by Altech. Id. at 573-74, 606. .Though the precise,cause of the analyzer malfunctions cannot be determined, the cause may have been related to the software defects and in any event were only partially related to maintenance. Ex. P-8 at 17; Tr. at 580, 588,
. Accord T. J. Stevenson, 629 F.2d at 361 (holding notice under § 2-607(3)(a) "must be evaluated from the perspective of the policies which it seeks to encourage: compromise by the parties; and conduct within the bounds of commercial good faith.”); E. Air Lines, 532 ■ F.2d at 972 (“Early warning permits the seller to investigate the claim while the facts are fresh, avoid the defect in the future, minimize his damages, or perhaps assert a timely claim of his own against third parties.”).
. Consequently, this case is distinguishable from C.R. Daniels, Inc. v. Yazoo Mfg. Co.,
. Steel argues that the CEMS were worthless yet also admits—as Vogel testified—that it reused $23,340 in components from the ■Altech CEMS in new; operational CEMS, Doc. # 97 at 25-26; Tr. at 311.
. Steel never designated Capíes as an expert witness. To the extent Capíes would have testified that, in his opinion, MDEQ did not consider such violations in choosing the fine amount in this case, such would be improper lay opinion. United States v. Riddle,
. As described in § 75-2-712(1), "the buyer may ‘cover’ by making in good faith and without unreasonable delay any reasonable purchase of or contract to purchase goods in substitution for those due from the seller.”
. Steel seeks an additional fifty cents in its proposed findings and conclusions; however, this appears to reflect an arithmetic error. Although Steel introduced several purchase orders among invoices of its claimed incidental expenses, Steel offered testimony that only a list of such invoices represents “CEMS expenses that Steel Dynamics paid above and beyond the initial purchase of the CEMS units.” Tr. at 194.