STATE of West Virginia ex rel. UNITED ASPHALT SUPPLIERS, INC., Petitioner,
v.
Honorable David H. SANDERS, Judge of the Circuit Court of Berkeley County; Martinsburg L.L.C.; Giant Food Stores, Inc.; Richard D. Poole, Inc.; and United Paving, Inc., A West Virginia Corporation, Respondents.
Supreme Court of Appeals of West Virginia.
*136 Susan Snowden, Esq., Douglas S. Rockwell, Esq., Joseph L. Caltrider, Esq., Martin & Seibert, Martinsburg, West Virginia, Attorneys for Petitioner.
Michael D. Lorenson, Esq., Bowles, Rice, McDavid, Graff & Love, Martinsburg, West Virginia, David Flores, Esq., Harmon & Davies, P.C., Lancaster, Pennsylvania, Attorneys for Martinsburg L.L.C., Giant Food Stores & Richard D. Poole.
WORKMAN, Justice:
Petitioner United Asphalt Suppliers, Inc. ("United Asphalt") seeks a writ of prohibition in сonnection with the March 19, 1998, order of the Circuit Court of Berkeley County directing it to participate in arbitration proceedings. As a nonsignatory to any contract containing an arbitration clause, Petitioner argues that it shоuld be permitted to seek redress in a judicial forum. Having thoroughly reviewed this matter, we conclude that the lower court erred in ordering United Asphalt, as a nonsignatory to any arbitration agreement, to resolve its dispute through arbitrаtion. Accordingly, we determine that Petitioner is entitled to a writ of prohibition.
I. FACTS
On September 15, 1995, Martinsburg, L.L.C. (hereinafter referred to as "Owner" or "Respondent") and Giant Food Stores (hereinafter referred to as "Lessor" or "Respondent") entered into a contract with Richard Poole, Inc. (hereinafter referred to as "Contractor" or "Respondent") to build a supermarket in Martinsburg, West Virginia. The Contractor entered into a subcontract with United Paving to pave the parking lot area of the grocery store. The Petitioner in this case, United Asphalt, sold United Paving the asphalt materials used to pave the parking lot. When Contractor failed to pay United Paving under the subcontract,[1] Petitioner filed a mechanic's lien on January 17, 1997, against Owner and Lessee for the cost of the materials it had supplied to United Paving.
Petitioner initiated a civil action in circuit court to recover the $124,717.38 plus interest that it had incurrеd in material outlays. At the same time that Petitioner instituted its suit, United Paving filed a separate civil action against Owner, Lessee, and Contractor to recover on the subcontract. By order dated March 19, 1998, the circuit court consolidated the two actions seeking recompense for the asphalting of the parking lot. As part of the consolidation order, the lower court stayed further proceedings before that tribunal pending AAA arbitration prоceedings between Contractor and United Paving. In addition, the circuit court ordered Petitioner to participate in the arbitration proceeding.[2] Petitioner seeks a writ of prohibition to prevent enforcement оf the lower court's directive which required United Asphalt *137 to resolve its claims through arbitration.
II. Standard of Review
We recently set forth the applicable standard of review for writs of prohibition that do not involve jurisdictional concerns:
In determining whether to entertain and issue the writ of prohibition for cases not involving an absence of jurisdiction but only where it is claimed that the lower tribunal exceeded its legitimate powers, this Court will examine five factors: (1) whether the party seeking the writ has no other adequate means, such as direct appeal, to obtain the desired relief; (2) whether the petitioner will be damaged or prejudiced in a way that is not correctable on appeal; (3) whether the lower tribunal's order is cleаrly erroneous as a matter of law; (4) whether the lower tribunal's order is an oft repeated error or manifests persistent disregard for either procedural or substantive law; and (5) whether the lower tribunal's order raises new and important problems or issues of law of first impression. These factors are general guidelines that serve as a useful starting point for determining whether a discretionary writ of prohibition should issue. Although all five factors need not be satisfied, it is сlear that the third factor, the existence of clear error as a matter of law, should be given substantial weight.
Syl. Pt. 4, State ex rel. Hoover v. Berger,
III. Discussion
This Court has recognized in syllabus point one of Board of Education v. W. Harley Miller, Inc.,
Petitioner maintains that it is hornbook law that "mutuality of аssent is an essential element of all contracts." Bailey v. Sewell Coal Co.,
Respondents argue that the lower court correctly referred Petitioner's сlaims to arbitration based on the identity of interest between United Asphalt and United Paving. Based on the fact that the same individual Joe Duganowns and operates both United Asphalt and United Paving, Respondents contend that United Asphalt's сlaims are subject to arbitration.[3] In support of its *138 position, Respondents cite the decision of the Fourth Circuit Court of Appeals in J.J. Ryan & Sons v. Rhone Poulenc Textile, S.A.,
The J.J. Ryan case is frequently cited as authority for the existence of a well-recognized exception to the rulе that only parties who have actually signed an agreement containing an arbitration clause can be forced to arbitrate their claims. See Thomson-CSF, S.A. v. American Arbitration Ass'n,
While a clear exception to the rule against compelling nonsignatories to arbitrate does exist, the limited record upon which this case was submitted does not permit us to even consider whether that exception applies under the facts of this case. Although Respondents rely almost exclusively on the alleged similar identity in interests of United Asphalt and United Paving to support their contention that arbitration is proper,[4] the record bеfore us contains nothing other than a bare assertion of such identity in corporate interests.[5] We are understandably reluctant to accept such allegation as true without an affidavit or other document evidencing thе alleged similarity of ownership interest that Respondents avow.
Despite the recognized exception to the rule requiring express assent to require arbitration, there is equally "[p]ersuasive authority... that a ... court is not required to compel arbitration between parties who have *139 not agreed to such arbitration." Collins v. International Dairy Queen, Inc.,
Federal policy favors arbitration over litigation and requires a district court to resolve any doubt about the application of an arbitration clausе in favor of arbitration. Nevertheless, this policy "cannot serve to stretch a contract beyond the scope originally intended by the parties." The policy favoring arbitration does not compel the court to require arbitration of disputes if arbitration was not the intent of the parties.
Id. at 694 (citations omitted and quoting Seaboard Coast Line Ry. Co. v. Trailer Train Co.,
Based on the foregoing, a writ of prohibition is issued prohibiting enforcement of the March 19, 1998, order entered by the Circuit Court of Berkeley County directing United Asphalt to participate in arbitration prоceedings.
Writ granted.
Chief Justice DAVIS, Justices MAYNARD, STARCHER and McCUSKEY joined in the opinion of this court.
Justice McGRAW did not participate in the decision of this case.
NOTES
Notes
[1] The Contractor's failure to pay on the asphalting contract with United Paving stems from its cоntention that the work performed was defective and had to be corrected by another entity.
[2] This ruling was in response to Respondents' motion to require United Asphalt to arbitrate its claims.
[3] Respondents state additionally that United Paving admitted in the sister suit (97-C-339) that its claim for $142,135 included $124,717.38 worth of materials supplied to it by United Asphalt. Further, Respondents observe that the reason United Asphalt has not brought suit against United Paving is because it would have been suing itself. In its responses to interrogatories submitted to it by Respondents, however, United Asphalt denied that it refrained from suing United Paving based on Joe Dugan's ownership interests in United Paving and United Asphalt.
[4] Respondents also assert the policy-based contention that the Contractor may be forced to relitigate issues with United Asphalt in circuit court that have already been resolved, possibly to its favor, in arbitration. In addition, Respondents argue that arbitration is proper because United Asphalt alleged its claim with reference to the construction subcontract in its complaint.
[5] Moreover, although Respondents represent in their brief that Joe Dugan owns and operates both United Asphalt and United Paving, a review of United Asphalt's answers to Respondents' interrogatories indicates that Mr. Dugan is "principal and part owner" of both of those companies.
