State v. Blanchard Construction Co.

91 Kan. 74 | Kan. | 1913

The opinion of the court was delivered by

Porter, J.:

It is conceded at the outset that the rules of strict construction which control in cases of accommodation sureties are no longer applied in the case of a bond written by a corporation engaged in the business of furnishing surety for compensation. (Hull v. Bonding Co., 86 Kan. 342, 120 Pac. 544; Medical Co. v. Hamm, 89 Kan. 138, 130 Pac. 650; The Y. M. C. A. v. Ritter, 90 Kan. 332, 133 Pac. 894; Guaranty Co. v. Pressed Brick Co., 191 U. S. 416, 24 Sup. Ct. Rep. 142, 48 L. Ed. 242; Note, 23 A. & E. Ann. Cas. 1085; Note, 33 L. R. A., n. s., 513), and that if a bond like the one su'ed on is fairly open to two constructions, one of which will uphold and the other defeat the claim of the insured, that which is most favorable to the insured will be adopted. But it is rightly contended that where there is no ambiguity, the plain intention of the parties can not be disregarded or nullified by construction.

*82It is insisted by the defendant that none of the estimates were made in the manner provided by the contract ; that the first two estimates violated the contract because they included material and labor that had not in fact been used in the construction of the work at the time the estimates were certified; that none of the other estimates was sufficient to authorize payments,, because they were not made by Stanton, personally; that he placed his “O. K.” upon them without any personal knowledge or information as to their correctness; and further, that they were insufficient for the reason that they likewise included many items for labor and material that had not been used in the construction of the work. Briefly summarized, the contention is that the state, having made these unauthorized payments in violation of the terms of the contract, the bonding company is discharged from any liability upon the bond.

It is said that “John F. Stanton was . . . elected to the important position of state architect . . . and the Bonding Company had a right to rely upon his ability and integrity to the end that the contractor should not receive more than he was entitled to under the contract.” The rights of the parties to the contract are not affected by the fact that Stanton was a state officer. The state architect is appointed by the governor, but it is no part of his duties to act as umpire between the state and a contractor. The parties merely chose him as a suitable person upon whose certified estimates the payment should be made. They might have selected any other person or agency for the purpose. In making the estimates he was not acting as state architect, but merely as an individual.

Upon the findings of fact showing the manner in which the third, fourth and fifth estimates were made, it seems to us clear that they were- the estimates of John F. Stanton, whether in certifying to their correctness he relied upon information obtained from other persons or acquired it in the first instance him*83self. The contract did not in terms require him to see, personally, that the work was done or the material, used. The provision was that he should make an estimate of the labor and material. If he acted in good faith in relying upon information from others as to the extent of the work and the amount of labor and material that had been used, and the Board of Regents in good faith made the payments, the terms of the contract were satisfied.

It is not claimed that there was actual fraud in the manner in which the estimates were made. It is argued, however, that the including of items for labor and material that had not in fact been used in the construction when the estimates were certified amounted to a constructive fraud upon the bonding company.

The form in which the certificates were made was clearly sufficient. The employment of the abbreviation or symbol of “O. K.” in such transaction is in accordance with common usage, and its meaning was not misunderstood by any of the parties.

In Lumber Co. v. Peterson & Sampson, 124 Iowa, 599, 100 N. W. 550, payments were to be made to the contractor upon written certificates of the architect, based upon estimates made by him of the amount earned. The supreme court of Iowa upheld payments of bills which were indorsed by the architect, “O. K.” In the opinion it was said:

“Whether the architects’ ‘O. K.’ indorsement of other bills for payments may fairly be held to be a compliance with the contract depends upon the meaning to be attached to that abbreviation or symbol. ... As already remarked, the purpose of the certificate is to witness the fact that the sum named therein has been earned, and any form of written communication which conveys that information intelligibly and to the satisfaction of the parties should be held sufficient. Now, ‘O. K.’ may have no title to be classed as ‘elegant English,’ but in the business life of this country it has for many years been in common use, and has acquired a meaning which is not at all obscure or uncertain. Web*84ster’s International Dictionary defines it as ‘all correct.’ The Century Dictionary gives its meaning as ‘all right; 'correct; now commonly used as an indorsement, as on a bill.’ It is neither more nor less than a brief, but expressive, certificate of the correctness of the bill or claim on which it is indorsed.” (pp. 610, 611.)

The contract was made a part of the bond, and it is true the provision that no payment should be made except on the certificate of the architect that the work for .which the payment was due had been properly done, like the provision for withholding 10 per cent as a final payment, was for the benefit not only of the original parties but the bonding company as well. (The Y. M. C. A. v. Ritter, 90 Kan. 332, 133 Pac. 894, and cases cited in the opinion.) But this brings us no nearer a solution of the real question as to the liability of the defendant upon the bond. The bonding company guaranteed the faithful performance of the contract on the part of the construction company. The latter did not faithfully perform. The bonding company therefore became liable for the damages sustained by the breach, unless, as •defendant contends, the state is estopped from asserting the liability because it made payments for work •and material that had not in fact been used in the construction of the work at the time. The contract, however, expressly provided that the state was to pay 90 per cent of each estimate when made by the architect. Is the state estopped then from maintaining this action because before making the payments it failed to take the precaution to see that the estimates were true and •correct? We think there can be but one answer. The .state purchased the bond for its protection, in order that the faithful performance of the contract might be .guaranteed and the state be relieved from all obligations except to pay the '90 per cent when the certificates were made and the final payment when the work was completed.

All the parties to the contract agreed that when the estimates were made and certified the amounts due *85thereon should be paid to the contractor. The bond provided that “if payments are not made promptly in accordance to contract, this bond becomes null and void.” This clause was placed upon the face of the bond with a rubber stamp. The dispute as to whether it was stamped thereon at the instance of the state or the bonding company we regard as wholly immaterial. It was, however, to the interest of the surety that payments should be promptly made to the contractor to enable the latter to purchase labor and material and to carry out the contract; and the surety was obviously more interested in the ability of the construction company to perform its contract than was the state. Irrespective of these considerations, the state was obliged to make the payments promptly when the estimates were duly certified, unless it can be said that there was evidence or some finding of bad faith on its part in making the payments. Nothing in the evidence or in the court’s findings indicates that the state acted otherwise than in good faith.

In Smith v. Molleson, 148 N. Y. 241, 42 N. E. 669, the contract required the estimate of the required “ ‘monthly payments not to exceed eighty per cent of the estimated value of the work performed on the building’ ” (p. 247.) In an action on the bond one ground of defense was that the plaintiff had advanced to the contractors a larger portion of the contract price than he was required to by the contract because he had paid upon estimates based upon work done upon the granite at the quarry and at the place where it was dressed before it was actually set in place in the building. The surety was a private person, and under the rule of strictissimi juris, was not to be held beyond the precise stipulations of his contract. Nevertheless the court of appeals held that these payments did not constitute such a departure from the contract as to become available as a defense to the surety, and that the meaning of the contract should not turn on the use of the words *86‘‘on the building”; that the work on the building necessarily involved the preparation and carriage of the material, which were shown to be the most expensive part of the contract, and that the contract necessarily contemplated that the contractor would use the monthly payments for meeting these expenses, and would be practically unable to perform the contract if these payments were not made before the stone was actually set in the building. It was said in the opinion:

“The parties had the right to give to the expression, ‘work performed on the building,’ a broader meaning which could very properly include the value of any work done or materials procured under the contract towards its • erection, although the granite procured and prepared had not yet been placed.” (p. 248.)

In construing the contract the court took into consideration the situation of the parties, the nature of the work and other provisions of the instrument, and held that the intention was to make the advances as the work progressed. It was further said in the opinion:

“To give to it the other construction would, in practice, disable the contractors at the very outset from performance and impose upon the defendant a liability, inevitable from the beginning, and possibly in a much larger amount than has followed the construction adopted by the parties themselves.” (p. 249.)

By the terms of the contract in this case the certificate of the architect was binding upon the original parties, and under the terms of the bond it became binding upon the surety. In the absence of fraud or mistake, the state was obliged to pay 90 per cent of the certified estimates. Neither fraud nor mistake is set up as a defense, and it is conclusively established by the evidence and findings that the plaintiff made the payments in good faith. The total amount of the five estimates was $16,618.53, and this the court finds was the value of the labor and material at the time they were furnished and when the estimates were made. The architect was agreed upon by the parties to the. con*87tract as the person upon whose judgment and decision with respect to the character, amount and value of the work payments were to be made. In the absence of fraud or mistake they are bound by his judgment and decision. In Board of Education v. Shaw, 15 Kan. 33, it was ruled in the syllabus:

“Where the parties to a building contract agree upon an architect, and stipulate and agree to rely upon his judgment, skill and decision as to the character, amount and value of work to be done, they must abide 'by his judgment and decision, or impeach it upon the ground of fraud, mistake, undue influence, or some other good cause.” (Syl. ¶ 2.)

Our conclusion is that the plaintiff is not estopped from maintaining this action because it made the payments upon the certified estimates of the architect; but it is manifestly unj ust that the state should recover for the value of any labor or material included in the estimates which was thereafter diverted to the use of the state. It seems to be practically conceded that material of considerable value which was included in the certified estimates was used in the construction of the gas-producing plant and gas holder. Dimension lumber was used for concrete forms, and sand, cement and other material purchased for the mechanical engineering building were used in the construction of the gas-producing plant. There is a finding that the sand was replaced. We are unable to discover from the evidence or from the findings the value of the amount of labor and material included in the estimates which was thus diverted to the use of the state.

The judgment will therefore be modified and the cause remanded with directions to ascertain the aggregate value of all such items and to deduct the same from the amount of the judgment.