It must first be determined whether or not the items claimed by the plaintiff in count 3 constituted “extra work” as defined by § 1.29 of the State Standard Specifications, in accordance with which the contractor agreed to perform the work under the contract. “Extra work” is defined as “work or material, the performance or furnishing of which is found necessary for proper completion of the improvement and which in principle is an obligation of the contractor, but which is not covered by any item in the bid schedule in the
The plaintiff in error argues that the work done does not come within the definition of “extra work” above for the reason that the defendant in error failed to comply with the requirements of § 2.06 of the Standard Specifications, which provide that “The bidder is required to examine carefully the site of, and the proposal, plans, Specifications and Contract Form for the work contemplated and it will be assumed that he has judged for and satisfied himself as to the conditions to be encountered, as to the character, quality and quantities of work to be performed and the materials to be furnished, and as to the requirements of these Specifications, Special Provisions and Contract. No adjustments on compensations will be allowed for losses caused by failure to comply with the above requirements.” Construing this provision most strongly against the defendant, who formulated it, we do not believe that the conditions encountered on the project were such that the contractor should have been expected to have anticipated in the exercise of reasonable diligence. The fact that the contract makes provisions for extra work necessitated by unforeseen conditions is evidence enough that not every condition is expected to be anticipated. The additional fact that the defendant executed a supplemental agreement compensating the plaintiff for materials used in the extra work estops it from asserting the defense that the plaintiff was barred from a recovery for failure to comply with this section. Paragraph 24 (d) of the plaintiff’s amended petition alleges that there is no dispute between the parties over the fact that the work was “extra work” and that the only issue with reference to this claim is the amount due the plaintiff for this work. The defendant’s general demurrer to this allegation admits its truth for purposes of pleading.
Having decided that under the allegations of the petition the work was “extra work,” we must now determine whether there was either such a compliance by the plaintiff with the provisions
Was there a waiver by the defendant of this provision requiring a prior written agreement? Section 4.03 provides in part that “ [supplemental agreements . . . increasing or decreasing the quantity of work by more than twenty [20] percent as provided above, are independent of and do not waive any of the provisions regarding extra work as stipulated in Article 4.O4.” (Emphasis supplied). This would seem to indicate that the supplemental agreement did not waive the necessity for the supplemental agreement or the extra work order to have been executed before the work was started.
As described above, the defendant's actions evidenced its ac
The defendant executed the purported contract with the knowledge that the plaintiff intended to claim additional com
Another ground urged by the plaintiff in error for sustaining its general demurrer is the failure of the plaintiff below to specifically allege compliance with § 7.17 of the Standard Specifications, which provides as follows: “Both parties to the contract agree that as a condition precedent to the filing of an action in any court involving the amount or rate of payment or settlement for work performed by the Contractor under these Specifications and Contract, and as a condition precedent to the liability of the Board for any amount other than contained in the estimates approved by the Engineer, any question at issue
Assuming that this point is reached by a general demurrer, we do not think this contention is meritorious. If the italicized portion of this section above conflicts with the provisions therein giving the board of arbitration power to determine the Highway Board’s liability “for any amount other than contained in the estimates approved by the Engineer,” the contract must be construed against the defendant, who wrote it. Under the express terms of the contract, only compensation for “work performed and disallowed by the engineer” is to be subjected to arbitration. This work was ordered, performed, and, as discussed previously, allowed by the engineer by his having pre
For all of the above reasons, the court did not err in overruling the general demurrer to count 3 as amended.
The plaintiff’s claim for damages in count 4 is based upon the defendant’s alleged breach of contract in not anticipating the subsurface conditions in the preparation of the contract, plans and specifications and in delaying the reaching of a decision and making necessary additional plans and drawings to correct the conditions. Reference to the following portions of the contract and the Standard Specifications is sufficient to show that this claim was without merit and therefore subject to the general demurrer: Contract, Par. 4: “The decision of said State Highway Engineer upon any question connected with the execution of this agreement or any failure or delay in the prosecution of the work by the said contractor shall be final and conclusive”; § 8.07, Stand. Spec.: “The Engineer shall have the authority to suspend the work wholly or in part, for such period as he may deem it necessary, due to unsuitable weather, or such other conditions as are considered unfavorable for the suitable prosecution of the work. . .
No additional compensation shall be paid the contractor because of such suspension. . .
The work shall be resumed when conditions are favorable or when corrective measures satisfactory to the Engineer have been applied, when and as ordered by the Engineer in writing” (Emphasis supplied); § 9.03, Stand. Spec.: “The Contractor shall receive
Concerning the defendant’s failure to anticipate such subsurface conditions, it is sufficient to say that provision was made for the revision of plans to correct any such conditions and for additional compensation for such “extra work” thereby necessitated. In the absence of such provisions in the contract, it would be a jury question as to whether the defendant’s three weeks’ delay was a breach of the contract, but in the face of the clear provisions, the claim must be held to be subject to the general demurrer.
The court erred in its judgment overruling the. general demurrer to count 4 for the reasons discussed above, but did not err in overruling the general demurrer to count 3 for the reasons discussed in Division 1 of this opinion.
Judgment affirmed in part; reversed in part.
