The dispositive issue on appeal is whether the trial court properly granted the motion of the defendant, Kenneth Lewis, to dismiss an information charging him with violations of General Statutes § 20-427,
The record discloses the following pertinent facts. The defendant is a registered home improvement contractor operating a business under the name of American Construction. In April, 2003, the defendant entered into a home improvement contract with a consumer, Arun Agarwai, for various improvements to Agarwal’s residence in Woodbridge. Pursuant to the contract and an addendum entered into by the parties (contract), these improvements included removing and installing a roof and installing a deck, sunroom, siding and windows. The contract price, including labor and materials, totaled $46,000. Agarwai made two advance payments to the defendant totaling $14,300—$4300 on April 27, 2003, and $10,000 on May 3, 2003. The defendant did not perform any of the work set forth in the contract at Agarwal’s residence, but the defendant asserted in his trial court brief that he had spent approximately $4195 of the money advanced on a budding permit and materials. On or about June 11, 2003, Agarwai sent written notice to the defendant stating that he was canceling the contract and requesting a refund of the advance money he had paid. The defendant failed to
Thereafter, the state charged the defendant in a two count information with violating § 20-427 (b) (8); see footnote 1 of this opinion; for failing to refund the payment for a home improvement within ten days of a written request. The defendant, pursuant to Practice Book § 41-8 (8), moved to dismiss the information, asserting that the statute under which he was charged is (1) unconstitutionally vague on its face, and (2) unconstitutionally vague as applied to the facts of this case. The defendant attached to his motion excerpts from Agarwai’s deposition taken in connection with his companion civil action against the defendant, and a copy of the building permit issued to the defendant together with the application attached thereto. The parties submitted memoranda of law on the motion to dismiss, but the trial court did not hold an evidentiary hearing.
In a memorandum of decision dated July 9, 2004, the trial court granted the defendant’s motion to dismiss. The court held that § 20-427 (b) (8) was unconstitutionally vague as applied to the defendant’s conduct because the statute is unclear as to what constitutes performance of a “substantial portion” of the contracted work. Accordingly, the court granted the defendant’s motion to dismiss on that basis. The court also addressed the defendant’s facial challenge, determined that the statute was not unconstitutionally vague on its face and accordingly denied the motion to dismiss on that basis. The defendant does not challenge on appeal that conclusion of the trial court. The state appealed from the judgment of the trial court to the Appellate Court, and we transferred the appeal to this court pursuant to General Statutes § 51-199 (c) and Practice Book § 65-1.
The defendant responds that the trial court properly granted his motion based on those facts that were undisputed and the materials that he had attached to his motion. Additionally, the defendant contends that, even if the trial court should not have considered the materials accompanying his motion to dismiss, the burden fell on the state to challenge the trial court’s consideration of those materials and to seek an evidentiary hearing. By failing to do so, the defendant contends that the state acquiesced to the trial court’s reliance on the record it had before it. We agree with the state.
We begin with the pertinent legal principles that guide our decision. “A statute is not void for vagueness unless it clearly and unequivocally is unconstitutional, making every presumption in favor of its validity. ... To demonstrate that [a statute] is unconstitutionally vague as applied to him, the [defendant] therefore must . . . demonstrate beyond a reasonable doubt that [he] had inadequate notice of what was prohibited or that [he was] the victim of arbitrary and discriminatory enforce
“The general rule is that the constitutionality of a statutory provision being attacked as void for vagueness is determined by the statute’s applicability to the particular facts at issue. ... To do otherwise, absent the appearance that the statute in question intrudes upon fundamental guarantees, particularly first amendment freedoms, would be to put courts in the undesirable position of considering every conceivable situation which might possibly arise in the application of [the statute]. . . . Thus, outside the context of the first amendment, in order to challenge successfully the facial validity of a statute, a party is required to demonstrate as a threshold matter that the statute may not be applied constitutionally to the facts of [the] case.” (Citation omitted; internal quotation marks omitted.) Rocque v. Farricielli, 269 Conn. 187, 204-205, 848 A.2d 1206 (2004).
The defendant’s claim does not implicate his first amendment rights. Rather, the essence of the defendant’s claim is that a home improvement contractor of ordinary intelligence would not have had fair warning that his conduct was proscribed by § 20-427 (b) (8). Accordingly, to establish the unconstitutionality of the statute as applied to him, it was incumbent on the defendant to present a factual record demonstrating how the
Recogmzing tMs well established principle, the defendant claims that he provided a factual record to substantiate Ms constitutional challenge to the statute’s validity and upon wMch the trial court could make its determination. Specifically, the defendant relies on the excerpts from Agarwal’s deposition,
Although we generally review a trial court’s factual findings under the “clearly erroneous” standard, when a trial court makes a decision based on pleadings and
As the state properly points out, however, the issue in this case of whether § 20-427 (b) (8) is unconstitutional as applied depends on factual findings. Stated another way, in the absence of either undisputed facts,
We also disagree with the defendant’s claim that any fault arising from a deficiency in the record belongs to the state. This argument misses the mark. It was not incumbent upon the state to provide the evidence upon which the trial court could make factual findings essential to the defendant’s challenge to the statute as applied to him. The burden rests with the party mounting the constitutional challenge to provide an adequate factual record in order to demonstrate the statute’s actual adverse impact on him and not merely its impact under some hypothetical set of facts as yet unproven. State v. Madera, 198 Conn. 92, 106, 503 A.2d 136 (1985). “Determination of the scope and constitutionality of legislation in advance of its immediate adverse effect in the context of a concrete case involves too remote and abstract an inquiry for the proper exercise of the judicial function.” (Internal quotation marks omitted.) Bell Atlantic Mobile, Inc. v. Dept. of Public Utility Control, 253 Conn. 453, 490, 754 A.2d 128 (2000). A party “cannot mount a constitutional challenge to a statute on the basis of its possible applications in circumstances not presented by his own case, unless first amendment freedoms are affected, a situation not claimed to exist here.” State v. Madera, supra, 106; see also id., 106-107 (“In the absence of a clear indication in the record that the state is relying upon a claim that the defendant ‘recklessly’ caused the destruction of the apartment building and thus committed arson in the
The judgment is reversed and the case is remanded with direction to deny the defendant’s motion to dismiss, and for further proceedings according to law.
In this opinion the other justices concurred.
General Statutes § 20-427 provides in relevant part: “(b) No person shall ... (8) fail to refund the amount paid for a home improvement within ten days of a written request mailed or delivered to the contractor’s last known address, if no substantial portion of the contracted work has been performed at the time of the request and more than thirty days has elapsed since the starting date specified in the written contract, or more than thirty days has elapsed since the date of the contract if such contract does not specify a starting date.
“(c) In addition to any other remedy provided for in this chapter . . . (2) any person who violates the provisions of subdivision (8) of subsection (b) of this section shall be guilty of a class B misdemeanor if the home improvement that is offered or made has a total cash price of ten thousand dollars or less and shall be guilty of a class A misdemeanor if the home improvement that is offered or made has a total cash price of more than ten thousand dollars. Notwithstanding subsection (d) of section 53a-29 or section 54-56e, if the court determines that a contractor cannot fully repay his victims within the period of probation established in subsection (d) of section 53a-29 or section 54-56e, the court may impose probation for a period of not more than five years. A violation of any of the provisions of this chapter shall be deemed an unfair or deceptive trade practice under subsection (a) of section 42-110b. . . .”
General Statutes § 20418 et seq.
The state also claims that the trial court improperly determined that § 20-427 (b) (8) is unconstitutionally vague as applied to the defendant’s conduct. Because we agree with the state’s first claim, we do not address its second claim.
Although the excerpts from Agarwal’s deposition that were attached to the defendant’s motion were not signed by the officer before whom the deposition had been taken, the sealed deposition, containing the requisite signature, was available for inspection by the trial court by virtue of the sealed deposition having been referenced in the fact section of the defendant’s memorandum of law in support of his motion.
The defendant relies on these documents to support his contentions that he spent a substantial amount of the advance payments for the building permit and the materials allegedly delivered to Agarwal’s residence, that he did not commence the work because of a dispute over the scope of the work to be performed and that some of these materials ultimately were used by other contractors hired by Agarwal.
We note, however, that we make no determination as to the merits of the defendant’s constitutional claim, which therefore is not barred by the doctrine of res judicata. See Cladysz v. Planning & Zoning Commission, 256 Conn. 249, 260, 773 A.2d 300 (2001) (“[ijssue preclusion arises when an issue is actually litigated and determined by a valid and final judgment, and that determination is essential to the judgment”).