138 Conn. 334 | Conn. | 1951
The plaintiff brought this action against the defendant Deliso Construction Company to recover damages for the alleged breach of a highway construction contract. The Hartford Accident and Indemnity Company, which had given its bond conditioned upon the faithful performance of the contract, was joined as party defendant. The Deliso Company, hereinafter called the company, filed a counterclaim to recover the reasonable value of the work it had done up. to the time when it rescinded the contract, less the payments it had received, because of an alleged misrepresentation by officials of the state highway department. The court rendered judgment for both defendants on the complaint and for the company on its counterclaim. The plaintiff’s appeal is addressed only to that phase of the judgment which disposed of the counterclaim.
The court found, among others, the same facts as those which are recited at length in the opinion on a former appeal. State v. Hartford Accident & Indemnity Co., 136 Conn. 157, 160, 70 A. 2d 109. They need not be repeated except in the following abbreviated form: The company, with others, submitted to the state highway department a bid on a proposed road construction job. The bidders had been supplied with plans and specifications, together with a list of items of work to be performed. Included in the latter was an item, "Unclassified Excavation---C. Y.---125, 983.” The department’s standard specifications classi
Within a few months after the company commenced work, it had excavated almost 39,000 cubic yards of rock. It was apparent by that time that many more thousand cubic yards remained. After attempting without success to obtain from the highway depart
It was pointed out in the opinion on the former appeal that the award of damages to the company at the first trial could not be supported because of certain discrepancies in the finding. State v. Hartford Accident & Indemnity Co., supra, 167 et seq. It was there stated that “If the company has any right to recover, it must be based upon the representations made by the director of engineering at the conference at which he, the highway commissioner and the president of the company were present.” Id., 167. We further said that “If it should be found that the department did represent to the company that it would be necessary to excavate only 38,000 cubic yards of rock when the amount was in fact more than 69,000, and that the defendant was induced to enter into the contract by that representation, the court might be justified in concluding that the company, acting within a reasonable time, had a right to rescind the contract.” Id., 169.
The conflict and uncertainty referred to in the former opinion are resolved by the finding on the present appeal. The court has specifically found that at the conference in question the director of engineering repeatedly stated to the company’s agent not only that the cross-section drawings showed the amount of rock to be excavated but also that it amounted to 38,000 cubic yards. It was in reliance on these representa
The plaintiff now contends that the statements of the director of engineering were not binding upon it since, it is claimed, they were not within the scope of his authority to make. The contention is that the statements were made after the bids were opened and that they changed the terms of the original bid proposal, contrary to the provisions of General Statutes, Cum. Sup. 1935, § 529c (Rev. 1949, § 2229).
These principles, however, have no pertinent application since the statements of the director of engineering at the conference did not involve a revision of the plans and specifications. The statements merely confirmed what the cross-section drawings disclosed. They neither diminished nor enlarged the extent of the work upon which proposals to bid had been invited, nor did they modify its character. They concerned information to which any bidder, uncertain as to the intended meaning of the plans and specifications, was in fairness entitled. Section 529c provides not only for the
The positive assertion that the drawings showed the amount of rock which would have to be cut and that it totaled 38,000 cubic yards was a representation upon which the company had a right to and did rely. United States v. Atlantic Dredging Co., 253 U. S. 1, 11, 40 S. Ct. 423, 64 L. Ed. 735; Christie v. United States, 237 U. S. 234, 242, 35 S. Ct. 565, 59 L. Ed. 933; Hollerbach v. United States, 233 U. S. 165, 172, 34 S. Ct. 553, 58 L. Ed. 898. This is not an action for deceit, which requires proof of the knowledge of the falsity of the representation. Henry v. Kopf, 104 Conn. 73, 75, 131 A. 412. The company was under no obligation to
There is no error.
In this opinion the other judges concurred.
Section 529c authorizes the highway commissioner to seek bids for construction work and outlines the procedure to be followed. This was the statute in force when the contract was executed in 1941.