This action was brought by appellant against the Central States Bridge Company on a contract with said company for certain material and labor used in constructing a bridge. Appellee bridge company had a contract with Marion county, Indiana, to build said bridge, and gave bond to the county, with appellee National Surety Company as surety. This action is also on the bond.
Various pleadings were filed, the case was tried, and the court, on request, made a special finding of facts and stated as a conclusion of law thereon that appellant was entitled to • recover the sum of $2,362.36. Appellant filed a motion for a new trial, which was overruled. Judgment was rendered on the finding and this appeal taken.
The errors assigned and presented for reversal are that the court erred (1) in its conclusion of law on the finding of facts, and (2) in overruling the motion for a new trial.
The court found, in substance, that the relator and each of the appellees were regularly organized corporations; that the Central States Bridge Company entered into a contract with Marion county, Indiana, to construct the Emerichsville bridge; that appellees executed the bond in question for the performance of said contract; that relator entered into a contract with appellee Central States Bridge Company to furnish stone to be used in constructing said bridge; that on
the sum of..................................$2,421.06
less the amount due to appellee bridge company under the set-off............................ 271.00
Leaving a net balance of.......................$2,150.06,
to which the court added interest from May 23, 1907, to January 19,1909, in the sum o£........ 212.30,
and stated the total amount due to be............$2,362.36.
The motion for a new trial alleges (1) that the amount of recovery is too small; (2) that the decision is not sustained by sufficient evidence; (3) that the decision is contrary to law; (4) that the court erred in admitting exhibits thirty-seven and fifty-two.
Appellees’ third paragraph of. answer' was addressed to the first paragraph of the complaint by way of set-off. This answer proceeded on the theory that relator furnished to appellee bridge company stone that did not comply with the contract and specifications, and. that said appellee was compelled to do and cause to be done certain work thereon before such stone could lawfully be used by it in constructing said bridge; that relator shipped certain stone to said appellee unprepared for use, and desired to shape and carve it at or near the bridge; that at the request of relator, appellee bridge company prepared grounds, appliances and sheds necessary for that purpose, and also furnished certain labor in handling said stone; that a bill of particulars thereof was made and filed with the answer, and Remand was made that the amount thereof be set off against any sum found due to appellant.
The evidence preliminary to the introduction of the sheets from the ledger showed, without serious conflict, that Mr. Dudley was, at the time the bridge was constructed, the bookkeeper for appellee bridge company; that other employes of said appellee had charge of the work and material mentioned in the set-off; that the time of the laborers and other items of the account were from day to day, by the men so in charge of the work, turned over to the bookkeeper; that he entered in the book offered in evidence the items as they
Appellant asserts that the account so kept, and identified as the book of said appellee, is not admissible in evidence on its own behalf. In support of this contention it cites the following cases: Pittsburgh, etc., R. Co. v. Noel (1881),
Some of the eases cited by appellant differ widely from the facts of this ease, and some deal with questions relating to private memoranda of a party, and not with shop-books or accounts kept in the due course of business, where the transactions are somewhat extensive and the items numerous. A failure to observe this distinction has led to some confusion. However, some of the cases cited by appellant tend to support its contention that the evidence offered should not have been admitted, because the account was kept by said appellee’s bookkeeper.
The latter class of cases seems to follow the early case of De Camp v. Vandagrift (1837),
In the case of Johnson v. Zimmerman (1908),
Appellant had ample opportunity to overcome this prima facie proof of value, if not correct, but there seems to have been no effort to do so. On the other hand, it is apparent from the record that the case ivas tried by appellant on the theory that it was entitled to pay for extra work and material occasioned by changes in the plans and specifications, and was defended by appellee bridge company, on the ground that such extras were by agreement of the parties
We find no available error in the record. The judgment is therefore affirmed.
