State Ex Rel. Utilities Commission v. Edmisten

230 S.E.2d 647 | N.C. | 1976

230 S.E.2d 647 (1976)
291 N.C. 424

STATE of North Carolina ex rel. UTILITIES COMMISSION and Carolina Power and Light Company, Applicant,
v.
Rufus L. EDMISTEN, Attorney General, et al., Intervenors, Protestants.

No. 47.

Supreme Court of North Carolina.

December 21, 1976.

*649 Edward B. Hipp, Gen. Counsel, and Wilson B. Partin, Jr., Asst. Commission Atty., Raleigh, for North Carolina Utilities Commission, plaintiff-appellee.

R. C. Howison, Jr. and William E. Graham, Jr., Raleigh, for Carolina Power & Light Co., plaintiff-appellee.

Thomas P. McNamara, U. S. Atty., by Christine A. Witcover, Asst. U. S. Atty., Raleigh, R. C. Hudson, Norfolk, Va., for Executive Agencies of United States of America, defendant-appellant.

HUSKINS, Justice:

In its first assignment of error appellant challenges the decision of the Commission to consolidate the Military Service classification (MS) with other classes into the new G-3 schedule.

Appellant concedes, and we agree, that it is not presently hurt by the reclassification with respect to the increased rates which it will be required to pay. As noted, the Utilities Commission has adopted a reclassification program designed (1) to bring customer rates into closer alignment with costs of providing service and (2) to simplify existing schedules. The Commission's recent cost-of-service analysis indicates that, under the current rate structure, some service classes are paying a higher proportion of the cost of service than other classes. Thus there is an inter-class cross subsidation resulting in price discrimination. Although this effect originated in historically sound policy, considerable testimony before the Commission suggests that the underlying reasons are no longer compelling. Thus the Commission sought to correct these inequities by more closely aligning the rate of return from each class with that of the system average.

It is true that in moving toward this goal the rates of some groups, including appellant, were raised more, proportionately, than others. The net effect of this increase, however, was to bring CP&L's rate of return for services furnished appellant more in line with that of the system average, in this case 10.215 percent as compared to an overall rate of return of 10.115 percent. As one witness noted, "[y]ou can't make rates much closer than that." Clearly, appellant is not presently aggrieved by the rate schedule as presently applied.

Appellant, however, contends that it will likely be aggrieved in the future by virtue of its joinder with the Textile Mill class (TM-1) and the High Load Factor class (HFL) into the new G-3 classification. It argues that it should not be combined with the other groups because it has service or use characteristics which are incompatible with those groups. For example, it has a different average load factor, minimum demand, and service voltage than the other groups. Appellant further contends that because of these different use characteristics it may, in the future, bear a disproportionate share of the costs within the G-3 classification. That is, it may be aggrieved by intra-class subsidation should it be combined into a rate class with dissimilar groups.

Discussion of this contention requires us first to outline the legal framework within which the Commission ordered the reclassification.

The Utilities Commission is vested generally with the power to regulate utilities and their rates. G.S. 62-2. A rate is defined as "every compensation, charge, fare, tariff, schedule, toll, rental and classification, or any of them, demanded, observed, charged or collected by any public utility, for any service product or commodity *650 offered by it to the public, and any rules, regulations, practices or contracts affecting any such compensation, charge, fare, tariff, schedule, toll, rental or classification." G.S. 62-3. All rates must be just and reasonable. G.S. 62-130 and G.S. 62-131. The consumer has no vested right in existing rates, Utilities Commission v. Municipal Corporations, 243 N.C. 193, 90 S.E.2d 519 (1955), and the Commission may change the rates as circumstances dictate. G.S. 62-130.

This authority is not unbridled. "There must be substantial differences in service or conditions to justify difference in rates. There must be no unreasonable discrimination between those receiving the same kind and degree of service." Utilities Commission v. Mead Corp., 238 N.C. 451, 78 S.E.2d 290 (1953). See Utilities Commission v. Municipal Corporations, supra. It follows that where substantial differences in services or conditions do exist, unreasonable application of the same rates may be discriminatory and thus improper.

The burden of showing the impropriety of rates established by the Commission lies with the party alleging such discrimination. See Utilities Commission v. Light Co. and Utilities Commission v. Carolinas Committee, 250 N.C. 421, 109 S.E.2d 253 (1959). The rates fixed by the Commission are deemed just and reasonable. G.S. 62-132. The Legislature has reiterated this determination by providing that upon "any appeal, the rates fixed or any rule, regulation, finding, determination, or order made by the Commission under the provisions of this Chapter shall be prima facie just and reasonable." G.S. 62-94(e). Utilities Commission v. Telephone Co., 266 N.C. 450, 146 S.E.2d 487 (1966); Utilities Commission v. Coach Co. and Utilities Commission v. Greyhound Corp., 260 N.C. 43, 132 S.E.2d 249 (1963); Utilities Commission v. R.R., 249 N.C. 477, 106 S.E.2d 681 (1959); Utilities Commission v. Casey, 245 N.C. 297, 96 S.E.2d 8 (1957).

This does not preclude appellant from showing on appeal, if it can, that the order is not supported by competent, material and substantial evidence. Utilities Commission v. Coach Co., 261 N.C. 384, 134 S.E.2d 689 (1964); Utilities Commission v. R.R., 238 N.C. 701, 78 S.E.2d 780 (1953). After careful review of this record, however, we hold that the appellant has not carried this burden.

It is apparent that in devising the rate structure the Commission was faced with conflicting goals. One goal was the elimination of all cross subsidation. It is likely that under the combined class arrangement, as adopted by the Commission, some intraclass cross subsidation may occur. In a rate-making scheme based on cost of service to classes, the fewer classes there are, the more likely it is that such cross subsidation will arise. Conversely, a large number of classes reduces the likelihood. Carried to an extreme, costs will be most accurately allocated where each customer is a class by himself and his rates are based on the cost of service to him. By this method a customer living miles from a power station would pay more than a resident living next to a transmission facility. Such a scheme is patently unworkable at the present time. It conflicts with a second goal of rate-making: simplification of the rate structure. Several witnesses testified to the need for simplification. It was noted that North Carolina has considerably more rate classes than most other areas. In fact, the rate experts recommended that the schedule be further reduced to only three classes.

Thus it is apparent that a balance must be struck between the two objectives. This the Commission did in its order of 6 January 1975. We recognize that appellant has lodged strong and cogent objections to the resolution adopted by the Commission, but it is not the function of this Court to select among permissible determinations. That we might have weighed the factors differently is not sufficient to allow us to reverse or modify the order. Utilities Commission v. Telephone Co., 281 N.C. 318, 189 S.E.2d 705 (1972). There must be a showing by appellant that the evidence on which the order is based is insufficient to support that order. G.S. 62-94(b)(5). Appellant *651 has made no such showing. Hence, this assignment is overruled.

In its second assignment of error appellant contends that the Commission erred in entering an order allowing rates of return from a low of 2.702 percent (rural farm, RF) to a high of 13.276 percent (municipal pumping, MP-1) in that they are unreasonably disproportionate to the average rate of return, i. e., 10.115 percent. Neither of the users cited to show the two extremes are parties to this appeal. CP&L's rate of return from appellant under the new schedule would be 10.215 percent which is, as noted at the outset, reasonably close to the average rate. It is clear that appellant is not prejudiced by these alleged unreasonable variations. It is paying only its fair share, a fact which is conceded. Therefore, we do not review this assignment.

Finally, appellant contends that the Cost-of-Service-Study upon which the Commission based its order was incompetent. The thrust of appellant's argument is that the study by CP&L was based on system-wide retail data in North and South Carolina when it should have been based solely on data compiled within the North Carolina jurisdictional area to which the Commission's schedule will apply.

It is true that if the system-wide study significantly varied from results which would be produced by a study based solely on North Carolina data, it would be incompetent. North Carolina rates may not be structured by external system usage. See Corporation Com. v. Mfg. Co., 135 N.C. 17, 116 S.E. 178 (1923). Such action is outside the intended scope of the Commission's authority. G.S. 62-2.

On the record presented here, however, there is ample evidence that data underlying the system-wide cost-of-service studies was representative of the company's operating conditions in North Carolina. Among other factors, we note that 82 percent of all retail system customers are located in North Carolina and that 81 percent of all retail KWHs are sold to customers in this state. With regard to the particular interests of the appellant, we note that seven of CP&L's eight military customers system-wide are located in North Carolina. Based on this and other testimony, we find that the Commission's reliance on data supplied by the contested study was reasonable and that the resulting rates were structured from data representative of CP&L's intrastate experience. Accordingly, this contention is without merit.

Careful review of the entire record compels the conclusion that there is competent evidence to support that portion of the Commission's order of 6 January 1975 which approved the elimination of the Textile Mill Schedule (TM), the High Load Factor Schedule (HLF), and the Military Service Schedule (MS), and the moving of customers in the eliminated schedules into a general service classification, designated Schedule G-3. The well-reasoned decision of the Court of Appeals with respect to the questions raised on appeal to this Court by Executive Agencies of United States of America must therefore be upheld.

AFFIRMED.

midpage