270 Mo. 429 | Mo. | 1917
Lead Opinion
— In April, 1914, complaints were filed with the Public Service Commission praying that an inquiry be made into the character of service rendered by the United Railways Company of the city of St. Louis. The specifications in said complaints were comprehensive and embraced many phases of street railway service. The Commission, after hearing evidence and making such other investigations and inquiries as it deemed proper, made an order, set forth under six headings or subdivisions. The first, third and fourth related to the manner in which the Railways Company was to operate, manage and conduct its cars; the fifth and sixth prescribed the time and manner of the company’s acceptance and compliance with the order; and the second required the company within a specified time to apply to the city authorities for permission to ■ construct and operate certain extensions of the company’s system as designated in the order. The company form-, ally expressed its willingness to comply with the order except as required by the second subdivision, which is as follows:
“Ordered 2nd, That the United Railways Company, defendant herein, be and it is hereby directed and re*436 quired to make application, within thirty days from the effective date of this order, to the proper municipal authorities of the city of St. Louis, Missouri, for the necessary franchises, permits and authority, and to the property owners for the necessary consents, authorizing said defendant company to construct all of the following sections of track, and that the construction of all of said tracks, which may he so authorized, shall be made within the time herein specified.”
Following this the particular lines of the company required to be extended are designated and the times prescribed within which each extension is to be made. Upon the promulgation of this order the company filed a motion for rehearing, and upon its denial made application to the circuit court of the city of St. Louis for a writ of review to determine the validity of that portion of the order to which objection had been made. The circuit court sustained the order of the Commission and the company appeals.
While the proceedings were pending before the Commission the city of St. Louis adopted a new charter, which ‘provides that the city shall have power to regulate rates, quality of use, service and products and methods of conduct and operation of public utilities and at certain times to buy the plant and property of such utilities; and to compel from time to time reasonable extension of facilities for such service. [Sec. 1, art. 1, and sec. 2, art. 19, Charter of St. Louis.]
There is no controversy as to the facts or the regularity of the proceedings and the parties stipulate that the only issues are questions of law, viz., (1) the power of the Commission to order the Railways Company to apply to the municipal authorities of the city of St. Louis for franchises to operate a street railway or extensions thereof in the public streets of said city, and (2) the constitutionality of that portion of the charter of said city authorizing a municipal regulation of public utilities as therein prescribed.
“No law shall be passed by the General Assembly granting the right to construct and operate a street railroad in any city, town, village or on any public highway without first acquiring the consent of the local authorities having control of the street or highway proposed to be occupied by said street railroad and the franchises so granted shall not be transferred without similar assent first obtained.” [See. 20, art. 12, Constitution of Missouri.]
The pertinent parts of the Public Service Act, under which the Commission is seeking to exercise the power here complained of by appellant, is as follows:
“If in the judgment of the Commission, additional tracks, switches, terminals or terminal facilities , . . or any other property, construction, apparatus, equipment, facilities or device for use by any . . . street railroad corporation in or in connection with the trans*438 portation of passengers . . . ought reasonably to be provided, or any repairs or improvements to or changes in any thereof in use ought reasonably- to be made, or any additions or changes in construction should reasonably be made thereto in order to promote the security or convenience of the public . . . or in order to secure adequate service or facilities for the transportation of passengers . . . the Commission shall, after a hearing, . . . make- and serve an order directing such repairs, improvements, changes or additions to be made within a reasonable time and in a manner to be specified therein, and every . . '. street railroad corporation is hereby required as directed to make all' repairs, improvements, changes and additions required of it by any order of the Commission served upon it . . .” [Sec. 49, Public Service Commission Act, p. 588, Laws 1913.]
The constitutional provision quoted is definite in its terms; discussion as to its purpose would therefore seem superfluous. Under ordinary circumstances little or no question can arise as to the uses and purposes of streets and public highways; and the wisdom in confiding their supervision and control to local authorities, being evident, need not be commented upon. The Constitution hut gives affirmative recognition to these facts. However, the enactment of the statute creating the Public Service Commission to effectuate its purpose in the supervision of public utilities, among others street railways, has, under section 49, supra, given or attempted to give certain powers to the Commission over streets and highways. The extent of this power under the Constitution is the matter here to be determined. While recognizing the rule that constitutional limitations upon legislative action must be construed in favor of the power of the Legislature- and he either expressly declared or clearly implied (State v. Wilson, 265 Mo. 1), it must also he borne in mind that when so expressed or implied they are to be construed as mandatory rather than directory (State ex rel. v. Hitchcock, 241 Mo. 433) and consequently exclusive in their terms.
The constitutional provision plainly requires as a prerequisite to the enactment of a valid statute for the construction and operation of street railroads that the consent of the local authorities therefor he. first acquired. While the language employed in the Constitution, if literally construed, may be held to be directed only to corporations seeking the privilege to construct and operate such public utilities, a reasonable construction of the provision will not justify this limitation upon its meaning; its purpose is not so much to limit the power and define the course to be pursued in securing the right to construct and operate as it is to declare where the power rests which is necessary to he invoked before the rights sought are granted.
The source of this power, viz., the local authorities, having been defined, the terms under which it is granted authorize the conclusion that it is absolute. It is a general rule, applicable here as elsewhere, that constitutional provisions are mandatory; their prohibitions and injunctions must therefore be obeyed. [State ex rel. v. Hitchcock, 241 Mo. 433; 8 Cyc. 762, and cases.] This being true, it is immaterial, so far as the application and extent of the power is concerned, whether the statute enacted in relation thereto he simply permissive, as is usually the case, or mandatory, as in the instant case; a condition precedent to the validity of the statute in any case is that the consent of the local authorities be first obtained. To obviate the application of the Constitution to the statute and as a consequence render the
The purpose of the order here sought to be enforced is to require, the appellant to extend its road; that this is sought to be accomplished by indirection is not material ; the resultant effect is the same. The order, while not directly requiring the appellant to make the extension, does require it to procure the consent of the proper authorities that (using the language of the order) “the construction of all of said tracks which may be so authorized shall be made within the time herein specified.” The purpose of the order is therefore evident, although it is mandatory more by inference than express declaration. Plowever this may be, the very words of the order carry with them a concession that consent is a prerequisite to its , enforcement. Consent such as the law recognizes cannot be the
This is not true of the remainder of the order made by the respondents, to which appellant has given compliance; its terms are well within the broad and full power given respondents to regulate and control public utilities, which power, so far as exercised, has not contravened any constitutional provision.
Holding, as we do, subdivision 2 of the order to be inoperative for the reasons stated, it has not been deemed necessary to discuss the question as to whether or not the attempted enforcement of said subdivision involves the -making of a contract; nor does the extent of the police power of the State enter into the question when the attempted exercise of the same would result in a violation of the organic law.
In the discussion of the question as to the binding force of subdivision 2, we have proceeded upon the
Furthermore, the Public Service Commission, being a creature of the statute, can only exercise such pewers as are expressly conferred on it; and the statute conferring such powers, to authorize action thereunder,
.That the city shall have power “to regulate the construction, maintenance, equipment, operation, service, rates and charges of public utilities, and compel, from time to time, reasonable extensions of facilities for such service. ” [Clause 13, sec. 1, art. 1, Charter, City of St. Louis.]
“The Board of Aldermen shall at all times have full power, to-be exercised by ordinance, over all public utilities now or hereafter existing in the city, and may regulate the charges for the use, service or product thereof and establish whatever requirements may be necessary to secure efficient use, service or products,
While not material to the validity of these sections, it is a matter of historical interest that they were adopted as a part of the new charter of the city of St. Louis which became operative about two years after the enactment of the Public. Service Act. The purpose of the latter was to provide a uniform system throughout the State for the regulation and control of public utilities, and to create and establish a board clothed with ample administrative powers to investigate, hear and determine all-matters concerning the conduct and management of such utilities, whether complaints in regard thereto were submitted by the representatives of the latter or their patrons. In thus providing by a State law a means whereby all questions of the character referred to might be heard and determined, it was evidently contemplated by the Legislature that local regulations, such as municipal charters and ordinances adopted for a like purpose as the State law, should, upon the enactment of the latter, become thereby superseded or abrogated; or, if adopted later than the State law, that they should be inoperative and void, otherwise confusion and the consequent defeat of the purpose of the statutes would result from conflicts of authority which would inevitably arise. While the freeholders in certain municipalities, for example the city of St. Louis, may, under the express authority of the Constitution (Sec. 16,# art. 9), frame and adopt a charter for their government, they do not thereby acquire the right to assume all powers the State may exercise within its limits, but only those incident to it as a municipality or which concern matters of purely local government. Judge Dillon (Mun. Corp. [5 Ed.], sec. 63), in discussing the rule as above announced, says in effect: “While a city may frame a charter for its government as a city, including all that is necessary to its conduct and management as a municipality, it does not thereby incorporate into its government all the power the State has for the protection of
We have' several times given express approval to this rule, notably in State ex rel. v. Telephone Go., 189 Mo. 83, where, in defining the meaning of the Constitution in providing that certain cities may frame charters for their own government, we said that “this provision is to be limited as stated in the foregoing rule,” and, further elaborating the application of the doctrine, declared that the Constitution does not “confer unlimited power on the city to regulate by its charter all matters strictly local, for there are many matters local to the city requiring.governmental regulation, which are foreign to the scope of municipal government. In none of the cases that have been before this court bringing into question the charters of St. Louis and Kansas City under the Constitution of 1875 (Sec. 16, art. 9) have we given to the constitutional provision any broader meaning than above indicated.” (Citing many Missouri cases.)
The power of the freeholders of the city of St. Louis in framing and adopting the present charter must be held, when properly exercised, to have been limited as in the rule stated. The control a-nd management of public utilities had then been provided for by the Public Service Commission Act; and such control was not a matter of purely local or municipal concern, but one subject to the State legislative will. The power having been thus classified and defined, the attempt of the framers of the charter to also provide for such control constituted an unwarranted invasion of a province clearly within the purview of the State. In so far, therefore, as clause 13 of section 1 of article 1 and section 2 of article 19 of the present charter of the city of St. Louis attempt to provide for the regulation of public utilities for the management and control of which express provision has been made in the Public Service Act, such clause and sections of said charter are declared to be inoperative and of no effect.
Concurrence Opinion
(concurring) — I fully concur in the opinion filed in this case, except as to that part of it which I understand holds that section 49 of the Public Service Commission Act, page 588, Laws 1913, empowers the Commission to order the company to construct and operate new and additional main lines of street railroads, - as distinguished from what are generally designated ás switches, side tracks, cross-overs and terminals, which 'are used in conjunction with main lines, to assist and facilitate the transportation of passengers over main lines the company has voluntarily constructed. Such side tracks, etc., are purely incidental to the operation of the main lines, and the Commission has and should have full and ample power to compel their construction; but I do not believe the Legislature intended or has the constitutional authority to compel the company, in the absence of an agreement by charter, or otherwise, to go into new territory and construct new main lines and operate cars over them for the transportation of passengers. That would compel the company, against its will, to invest its means in the construction of lines and conduct a transportation business, perhaps at a dead loss from start to finish. I can conceive nothing which would be more hazardous to capital than that, or which would more completely deprive a person of his property without his consent or without due process of law.
T might be perfectly willing to construct a railroad from Jefferson City to Columbia, and operate cars over the same for the transportation of freight and passengers, but that .is no reason why I should be compelled to extend the road north and west to the Iowa line for the same purposes; the former might be a good and paying
I know of no law or morals which require anyone to invest his means in a new business enterprise; but where he owns a public franchise of course he should be required to so use it as to yield the greatest good to the public, consistent with earning a reasonable remuneration on the investment.
For the reasons stated, I concur in the result.
ON MOTION TO MODIFY OPINION.
— The right to build a street railroad on Lee Avenue may be conceded to have been granted to the predecessor of the United Railways Company, as well as the right of the former to transfer its franchise to the latter company. This latter right is authorized under the 8th subdivision of section 3316, Revised Statutes 1909. The question confronting us here, however, is how long does this privilege or right continue? It was granted to the original company in April, 1892, and in April, 1893, the right was extended, no limitation being stated in the ordinance of extension. Almost twenty-four years have therefore elapsed since the extension of the right, 'and yet the attitude of the company holding the same has been one of complete inactivity. Under this state of facts is the presumption authorized that the company has abandoned its purpose of extending its line, and if this be true, can it, after the expiration of the period of time stated, now exercise the right originally conferred? If it cannot enforce this right, then it does not exist; and if it does not exist the Public Service Commission should not now be authorized by reason of the original grant to direct the railroad company’s conduct in regard to said street as the Commission is empowered to do cpncerning any other operative portion of the company’s franchise. Under the common law an easement may be lost by nonuser in twenty years. [3 Bl. Com. 262; Given v. Wright, 117 U. S. 648.] We need not concern ourselves as to
Despite the fact that these rulings were rendered in cases in which judicial action was invoked to forfeit the franchises, they constitute persuasive arguments in favor of the conclusion that when the facts, as in the instant case, involve the right to use the street, Lee Avenue, for the purpose of a street railway and same has not been exercised by the railway company for the period of time stated, the right cannot be enforced by the company and the converse of the proposition must be true, that the Public Service Commission is not authorized to enforce action by the railway company.
That the right of the Commission to direct the action of the railway company under its original grant to construct its road upon Lee Avenue does not now exist finds support by analogy in our ruling in State ex rel. v. Associated Press, 159 Mo. 410. This was an application for a writ of mandamus to compel the Associated Press to grant relator certain privileges which had been possessed under its charter by the respondent.
Concurrence Opinion
(concurring in-Per Curiam Opinion).— Whether the Railways Company -had abandoned its franchise by twenty-four years of non-user, was a judicial question (State ex rel. v. Railway Co., 140 Mo. l. c. 552; Roanoke Inv. Co. v. Railroad, 108 Mo. l. c. 64) which it was not the. province of the Public Service Commission to determine. Hence that body had no authority to direct the- appellant under the circumstances! disclosed <by the record, to begin work anew' under the fra-nchisé granted to its predecessor in April, 1892, and its order to that effect was properly set aside in the original opinion. Wherefore there is no merit in the motion for a rehearing.