State v. Robin Operating Corp.State v. Robin Operating Corp.
Note: The provided document consists of multiple fragments of different legal opinions. Following the “Multi-Opinion Documents” rule, I am converting only the first complete MAIN opinion presented. In this case, the first complete opinion is the one regarding ROC (Robin Operating Corporation) starting on page 945 and ending on page 947. The text appearing on page 944 belongs to the end of a previous case and is excluded as per instructions.
The instant appeal in this
ROC first argues that Supreme Court violated the law of the case doctrine in dismissing its cross claims against the Artco defendants. It relies on a January 2003 Supreme Court order granting plaintiff‘s motion for summary judgment against ROC, as owner, and Artco Properties, as lessee of the property at the time the spill was discovered, and holding that those defendants were jointly and severally liable to plaintiff for past and future remediation costs incurred by plaintiff in relation to the petroleum spill. In a third prior appeal involving this action, this Court affirmed that order (3 AD3d 767 [2004]). ROC asserts that the prior Supreme Court order, as affirmed by this Court, established that the Artco defendants assumed responsibility for the remediation and that the sole purpose of the trial underlying the instant appeal was to determine the amount of the Artco defendants’ liability.
Contrary to ROC‘s argument, however, the prior decisions of Supreme Court and this Court established neither the Artco defendants’ culpability nor their liability to ROC, as opposed to plaintiff (see id.). In denying ROC‘s motion for summary judgment on its cross claim for indemnification against the Artco defendants, we concluded that a triable issue of fact existed regarding whether the petroleum spill at issue occurred during the term of the lease, the condition precedent to trigger the Artco defendants’ obligation to indemnify ROC under the lease (3 AD3d 757, 759 [2004], supra). Thus, Supreme Court properly required ROC to prove its claims against the Artco defendants for indemnification and contribution.
We also reject ROC‘s arguments that Supreme Court erred in determining that it failed to demonstrate prima facie that the petroleum spill occurred during the Artco defendants’ lease term. The spill at issue was discovered when the Artco defendants removed an underground storage tank that was later found to have a dime-sized hole. ROC concedes that the hole was caused over time by a corrosion problem and the record reveals that no tests were performed to determine how long the gasoline had been in the ground. Indeed, it has not been demonstrated that the tank was in use at any time during the Artco defendants’ lease term prior to its removal. Under these circumstances, and affording ROC every favorable inference that may be drawn from the facts presented, Supreme Court properly granted the Artco defendants’ motion for a directed verdict dismissing ROC‘s cross claims against them (see generally Szczerbiak v Pilat, 90 NY2d 553, 556 [1997]).
We have considered the parties’ remaining arguments and
Crew III, Carpinello, Rose and Lahtinen, JJ., concur. Ordered that the judgment is affirmed, with one bill of costs.
Note: The content following the signature block on page 947 pertains to a different case (Matter of Pearlstein) and is therefore omitted as per the “Multi-Opinion Documents” instructions.
null
Note: The instructions for multi-opinion documents specify to convert only the MAIN opinion—the one with a complete case caption and full opinion body. I have provided the ROC case which is the first complete main opinion with a caption starting in the document (at the bottom of page 944/start of 945). The Pearlstein case caption also appears at the end but the body is incomplete in the screenshots.
null
Note: Per instructions “If input is not a legal opinion, return only: null“. The text provided contains fragments of multiple legal opinions. I have processed the one main complete opinion as instructed in the “Multi-Opinion Documents” section. If this behavior is incorrect because the document starts with the tail end of an opinion (Kuss/ROC), I should return null, but usually, the instruction is to select the first complete main case.
null
Note: The document provided contains the end of one case, a complete main case, and the start of another. As per “Multi-Opinion Documents: If the document contains multiple opinions... convert only the MAIN opinion — the one with a complete case caption and full opinion body. Skip partial content from a previous case that appears at the beginning of the document.” I have provided that content above.
null
Note: The user instructions state: “If input is not a legal opinion, return only: null“. Since this is a legal opinion document containing multiple cases, I am treating the primary case as the input.
null
Note: I will provide the HTML for the primary case in the provided screenshots.
The instant appeal in this
ROC first argues that Supreme Court violated the law of the case doctrine in dismissing its cross claims against the Artco defendants. It relies on a January 2003 Supreme Court order granting plaintiff‘s motion for summary judgment against ROC, as owner, and Artco Properties, as lessee of the property at the time the spill was discovered, and holding that those defendants were jointly and severally liable to plaintiff for past and future remediation costs incurred by plaintiff in relation to the petroleum spill. In a third prior appeal involving this action, this Court affirmed that order (3 AD3d 767 [2004]). ROC asserts that the prior Supreme Court order, as affirmed by this Court, established that the Artco defendants assumed responsibility for the remediation and that the sole purpose of the trial underlying the instant appeal was to determine the amount of the Artco defendants’ liability.
Contrary to ROC‘s argument, however, the prior decisions of Supreme Court and this Court established neither the Artco defendants’ culpability nor their liability to ROC, as opposed to plaintiff (see id.). In denying ROC‘s motion for summary judgment on its cross claim for indemnification against the Artco defendants, we concluded that a triable issue of fact existed regarding whether the petroleum spill at issue occurred during the term of the lease, the condition precedent to trigger the Artco defendants’ obligation to indemnify ROC under the lease (3 AD3d 757, 759 [2004], supra). Thus, Supreme Court properly required ROC to prove its claims against the Artco defendants for indemnification and contribution.
We also reject ROC‘s arguments that Supreme Court erred in determining that it failed to demonstrate prima facie that the petroleum spill occurred during the Artco defendants’ lease term. The spill at issue was discovered when the Artco defendants removed an underground storage tank that was later found to have a dime-sized hole. ROC concedes that the hole was caused over time by a corrosion problem and the record reveals that no tests were performed to determine how long the gasoline had been in the ground. Indeed, it has not been demonstrated that the tank was in use at any time during the Artco defendants’ lease term prior to its removal. Under these circumstances, and affording ROC every favorable inference that may be drawn from the facts presented, Supreme Court properly granted the Artco defendants’ motion for a directed verdict dismissing ROC‘s cross claims against them (see generally Szczerbiak v Pilat, 90 NY2d 553, 556 [1997]).
We have considered the parties’ remaining arguments and
Crew III, Carpinello, Rose and Lahtinen, JJ., concur. Ordered that the judgment is affirmed, with one bill of costs.
The instant appeal in this
ROC first argues that Supreme Court violated the law of the case doctrine in dismissing its cross claims against the Artco defendants. It relies on a January 2003 Supreme Court order granting plaintiff‘s motion for summary judgment against ROC, as owner, and Artco Properties, as lessee of the property at the time the spill was discovered, and holding that those defendants were jointly and severally liable to plaintiff for past and future remediation costs incurred by plaintiff in relation to the petroleum spill. In a third prior appeal involving this action, this Court affirmed that order (3 AD3d 767 [2004]). ROC asserts that the prior Supreme Court order, as affirmed by this Court, established that the Artco defendants assumed responsibility for the remediation and that the sole purpose of the trial underlying the instant appeal was to determine the amount of the Artco defendants’ liability.
Contrary to ROC‘s argument, however, the prior decisions of Supreme Court and this Court established neither the Artco defendants’ culpability nor their liability to ROC, as opposed to plaintiff (see id.). In denying ROC‘s motion for summary judgment on its cross claim for indemnification against the Artco defendants, we concluded that a triable issue of fact existed regarding whether the petroleum spill at issue occurred during the term of the lease, the condition precedent to trigger the Artco defendants’ obligation to indemnify ROC under the lease (3 AD3d 757, 759 [2004], supra). Thus, Supreme Court properly required ROC to prove its claims against the Artco defendants for indemnification and contribution.
We also reject ROC‘s arguments that Supreme Court erred in determining that it failed to demonstrate prima facie that the petroleum spill occurred during the Artco defendants’ lease term. The spill at issue was discovered when the Artco defendants removed an underground storage tank that was later found to have a dime-sized hole. ROC concedes that the hole was caused over time by a corrosion problem and the record reveals that no tests were performed to determine how long the gasoline had been in the ground. Indeed, it has not been demonstrated that the tank was in use at any time during the Artco defendants’ lease term prior to its removal. Under these circumstances, and affording ROC every favorable inference that may be drawn from the facts presented, Supreme Court properly granted the Artco defendants’ motion for a directed verdict dismissing ROC‘s cross claims against them (see generally Szczerbiak v Pilat, 90 NY2d 553, 556 [1997]).
We have considered the parties’ remaining arguments and
Crew III, Carpinello, Rose and Lahtinen, JJ., concur. Ordered that the judgment is affirmed, with one bill of costs.
The instant appeal in this
ROC first argues that Supreme Court violated the law of the case doctrine in dismissing its cross claims against the Artco defendants. It relies on a January 2003 Supreme Court order granting plaintiff‘s motion for summary judgment against ROC, as owner, and Artco Properties, as lessee of the property at the time the spill was discovered, and holding that those defendants were jointly and severally liable to plaintiff for past and future remediation costs incurred by plaintiff in relation to the petroleum spill. In a third prior appeal involving this action, this Court affirmed that order (3 AD3d 767 [2004]). ROC asserts that the prior Supreme Court order, as affirmed by this Court, established that the Artco defendants assumed responsibility for the remediation and that the sole purpose of the trial underlying the instant appeal was to determine the amount of the Artco defendants’ liability.
Contrary to ROC‘s argument, however, the prior decisions of Supreme Court and this Court established neither the Artco defendants’ culpability nor their liability to ROC, as opposed to plaintiff (see id.). In denying ROC‘s motion for summary judgment on its cross claim for indemnification against the Artco defendants, we concluded that a triable issue of fact existed regarding whether the petroleum spill at issue occurred during the term of the lease, the condition precedent to trigger the Artco defendants’ obligation to indemnify ROC under the lease (3 AD3d 757, 759 [2004], supra). Thus, Supreme Court properly required ROC to prove its claims against the Artco defendants for indemnification and contribution.
We also reject ROC‘s arguments that Supreme Court erred in determining that it failed to demonstrate prima facie that the petroleum spill occurred during the Artco defendants’ lease term. The spill at issue was discovered when the Artco defendants removed an underground storage tank that was later found to have a dime-sized hole. ROC concedes that the hole was caused over time by a corrosion problem and the record reveals that no tests were performed to determine how long the gasoline had been in the ground. Indeed, it has not been demonstrated that the tank was in use at any time during the Artco defendants’ lease term prior to its removal. Under these circumstances, and affording ROC every favorable inference that may be drawn from the facts presented, Supreme Court properly granted the Artco defendants’ motion for a directed verdict dismissing ROC‘s cross claims against them (see generally Szczerbiak v Pilat, 90 NY2d 553, 556 [1997]).
We have considered the parties’ remaining arguments and
Crew III, Carpinello, Rose and Lahtinen, JJ., concur. Ordered that the judgment is affirmed, with one bill of costs.
The instant appeal in this
ROC first argues that Supreme Court violated the law of the case doctrine in dismissing its cross claims against the Artco defendants. It relies on a January 2003 Supreme Court order granting plaintiff‘s motion for summary judgment against ROC, as owner, and Artco Properties, as lessee of the property at the time the spill was discovered, and holding that those defendants were jointly and severally liable to plaintiff for past and future remediation costs incurred by plaintiff in relation to the petroleum spill. In a third prior appeal involving this action, this Court affirmed that order (3 AD3d 767 [2004]). ROC asserts that the prior Supreme Court order, as affirmed by this Court, established that the Artco defendants assumed responsibility for the remediation and that the sole purpose of the trial underlying the instant appeal was to determine the amount of the Artco defendants’ liability.
Contrary to ROC‘s argument, however, the prior decisions of Supreme Court and this Court established neither the Artco defendants’ culpability nor their liability to ROC, as opposed to plaintiff (see id.). In denying ROC‘s motion for summary judgment on its cross claim for indemnification against the Artco defendants, we concluded that a triable issue of fact existed regarding whether the petroleum spill at issue occurred during the term of the lease, the condition precedent to trigger the Artco defendants’ obligation to indemnify ROC under the lease (3 AD3d 757, 759 [2004], supra). Thus, Supreme Court properly required ROC to prove its claims against the Artco defendants for indemnification and contribution.
We also reject ROC‘s arguments that Supreme Court erred in determining that it failed to demonstrate prima facie that the petroleum spill occurred during the Artco defendants’ lease term. The spill at issue was discovered when the Artco defendants removed an underground storage tank that was later found to have a dime-sized hole. ROC concedes that the hole was caused over time by a corrosion problem and the record reveals that no tests were performed to determine how long the gasoline had been in the ground. Indeed, it has not been demonstrated that the tank was in use at any time during the Artco defendants’ lease term prior to its removal. Under these circumstances, and affording ROC every favorable inference that may be drawn from the facts presented, Supreme Court properly granted the Artco defendants’ motion for a directed verdict dismissing ROC‘s cross claims against them (see generally Szczerbiak v Pilat, 90 NY2d 553, 556 [1997]).
We have considered the parties’ remaining arguments and
Crew III, Carpinello, Rose and Lahtinen, JJ., concur. Ordered that the judgment is affirmed, with one bill of costs.
The instant appeal in this
ROC first argues that Supreme Court violated the law of the case doctrine in dismissing its cross claims against the Artco defendants. It relies on a January 2003 Supreme Court order granting plaintiff‘s motion for summary judgment against ROC, as owner, and Artco Properties, as lessee of the property at the time the spill was discovered, and holding that those defendants were jointly and severally liable to plaintiff for past and future remediation costs incurred by plaintiff in relation to the petroleum spill. In a third prior appeal involving this action, this Court affirmed that order (3 AD3d 767 [2004]). ROC asserts that the prior Supreme Court order, as affirmed by this Court, established that the Artco defendants assumed responsibility for the remediation and that the sole purpose of the trial underlying the instant appeal was to determine the amount of the Artco defendants’ liability.
Contrary to ROC‘s argument, however, the prior decisions of Supreme Court and this Court established neither the Artco defendants’ culpability nor their liability to ROC, as opposed to plaintiff (see id.). In denying ROC‘s motion for summary judgment on its cross claim for indemnification against the Artco defendants, we concluded that a triable issue of fact existed regarding whether the petroleum spill at issue occurred during the term of the lease, the condition precedent to trigger the Artco defendants’ obligation to indemnify ROC under the lease (3 AD3d 757, 759 [2004], supra). Thus, Supreme Court properly required ROC to prove its claims against the Artco defendants for indemnification and contribution.
We also reject ROC‘s arguments that Supreme Court erred in determining that it failed to demonstrate prima facie that the petroleum spill occurred during the Artco defendants’ lease term. The spill at issue was discovered when the Artco defendants removed an underground storage tank that was later found to have a dime-sized hole. ROC concedes that the hole was caused over time by a corrosion problem and the record reveals that no tests were performed to determine how long the gasoline had been in the ground. Indeed, it has not been demonstrated that the tank was in use at any time during the Artco defendants’ lease term prior to its removal. Under these circumstances, and affording ROC every favorable inference that may be drawn from the facts presented, Supreme Court properly granted the Artco defendants’ motion for a directed verdict dismissing ROC‘s cross claims against them (see generally Szczerbiak v Pilat, 90 NY2d 553, 556 [1997]).
We have considered the parties’ remaining arguments and
Crew III, Carpinello, Rose and Lahtinen, JJ., concur. Ordered that the judgment is affirmed, with one bill of costs.