181 Ind. 316 | Ind. | 1914
This was a suit on a contractor’s bond, instituted by appellant, the State of Indiana, on the rela
The special finding, among other things, discloses the following facts: A petition was filed before the board of commissioners, to construct a drain under the Five Mile Drainage Act of 1891. Acts 1891 p. 455, §5690 Burns 1901. The proposed drain was ordered established. Land of appellee, Peter Frantz, was assessed for construction in the sum of $764.50, and construction allotment No. 608 of the drain was apportioned to his land. Appellee, Frantz, entered into a contract for the construction of such allotment, for the sum of $764.50, and, to secure the performance of the contract, the bond in suit was executed. This bond was in a sum double the contract price. The engineer’s estimate was that allotment No. 608 would require the excavation of 411 cubic yards of stone, at the estimated cost of $1 per yard, and 1,414 cubic yards of earth at the estimated cost of 25 cents per yard. Appellee, Frantz, and some other contractors, commenced the construction of several allotments under their contracts when they discovered that the engineer’s estimates of the rock and earth excavation in their respective allotments were erroneous, and that in fact there was much more rock excavation required than esti
The court concludes: (1) that the law is with the defendants; (2) that the order of the board changing the specifications was void; (3) that appellee Frantz is not liable on the bond, because the extra cost of construction was not included in the engineer’s estimates; (4) that the obligation of the bond was discharged by the performance of work in value equal to the contract price; (5) appellee Frantz'was not bound by the contract and bond to perform work on the allotment in a value greater than the estimated cost of the work; (6) that the extra cost of completing the work should be assessed against all the lands benefited in proportion to benefits accruing. Appellant excepted to each conclusion of law except the second.
Appellees have filed a motion to dismiss this appeal. The reasons assigned go to the merits of the cause, and, if sufficient, would warrant an affirmance of the judgment below, rather than a dismissal of the appeal. Ryder v. Shea (1913), 180 Ind. 574, 103 N. E. 411. The motion is overruled.
Appellees seek to meet appellant’s contentions here by declaring that all the court’s conclusions of law, excepting the first one should be disregarded; that the action of the trial court in overruling the demurrer to the seventh paragraph of answer, if erroneous, was harmless because the complaint is insufficient. Counsel for appellees zealously contend that the superintendent of construction is not a proper relator to bring an action for the breach of a contractor’s bond; that the superintendent is
By §9, of the Five Mile Drainage Act of 1891 (Acts 1891 p. 455, §5698 R. S. 1901), the contractor was liable on his bond for all damages accruing by reason of his failure to complete the job within the time required. By the complaint here, a recovery is sought for the added cost of completing the allotment, for the added services of the superintendent, and for attorney fees. The value of each item is found by the court.
It is manifest that the trial court erred in the third, fourth, fifth, and sixth conclusions of law. The engineer’s estimates did not constitute any element of the contract. By its terms, appellee Frantz agreed “to construct and fully complete in the manner as set forth in the report of the viewers * * * allotment No. 608 * * * for the sum of $764.50”. This he failed to do, and such failure resulted in the necessary reletting of the contract for the completion of the work, and the performance of additional services by the superintendent, and for such failure appellee Frantz is liable on his bond. We are of the opinion that there is no liability for attorney fees. No provision therefor is found in the contract, and the statute in' force when it was executed provided for no such liability. 13 Cyc. 80, 81.
Note. — Reported in 103 N. E. 833. See, also, under (1) 3 Cyc. 197; (3) 14 Cyc. 1052; (4) 3 Cyc. 450. As to effect of architects’ certificates and engineers’ estimates when provided for in contract, see 56 Am. St. 312.