¶ 1. The question presented is whether a State environmental-enforcement action seeking declaratory and injunctive relief, recovery of response costs, and civil penalties triggers the right to a jury trial under Chapter I, Article 12 of the Vermont Constitution. We hold that the relief sought by the State in this case is essentially equitable in nature and, therefore, that *389 the right to trial by jury does not attach. The trial court’s conclusion to the contrary is reversed.
¶ 2. The facts and procedural history may be summarized as follows. In December 2003, the State of Vermont — through the Agency of Natural Resources (ANR) — filed a complaint in superior court against defendant Irving Oil Company. The complaint alleged that, on or about July 24, 1997, a delivery truck owned and operated by defendant overturned on the Quechee Road in Hartland, Vermont, releasing gasoline into the surrounding area. When defendant later refused to assume responsibility for the investigation and remediation of the resulting contamination, the State was compelled to do so, incurring substantial costs. The State’s complaint alleged that defendant was strictly liable under a provision of the Waste Management Act, 10 V.S.A. § 6615(a), for abatement of the release and the costs of remediation, and sought the following relief: (1) a declaratory judgment stating that defendant was strictly liable for abatement of the gasoline contamination at the site; (2) an injunction ordering defendant to assume responsibility for the ongoing investigation and cleanup of the site; (3) an order requiring defendant to reimburse the State for expenses that the State had been compelled to incur in investigating and remediating the site; and (4) civil penalties for violation of the prohibition against the release of hazardous materials. Id. §§ 6615(a)(4), 8221(b). 1
¶ 3. Defendant’s answer to the complaint included a demand for jury trial. The State, in response, moved to strike the demand, asserting that its claims were equitable in nature and therefore not subject to trial by jury. In June 2006, the trial court issued a written decision denying the State’s motion in most, but not all, respects. The parties had agreed that the claims for declaratory and injunctive relief were equitable in nature and not subject to jury trial, and the court so ruled. As to the State’s request for reimbursement of investigation and cleanup costs, however, the *390 court concluded that such a demand for monetary relief was a “classic claim for damages” at law and therefore triggered the right to a jury under Chapter I, Article 12 of the Vermont Constitution. 2 In addition, the court concluded that the State’s claim for civil penalties was analogous to a common-law action in debt traditionally tried in courts of law, and therefore also subject to trial by jury, although the amount of any penalties imposed would be determined by a judge, not a jury. 3
¶4. The State moved for permission to take an interlocutory appeal of the ruling. Although the trial court denied the request, we granted the State’s renewed motion to address the important legal and constitutional issues raised. For the reasons set forth below, we reverse the decision of the trial court.
I.
¶ 5. Although the right to a civil jury trial enjoys federal constitutional protection under the Seventh Amendment,
4
that provision has not been applied to the states. See
Curtis v. Loether,
¶ 6. As early as
Plimpton v. Town of Somerset,
The [Constitution was intended to provide for the future as well as the past .... Hence it is not the time when the violated right first had its existence, nor whether the statute which gives rise to it was adopted before or after the [Constitution, that we are to regard as the criterion of the extent of this provision of the [Constitution; but it is the nature of the controversy between the parties, and its fitness to be tried by a jury according to the rules of the common law that must decide the question.
Id. at 291-92 (emphasis in original).
*392
¶ 7. More recently, in
Hodgdon,
¶ 8. Characterizing the “remedy sought” as either legal or equitable is not without its own difficulties, however, and has often led to disagreements on the Supreme Court. See generally, e.g.,
Terry,
¶ 9. Following the Supreme Court’s two-part analysis, the parties here vigorously debate, first, the appropriate historical antecedent to a claim for response costs under the Waste Management Act, and, second, the proper characterization of the remedy sought as either legal or equitable. Defendant maintains in this regard that a governmental action for recovery of environmental cleanup costs is most analogous to a common-law action in quasi-contract, which it argues was traditionally tried at law, while the State argues that its claim is analogous to one for restitution, public nuisance, or equitable subrogation, all purportedly equitable claims tried to a court rather than a jury. Acknowledging the greater importance of the second inquiry, however, the State argues strenuously that recovery of environmental investigation and response costs incurred by the State represents a restitutionary remedy for the return of money expended on defendant’s behalf, relief traditionally characterized as equitable in nature. See
Gorton,
¶ 10. Defendant counters that the CERCLA cases are conclusory in their reasoning and analysis and that, in any event, their authority has been largely eroded by the more recent Supreme Court decision in
Great-West.
In a five-four decision,
Great-West
held that a provision of the Employee Retirement Income Security Act (ERISA), 29 U.S.C. § 1132(a)(3), that empowered health-plan participants to obtain “appropriate equitable relief’ to redress violations did not authorize an action by an insurer seeking reimbursement from a tort settlement entered into by the plan beneficiaries.
¶ 11. While certainly interesting and well argued, neither the historical debate over common-law analogues nor the doctrinal dispute over the nature of restitution represents, in our view, the correct basis of decision in this case. We are persuaded, rather, that regardless of its common-law antecedents or remedial category, the State’s request for reimbursement of environmental investigation and response costs serves largely as an adjunct to its claim for declaratory and injunctive relief and therefore is equitable in nature. As noted, the Supreme Court has recognized that a “monetary award incidental to or intertwined with injunctive relief may be equitable,”
Terry,
¶ 12. This principle is well illustrated in
Golden v. Kelsey-Hayes Co.,
the type of monetary relief that courts, and the Restatement, envision as equitable relief; they are incidental to the grant of equitable relief, yet are necessary to afford complete relief. A court does not err in denying a jury trial where the monetary award sought is incidental to, or intertwined with, equitable relief.
Id. at 661. Here, similarly, the damages sought by the State for response costs incurred are incidental to the request for an injunction to compel defendant to assume full responsibility for the cleanup, yet necessary to provide a complete remedy.
¶ 13. A similar analysis, in an altogether different context, was applied by the court in
Entergy Ark., Inc. v. Nebraska,
¶ 14. Similar reasoning underlay the court’s decision, in still another statutory setting, in
Adams v. Cyprus Amax Minerals Co.,
¶ 15. Consistent with these decisions, we conclude that the overarching remedy sought by the State here is broad declaratory and injunctive relief to confirm defendant’s liability for the contamination and to compel defendant to assume responsibility for its abatement. The prayer for reimbursement of response costs incurred to date is merely “incidental to and intertwined with” that effort; it complements the equitable remedy and serves to afford complete relief. Accordingly, we conclude that the right to jury trial under Chapter I, Article 12 does not attach.
¶ 16. Although defendant maintains that such a conclusion contravenes the United States Supreme Court’s seminal decisions in
Dairy Queen, Inc. v. Wood,
II.
¶ 17. The State additionally contends the trial court erred in finding that defendant was entitled to jury trial on the claim for civil penalties under 10 V.S.A. § 8221(b)(6).
7
The court relied principally on
Tull,
where the Supreme Court compared a civil-penalty provision of the federal Clean Water Act to an eighteenth-century common-law action in debt traditionally triable in a court of law, and characterized the relief sought as essentially punitive
*399
in nature, a remedy also traditionally available only at law.
¶ 18. A review of the statutory factors to be considered by a court in fixing the amount of any civil penalties in an action of this nature underscores their essentially equitable character. These include, to be sure, several criteria concerning the defendant’s culpability, such as whether it “knew or had reason to know the violation existed” and its “record of compliance,” 10 V.S.A. § 8010(b)(3), (4), but on the whole, the factors reflect a primary legislative concern with protecting the public health and safety and preventing unjust enrichment at the expense of the State and the public. See
id.
§ 8010(b)(1), (5), (7) (requiring consideration of “the degree of actual or potential impact on public health, safety, welfare and the environment,” the “economic benefit gained from the violation,” and “the state’s actual costs of enforcement”); see also
id.
§ 8001 (explaining that the legislative purposes underlying the secretary’s civil-enforcement powers include the “protection of environmental and human health” and “prevent[ing] the unfair economic advantage obtained by persons who operate in violation of environmental laws”). These considerations strongly suggest, in turn, a legislative intent to assign the careful balancing of equities that must necessarily underlie the decision to impose such civil penalties, and the amount of any penalty to be assessed, with the agency traditionally entrusted with such decisions: a judge rather than a jury. See
DiPirro v. Bondo Corp.,
¶ 19. Our holding that the civil-penalties remedy under § 8221(b) is essentially equitable finds additional support in decisions from other states reaching the same conclusion in similar environmental-enforcement contexts. See, e.g.,
Comm’r of Envtl. Protection v. Conn. Bldg. Wrecking Co.,
¶ 20. We hold, in conclusion, that neither the State’s prayer for recovery of response costs under 10 V.S.A. § 6615, nor its request for civil penalties pursuant to 10 V.S.A. § 8221(b)(6), requires a jury trial under Chapter I, Article 12 of the Vermont Constitution.
Those portions of the superior court order denying the State’s motion to strike the demand for jury trial are reversed.
Notes
Section 6615(a)(4) provides that a person responsible for the release of hazardous materials shall be liable for “abating such release” and the “costs of investigation, removal and remedial actions incurred by the state which are necessary to protect the public health or the environment.” Section 8221(b) provides that, in an environmental enforcement action, a court may, inter alia: “(1) enjoin future activities; (2) order remedial actions to be taken to mitigate hazard to human health or the environment; ... (5) order reimbursement from any person who caused governmental expenditures for the investigation, abatement, mitigation, or removal of a hazard to human health or the environment; (6) levy a civil penalty.”
Chapter I, Article 12 provides: “That when any issue in fact, proper for the cognizance of a jury is joined in a court of law, the parties have a right to trial by jury, which ought to be held sacred.”
The complaint had also asserted common claims for equitable subrogation and nuisance, and the court addressed these as well. Concerning the former, the court acknowledged that it could not discern “what the subrogation claim is based upon” but ruled, nevertheless, that subrogation was traditionally considered an equitable remedy not subject to trial by jury. Defendant has not cross-appealed from the court’s ruling, and we therefore lack jurisdiction to address the issue. See
Perry v. Med. Practice Bd.,
The Seventh Amendment to the United States Constitution provides:
In suits at common law, where the value in controversy shall exceed twenty dollars, the right of trial by jury shall be preserved, and no fact tried by a jury shall be otherwise reexamined in any Court of the United States, than according to the rules of the common law.
Although defendant cites
In re Acushnet River & New Bedford Harbor,
Defendant also appears to renew on appeal, albeit summarily, an argument developed more fully below that the damage claim should be considered legal in nature because it seeks reimbursement of funds from the Vermont Petroleum Cleanup Fund (PCF) used to purchase bottled water for residents whose wells were allegedly contaminated by the gasoline spill. Funded by regulatory fees from storage tank owners and operators, the PCF authorizes disbursements for the costs of remedial actions to “clean up spills of oil and other petroleum products,” 10 V.S.A. § 1941(b)(8), as well as for the “costs incurred in compensating third parties for bodily injury and property damage.” Id. § 1941(b)(2). Apparently because the State classified the disbursements under § 1941(b)(2), defendant maintains that the claim here must be characterized as an action at law for recovery of third-party property damages. The State’s accounting classification of the monies expended does not, however, alter the essentially equitable nature of the State’s action here, in which the prayer for expenses is intertwined with and subsidiary to the effort to compel abatement.
As noted, this section provides that, in a civil enforcement action, a court may “levy a civil penalty” and further directs that “[i]n fixing the amount of the penalty the court shall apply the criteria set forth in subsection 8010(b).” 10 V.S.A. § 8221(b)(6). Section 8010(b) sets forth the following criteria:
(1) the degree of actual or potential impact on public health, safety, welfare and the environment resulting from the violation;
(2) the presence of mitigating circumstances, including unreasonable delay by the secretary in seeking enforcement;
(3) whether the respondent knew or had reason to know the violation existed;
(4) the respondent’s record of compliance;
(5) the economic benefit gained from the violation;
(6) the deterrent effect of the penalty;
(7) the state’s actual costs of enforcement; and
(8) the length of time the violation has existed.
10 V.S.A. § 8010(b)(l)-(8).
Riendeau was discussing the imposition of civil penalties for discharges of waste in violation of 10 Y.S.A. § 1274, rather than the assessment of civil penalties under § 8221(b)(6), but the remedial goals are similar.
