49 Pa. Commw. 420 | Pa. Commw. Ct. | 1980
Opinion by
This is an appeal from an order of the Board of Claims (Board) which awarded damages to W. M. Anderson Co., Inc. (respondent) in restitution for uncompensated electrical work which the respondent furnished for the petitioner, the State Public School Building Authority (School Authority). The controversy arose out of a contract between the School Authority and the respondent for wiring for a School Authority building project.
In February of 1976, a dispute arose between the respondent and another electrical wiring contractor involved in the same project here concerned regarding who was obligated to install certain wiring. After meeting with both contractors - and reviewing the terms of the contract, the School Authority directed the respondent to install the wiring, and, in complying with this order, the respondent incurred an expense to itself of $25,348.54. This expense was unusually high because the respondent installed an additional wiring conduit rather than using an existing conduit which had been installed by the other contractor for the wiring it did. Having been refused compensation by the School Authority for this extra expense, the respondent appealed to the Board and the Board ordered the School Authority to pay restitution damages of $25,348.54. The School Authority does not now contest the Board’s interpretation of the contract, but contends only that the Board had no
The School Authority contends first that its resolution of the dispute was a discretionary governmental act, much like its awarding of contracts pursuant to competitive bidding, and that such a discretionary act cannot be overturned absent a showing of fraud, collusion or bad faith. We find no merit to this argument. It is incontrovertible, of course, that the Commonwealth has waived its immunity to suit for actions arising out of contract,
As for the mitigation of damages, the School Authority contends that, after it directed the respondent to complete the wiring, a further dispute arose concerning the respondent’s use of the existing conduit and, for reasons which are unclear, the respondent
It is a familiar rule of law that a party who suffers a loss due to a breach of contract has a duty to make reasonable efforts to mitigate his losses. Gaylord Builders, Inc. v. Richmond Metal Manufacturing Corp., 186 Pa. Superior Ct. 101, 140 A.2d 358 (1958). Put another way, the amount recoverable by the damaged party must be reduced by the amount of losses which could have been avoided by that party’s reasonable efforts to avoid them.
Based on a careful review of the . testimony before the Board, which focused almost entirely on the interpretation of the contract and only peripherally on the issue of mitigation, we must conclude that the School Authority failed to show that the installation of the second wiring conduit was an avoidable expense, that it failed to show that it was without notice of the dispute concerning the conduit, and that it failed to show what portion of the $25,348.54 expense was avoidable.
The respondent’s sub-contractor, who actually installed the additional conduit, testified that, during the work delay resulting from the School Authority’s
We believe, therefore, that the Board properly declined to find that the respondent’s losses were avoidable. Accordingly, we will affirm the Board’s order.
Order
And Now, this 22nd day of February, 1980, the order of the Board of Arbitration of Claims in the above-captioned matter is affirmed.
See the Act of Hay 20, 1937, P.L. 728, as amended, 72 P.S. §4651-1 et seq.
See Restatement of Contracts §336 (1932).