I. Introduction
{¶ 1} This is a regulatory-takings case. Regulatory-takings issues are complex and difficult and have defied attempts to provide a simple solution. Even the United States Supreme Court “quite simply, has been unable to develop any ‘set formula’ for determining when ‘justice and fairness’ require that economic injuries caused by public action be compensated by the government, rather than remain disproportionately concentrated on a few persons.” Penn Cent. Transp. Co. v. New York City (1978),
{¶ 3} RTG filed a complaint seeking a writ of mandamus to compel the state to appropriate the coal that the state’s UFM designation prevented RTG from mining. The appellate court held that imposition of the UFM regulation resulted in a taking of the coal that lies under the tracts of land that are located within the UFM-designated area and in which RTG owned coal rights only. However, the court held that the UFM designation did not result in a taking of the coal that lies under the tracts of land that RTG owned in fee. We reverse the judgment of the court of appeals in part and hold that the UFM regulation resulted in a taking of RTG’s coal that lies under the tracts of land in which RTG owned only coal rights and that are located within the UFM-designated area, as well as the coal rights that lie under the tracts of land that RTG owned in fee and that are located in the UFM-designated area.
{¶ 4} In a separate entry, the court of appeals denied RTG’s motion for attorney fees and costs. We also reverse this judgment and hold that RTG is due reasonable attorney fees and costs.
II. RTG’s Efforts to Mine Its Property
{¶ 5} James Rossiter is the president, CEO, and controlling shareholder of RTG. RTG is a coal-mining company. In 1982, RTG began investigating the viability of surface-mining coal in Valley Township, Guernsey County, just to the northwest of the village. RTG conducted extensive test drilling, which indicated the presence of high quality coal in this area. Consequently, RTG began acquiring property in this area for the purpose of mining coal. In all, RTG acquired approximately 500 acres of property through purchases in fee or purchases or leases of coal rights in sections 5, 7, and 8 of Valley Township. Approximately 200 acres of this property consisted of several tracts of property that RTG owned in fee (surface and coal rights). Approximately 300 acres consisted of several tracts of property in which RTG leased or owned coal rights only.
{¶ 7} After receiving the D-578 permit, Rossiter testified, RTG paid $100,000 to prepare the land for mining, including building a sediment pond, establishing drainage controls, removing and segregating topsoil, and building roads and ramps into the excavation.
{¶ 8} On June 5, 1987, pursuant to permit D-578-1, the permit area was revised to include an additional 77.2 acres adjacent to the original permit area. The DOR found that “[g]round water supplies monitored up to the date of this written finding have not displayed any significant changes in the quality and quality [sic] to the Village of Pleasant City’s well field.”
{¶ 9} On September 10, 1987, the aquifer that served the village’s water supply was designated a sole-source aquifer by the United States Environmental Protection Agency.
{¶ 10} On September 21, 1988, pursuant to R.C. 1513.073, the village filed a petition with the DOR that sought to designate 833 acres in Valley Township that lie below 820 feet in elevation as UFM because mining in this area would adversely affect the aquifer that supplies the village’s wells.
{¶ 11} On October 6, 1989, the chief of the DOR designated approximately 275 of the requested 833 acres as UFM. The chief determined that mining in this area could reduce the long-term productivity of the village’s water wells. The UFM designation affected property that RTG sought to mine. RTG and the village appealed from the chiefs decision to the Ohio Reclamation Board of Review (“board”).
{¶ 12} Before the appeal was decided, the area subject to the permit was increased by 8.4 acres. The board found that “[b]ased on the monitoring data collected by the Division of Water it is not anticipated that the quantity of water
{¶ 13} Ultimately, however, on June 16, 1994, the board issued an order that designated as UFM the entire 833 acres, which consisted of all lands in Sections 7 and 8 of Valley Township that lie below 820 feet. The UFM designation prevented RTG from mining much of its property.
III. RTG’s Mandamus Proceedings
{¶ 14} On September 21, 1994, RTG filed a complaint in the Franklin County Court of Common Pleas seeking a writ of mandamus to compel the state to appropriate the coal located within the UFM-designated area. RTG alleged that the UFM designation was a taking of its coal rights by regulation.
{¶ 15} On April 22, 1996, the trial court dismissed RTG’s complaint. On appeal, the Tenth District Court of Appeals reversed the trial court’s judgment and remanded the matter for a hearing and a determination whether a taking had occurred. State ex rel. R.T.G., Inc. v. Ohio Dept. of Natural Resources (Mar. 31, 1997), Franklin App. No. 96APE05-662,
{¶ 16} On August 6, 1998, RTG filed a complaint in the Tenth District Court of Appeals seeking a writ of mandamus to compel the state to initiate appropriation proceedings. State ex rel. R.T.G., Inc. v. Ohio Dept. of Natural Resources,
{¶ 17} The case was referred to a magistrate. In March 2000, RTG amended its complaint to add James and Phyllis Rossiter and the Myron Fishel Scholarship Trust as additional relators.
{¶ 18} On April 13, 2000, the state filed a motion for judgment on the pleadings against the Rossiters and the trust, alleging that their claims were barred by the statute of limitations. The magistrate denied the state’s motion, finding that a 21-year statute of limitations applied.
{¶ 19} For purposes of applying the takings analysis, the magistrate divided RTG’s land into two parcels. The first parcel consisted of the tracts of land that RTG owned in fee located within the UFM-designated area. The second parcel consisted of the tracts of land in which RTG owned or leased only coal rights located within the UFM-designated area.
{¶ 21} As to the coal rights, the magistrate applied the takings test of Lucas v. South Carolina Coastal Council (1992),
{¶ 22} Both RTG and the state filed objections to the magistrate’s decision. The appellate court held that the magistrate erred in applying a 21-year statute of limitations to the claims filed by the relators. However, it held that even in applying the more appropriate four-year statute of limitations, R.C. 2305.09(D), the relators’ claims were not time-barred.
{¶ 23} On the remaining issues, the appellate court adopted the magistrate’s decision in its entirety except with regard to the magistrate’s conclusion that RTG’s mining constituted a nuisance. The appellate court held that RTG’s mining was not a nuisance. Thus, the appellate court issued a writ of mandamus that compelled the state to appropriate the tracts of land in which RTG owned coal rights only and that were located within the UFM-designated area.
{¶ 24} On April 9, 2001, RTG moved the appellate court for an award of attorney fees and costs with regard to the mandamus action. The appellate court denied the motion.
{¶ 25} The state filed an appeal and RTG filed a cross-appeal of the judgment granting a writ of mandamus to compel the state to initiate appropriation proceedings. RTG also filed a separate appeal of the judgment denying RTG attorney fees and costs. We consolidated these appeals.
{¶ 26} There are several issues for this court to address. The first is whether the applicable statute of limitations expired before RTG moved to add the Rossiters and the trust as parties. The second is whether the state’s UFM designation resulted in a regulatory taking of RTG’s property. In order to answer this question, we must first determine the relevant parcel to which the takings analysis is applied. The third is whether RTG can recover attorney fees and costs.
{¶ 27} Appropriation cases “shall be governed by the law applicable in civil actions.” R.C. 163.22. Unless a particular statute contains a limitation, a civil action must be commenced within a period prescribed in R.C. 2305.03 to 2305.22. R.C. 2305.03. Neither R.C. Chapter 163 nor Chapter 2731 (mandamus) contains a statute of limitations. Therefore, we must examine R.C. 2305.03 to 2305.22 to determine the most appropriate limitation to apply in this case.
{¶ 28} This court has previously held that where a landowner sought to compel a railroad to commence an appropriation action for property that it had taken from the landowner pursuant to R.S. 3283, a predecessor of R.C. 4955.02, the appropriate statute of limitations was 21 years. Lawrence RR. Co. v. O’Harra (1891),
{¶ 29} We now disagree with the reasoning in O’Harra. We do not believe that an appropriation case “is a substitute for an action to recover the possession” of real estate. O’Harra,
{¶ 30} We also disagree with the appellate court’s finding that the limitation in R.C. 2305.09(D) applies to the claims filed by the Rossiters and the trust. R.C. 2305.09(D) provides a limitation “[f]or an injury to the rights of the plaintiff not arising on contract nor enumerated in sections 2305.10 to 2305.12[,] 2305.14 and 1304.35 of the Revised Code.” While none of the limitations listed in R.C. Chapter 2305 is a perfect fit for an action to compel appropriation proceedings, we find that the most appropriate statute of limitations is set out in R.C. 2305.07. It provides that “an action upon a contract not in writing, express or implied, or upon a liability created by statute * * * shall be brought within six years after the cause thereof accrued.” (Emphasis added.) R.C. 2305.07.
{¶ 32} In this case, the cause of action accrued when the board issued its final decision on June 16, 1994, which designated RTG’s property as unsuitable for mining. RTG filed its complaint on August 6, 1998. RTG moved to amend its complaint to add the Rossiters and the trust on March 7, 2000. Accordingly, the addition of the Rossiters and the trust was within six years of the date the action accrued. Thus, we affirm the appellate court’s determination that the Rossiters’ and the trust’s claims are not barred by the statute of limitations, albeit for different reasons.
V. Regulatory-Takings Law
{¶ 33} Both the United States and the Ohio Constitutions provide that private property shall not be taken for public use without just compensation. Fifth and Fourteenth Amendments to the United States Constitution; Section 19, Article I, Ohio Constitution; see, also, R.C. Chapter 163. The purpose of the Takings Clause is to prevent government from “forcing some people alone to bear public burdens which, in all fairness and justice, should be borne by the public as a whole.” Armstrong v. United States (1960),
{¶ 34} It was Justice Holmes who first recognized that “while property may be regulated to a certain extent, if regulation goes too far it will be recognized as a taking.” Pennsylvania Coal Co. v. Mahon (1922),
{¶ 35} Penn Cent. provides the proper taking test when the regulation deprives the property of less than 100 percent of its economically beneficial use. Tahoe-Sierra Preservation Council, Inc. v. Tahoe Regional Planning Agency (2002),
{¶ 36} In 1992, the Supreme Court again visited the regulatory-takings law in Lucas. The court acknowledged the Penn Cent. ad hoc balancing test, but recognized two situations in which a regulation results in a taking “without case-specific inquiry into the public interest advanced in support of the restraint.” Lucas,
{¶ 37} The rule in Lucas, recognizing these categorical takings, applies only “when a regulation deprives an owner of ‘all economically beneficial uses’ of his land.” (Emphasis in Lucas.) Tahoe-Sierra Preservation Council,
{¶ 38} Thus, under Lucas, if a regulation deprives the property of all of its economic value, there is no need to examine the policy behind the regulation, and a compensable taking results, unless the regulation merely prevents use of the property in a manner that creates a nuisance under state law.
{¶ 39} Accordingly, the United States Supreme Court has created a dichotomy in regulatory takings. Lucas applies where the regulation has deprived the property of all economic value, and Penn Cent. applies where the regulation deprives the property of less than all economic value.
A. Defining the Relevant Parcel, or The Denominator Problem
{¶ 40} The regulatory-takings analysis requires a court to compare the value of the property that has been taken by the regulation against the value of the
{¶ 41} Determining the relevant parcel of the takings fraction is critical because it usually determines the applicable takings test. In other words, determining how broadly or narrowly the relevant parcel is defined will determine whether there has been a complete deprivation of the economic value of the property, or whether a taking of something less has occurred. The more broadly the relevant parcel is defined, the less likely that a regulation will result in a complete economic deprivation and that the Penn Cent, test will apply; conversely, the more narrowly the relevant parcel is defined, the more likely that a regulation will result in a complete economic deprivation and that the Lucas test will apply.
{¶ 42} Determination of the denominator of the takings fraction has been a persistent and difficult issue. Palazzolo,
1. The Appellate Court Erred in Defining the Relevant Parcel
{¶ 43} In defining the relevant parcel, “[t]he effort should be to identify the parcel as realistically and fairly as possible, given the entire factual and regulatory environment.” Ciampitti v. United States (1991), 22 Cl. of Ct. 310, 319. The appellate court determined that RTG’s property consisted of two relevant parcels
2. The Relevant Parcel in the Vertical Context
{¶ 44} RTG argues that we should define the relevant parcel in the vertical context as including only the coal rights that lie under RTG’s property to the exclusion of any surface rights. The state asserts that coal rights cannot be severed from surface rights for purposes of this analysis and thus the relevant parcel must include both surface and coal rights. In this case, we agree with RTG.
{¶ 45} In Penn Cent., the court specifically declined to sever property rights in the vertical context for purposes of a takings analysis. In Penn Cent., a regulation prevented Penn Central from building a 55-story addition onto Grand Central Station. Penn Central argued that the regulation deprived it of its use of the air rights over Grand Central Station. The court declined to consider Penn Central’s air rights above Grand Central Station as a separate estate from the remainder of the property pursuant to the parcel-as-a-whole rule. Penn Cent.,
{¶ 46} Penn Central's nonseverability rule was reaffirmed in Keystone Bituminous Coal Assn.,
{¶ 47} However, subsequent to Penn Cent. and Keystone, some members of the court have expressed misgivings about the parcel-as-a-whole rule. In Lucas, the court discussed the uncertainty in determining the denominator and the resulting inconsistent pronouncements by the court in that regard. Lucas,
{¶ 48} That discussion in Lucas was merely dicta. However, property rights are defined by state law. Webb’s Fabulous Pharmacies, Inc., v. Beckwith (1980),
{¶ 49} We find that the criticism in Lucas regarding how to define the relevant parcel for the takings analysis is particularly relevant to coal rights in Ohio. Unlike other individual rights within the bundle of rights that make up a complete property estate, mineral rights are recognized by Ohio law as separate property rights. Moore v. Indian Camp Coal Co. (1907),
{¶ 50} It is undisputed that RTG is a company that surface-mines coal. It is also undisputed that RTG acquired all the property at issue herein, whether in fee or through coal leases or purchases, for the sole purpose of surface-mining the coal from these properties. The surface rights served as nothing more than an impediment to acquiring the coal. Thus, the right to mine coal “is what, and only what, this suit is all about.” Whitney Benefits, Inc. v. United States (C.A.Fed.1991),
3. The Relevant Parcel in the Horizontal Context
{¶ 51} RTG urges us to define the relevant parcel in the horizontal context as the property that is located within the UFM-designated area. The state urges the court to find that the relevant parcel is all 500 acres of RTG’s property pursuant to the parcel-as-a-whole rule. See Penn Cent. For the following
{¶ 52} Although contiguous tracts of property are typically considered as a single relevant parcel for purposes of a takings analysis, factual nuances may dictate a more flexible approach. Loveladies Harbor, Inc. v. United States (C.A.Fed.1994),
{¶ 53} Of the approximately 500 acres of contiguous property at issue herein, approximately 100 of these acres are located outside the UFM-designated area. The state contends that these 100 acres of property are part of the relevant parcel because this property includes coal rights.
{¶ 54} RTG has submitted evidence that of the approximately 500 acres at issue herein, the state’s UFM designation prevented it from mining approximately 218 “coal acres,” or 1.3 million tons of coal. RTG has admitted that fringe amounts of coal exist outside the regulated area. However, RTG’s mining of the coal was dependent upon economies of scale. Therefore, when the UFM designation prevented RTG from mining a majority of its coal reserves within the regulated area, it made mining those minimal reserves outside the UFM-designated area economically impracticable.
{¶ 55} Because there is no evidence that the coal outside the regulated area can be economically mined independent of the reserves in the regulated area, we hold that the relevant parcel in the horizontal context is limited on these facts to RTG’s coal that is located within the UFM-designated area.
4. The Relevant Parcel
{¶ 56} Merging our analyses regarding the relevant parcel in vertical and horizontal contexts, we hold that the relevant parcel in this case is the remaining coal located within the UFM-designated area.
B. The UFM Designation Destroyed RTG’s Coal Rights
{¶ 57} “What makes the right to mine coal valuable is that it can be exercised with profit.” Pennsylvania Coal,
{¶ 58} A categorical taking under Lucas is compensable unless the proposed use of the property is a nuisance. Lucas,
{¶ 59} In examining the nuisance element of Lucas, the appellate court herein, citing Taylor v. Cincinnati (1944),
{¶ 60} The appellate court then concluded that coal mining is not an absolute nuisance, because it can be conducted safely when care is taken. The court concluded that coal mining is also not a qualified nuisance, because coal mining itself is not nuisance, but rather a lawful activity subject to permit. Finally, the appellate court found that RTG had acted in a reasonable manner in mining the property and, until the UMF designation was issued, was allowed to mine the property pursuant to permits.
{¶ 61} After examining the law and the record in this case, we adopt the appellate court’s analysis regarding the issue of nuisance in its entirety and consequently find that RTG’s mining of its property did not constitute a nuisance as a matter of law for purposes of the takings analysis. Accordingly, the UFM designation resulted in a compensable taking of RTG’s coal.
VI. Attorney Fees
{¶ 62} RTG also sought an award of attorney fees and costs pursuant to R.C. 2335.39 and 2731.11, which was denied by the appellate court.
{¶ 63} Pursuant to R.C. 2335.39, the state must pay attorney fees if (1) the state was not substantially justified in initiating the matter in controversy, (2) there are no special circumstances that make the award unjust, (3) the moving party is not the state but is a party to the legal action at issue, and (4) the moving party prevailed in the legal action.
{¶ 64} The state argues that under R.C. 2335.39, fees are recoverable where the state initiates the legal action in question, as opposed to the state initiating the matter in controversy that resulted in the legal action. See Highway Valets, Inc. v. Ohio Dept. of Transp. (1987),
{¶ 65} R.C. 2335.39(B)(2) states:
{¶ 67} We construe this language to permit fees where the state initiates either the conduct that gave rise to the litigation or initiates the litigation caused by the controversy. Had the General Assembly intended to permit fees only where the state initiates the litigation, then it could have indicated that fees would be awarded only where the state initiated “litigation,” as opposed to the more general language of “matter in controversy” that was actually used.
{¶ 68} Furthermore, to construe this language otherwise would lead to an absurd result in this case. Clearly the purpose of R.C. 2335.39 is to protect citizens from unjustified state action. If fees under R.C. 2335.39 were permitted only where the state initiated the legal action, the protection that R.C. 2335.39 provides would not be available where landowners, such as RTG in the instant case, were compelled to initiate legal action to get relief from the state.
{¶ 69} The state also argues that it was substantially justified in not filing a condemnation action against RTG’s property. The state has the burden of proving that its position in initiating the matter in controversy was substantially justified. R.C. 2335.39(B)(2). Clearly the state has the authority to regulate mining pursuant to R.C. 1513.39. However, in this case, the regulation resulted in a taking of RTG’s property. While the state would have had no obligation to compensate RTG if RTG’s mining would have been a nuisance, the state still had the obligation to file a condemnation action and have that issue determined by a court. Thus, we find that the state has failed to show that it was substantially justified in failing to file a condemnation action in this case.
{¶ 70} Because we find that the state was not substantially justified in failing to initiate appropriation proceedings, and RTG otherwise qualifies for attorney fees under R.C. 2335.39, we hold that the appellate court erred in denying RTG attorney fees and reverse the appellate court on that issue.
{¶ 71} Pursuant to R.C. 2731.11, where a complaint seeking a writ of mandamus judgment is rendered in favor of the relator, the relator is entitled to costs. Therefore, RTG is also entitled to costs.
VII. Conclusion
{¶ 72} We hold that the state’s UFM designation resulted in a categorical taking of all of RTG’s coal rights pursuant to Lucas. Therefore, we reverse the
{¶ 73} We also reverse the judgment of the court of appeals that denied RTG attorney fees and costs, and remand the cause for the appellate court to determine RTG’s reasonable attorney fees and costs.
Judgments affirmed in part, reversed in part, writ issued and cause remanded.