729 S.E.2d 808 | W. Va. | 2012
In this construction lawsuit we are asked to examine a circuit court order refusing to compel a plaintiff corporation to arbitrate its claims against three defendant corporations. The circuit court entered two orders in which it found that the arbitration clauses in the
The defendants have petitioned this Court for a writ of prohibition to halt enforcement of the circuit court’s orders, and to compel the plaintiff to arbitrate its claims. After consideration of the record, and the briefs and the arguments of the parties, we grant the requested writ of prohibition as moulded.
I. Facts and Procedural Background
Respondent (and plaintiff below) Glenmark Holding, LLC (“Glenmark”), owns an office building in Morgantown, West Virginia, called the “Suncrest Executive Office Plaza” or “United Center.” Glenmark alleges that it took delivery of the newly constructed building in August 2004 and immediately began experiencing serious problems with the heating, ventilation and air-conditioning (“HVAC”) system.
On June 13, 2011, Glenmark brought a lawsuit claiming that the HVAC system had been improperly designed, that it had been improperly constructed, that the HVAC equipment used in the system was defectively designed or manufactured, or that the system had been improperly maintained. Glenmark named seven defendants, including the general contractor that oversaw construction of the building (petitioner Morgan Keller, Inc.), and the two companies that manufactured and later maintained the HVAC equipment (petitioner York International Corporation and its parent corporation, petitioner Johnson Controls, Inc., hereafter called the “York petitioners”).
On August 8, 2011, petitioner Morgan Keller, Inc., filed a motion to compel Glenmark to arbitrate its claims against Morgan Keller. Morgan Keller asserted that the duty to arbitrate arose from a contract Morgan Keller signed with Glenmark on August 1, 2003, to construct the office building. The contract was on a form drafted by the American Institute of Architects and was titled “ALA Document A101-1997, Standard Form of Agreement Between Owner and Contractor.” The contract incorporates by reference the “General Conditions of the Contract for Construction,” also known as “ALA Document A201-1997.” Document A201-1997 contains an express arbitration clause which states, “Any Claim arising out of or related to the Contract ... shall ... be subject to arbitration.”
Likewise, the two York petitioners filed a separate motion to compel Glenmark to separately arbitrate all of its claims against the York petitioners. The York petitioners manufactured some of the HVAC equipment that was in Glenmark’s office building; among various theories in its complaint, Glenmark now asserts that the equipment was “defective, ineffective, inefficient, and not suitable for use on that building[.]” However, after construction of the building was completed, in December 2004, Glenmark entered into a “Preventative Maintenance Agreement” with the York petitioners for periodic inspections of and routine maintenance on the HVAC system. The maintenance agreement has an arbitration clause that states, in part;
All claims, disputes and controversies arising out of or relating to this contract, or the breach thereof, shall, in lieu of court action, be submitted to arbitration in accordance with the Commercial Arbitration Rules of the American Arbitration Association[.]
Glenmark asserts that the York petitioners breached the maintenance agreement and carelessly failed to keep the HVAC equipment in working order.
The circuit court conducted a hearing on the petitioners’ two motions on September 8, 2011. The circuit court acknowledged that arbitration is preferred over litigation because of its supposed “expeditious, economic resolution of issues.” The circuit court noted, however, that by granting the petitioners’ motions that the petitioners would expend additional, not fewer, resources responding to the parties’ claims and cross-claims. Granting the motions would sever one individual lawsuit by Glenmark against seven defendants into at least three proceedings: (1) one lawsuit against six defendants, including the York petitioners for defective HVAC equipment; (2) one arbitration proceeding with Morgan Keller, for negligent general contracting services; and (3) one arbitration proceeding with the York petitioners over negligent maintenance of the HVAC equipment. Further, the petitioners and the other defendants (none of whom were parties to the arbitration agreements) would have to resolve their cross-claims in circuit court.
In an order dated October 5, 2011, the circuit court denied the York petitioners’ motion to compel arbitration. In an order dated October 19, 2011, the circuit court similarly denied petitioner Morgan Keller’s motion. In both orders, the circuit court determined that compulsory arbitration would be insufficient and inequitable to resolve all of Glen-mark’s claims against the petitioners, and “would result in an unnecessarily delayed ‘piecemeal’ resolution of this conflict and the waste of judicial resources.” Because of the claims and cross-claims of the parties, compelling arbitration “would permit neither the Plaintiff nor the Defendants to fully and effectively adjudicate their various claims and defenses.” The circuit court went on to find that the arbitration clauses in both contracts were unconscionable and, therefore, unenforceable.
On November 3, 2011, petitioner Morgan Keller and the two York petitioners filed a petition for a writ of prohibition with this Court. The petitioners ask that we halt enforcement of the circuit court’s orders, and that we halt all proceedings by Glenmark against the petitioners before the circuit court. As we discuss below, we grant the requested writ as moulded.
II. Standard of Review
A petition for a writ of prohibition is an appropriate method to obtain review by this Court of a circuit court’s decision to deny or compel arbitration.
In eases where the trial court is alleged to have exceeded their authority, we set forth the following standard of review:
III. Discussion
A. Threshold Issues in a Motion to Compel Arbitration
The petitioners assert that the interpretation of the arbitration clauses is governed exclusively by the Federal Arbitration Act (“the FAA”). “Under the Federal Arbitration Act, 9 U.S.C. § 2, a written provision to settle by arbitration a controversy arising out of a contract that evidences a transaction affecting interstate commerce is valid, irrevocable, and enforceable, unless the provision is found to be invalid, revocable or unenforceable upon a ground that exists at law or in equity for the revocation of any contract.”
When a trial court is required to rule upon a motion to compel arbitration pursuant to the Federal Arbitration Act, 9 U.S.C. §§ 1-307 (2006), the authority of the trial court is limited to determining the threshold issues of (1) whether a valid arbitration agreement exists between the parties; and (2) whether the claims averred by the plaintiff fall within the substantive scope of that arbitration agreement.8
The FAA permits the court to refuse enforcement of an arbitration agreement to the extent “such grounds ... exist at law or in equity for the revocation of any contract.”
The petitioners assert that the FAA leaves no place for the exercise of discretion by a trial court. They assert that once the FAA is invoked, a trial court is required, as a matter of law and without question or delay, to compel a respondent to participate in arbitration. The petitioners state in their brief to this Court, “because the Federal Arbitration Act controls and because [Glenmark’s] claims were subject to arbitration, the Circuit Court lacked subject matter jurisdiction to consider Glenmark’s claims.” We disagree.
“The FAA has no talismanie effect; it does not elevate arbitration clauses to a level of importance above all other contract
B. The Doctrine ’of Unconscionability and Piecemeal Litigation
Respondent Glenmark argues that the circuit court correctly found that, under the common law of contracts, the arbitration clauses are unconscionable. In part, Glen-mark contends that because the arbitration clauses will result in inefficient, inconsistent, and expensive “piecemeal” litigation, the clauses may be considered to be unconscionable. As we discuss below, we reject Glen-mark’s contention.
In Brown v. Genesis Healthcare Corp. (“Brown 7”),
“The doctrine of uneonscionability means that, because of an overall and gross imbalance, one-sidedness or lop-sidedness in a contract, a court may be justified in refusing to enforce the contract as written. The concept of unconscionability must be applied in a flexible manner, taking into consideration all of the facts and circumstances of a particular ease.”
Undertaking “[a]n analysis of whether a contract term is unconscionable necessarily involves an inquiry into the circumstances surrounding the execution of the contract and the fairness of the contract as a whole.”
“Under West Virginia law, we analyze unconscionability in terms of two component parts: procedural unconseionability and substantive unconscionability.”
This Court set forth the following guidelines for determining procedural unconseionability in Syllabus Point 17 of Brown I:
Procedural unconscionability is concerned with inequities, improprieties, or unfairness in the bargaining process and formation of the contract. Procedural unconscionability involves a variety of inadequacies that results in the lack of a real and voluntary meeting of the minds of the parties, considering all the circumstances surrounding the transaction. These inadequacies include, but are not limited to, the age, literacy, or lack of sophistication of a party; hidden or unduly complex contract terms; the adhesive nature of the contract; and the manner and setting in which the contract was formed, including whether each party had a reasonable opportunity to understand the terms of the contract.25
We are cognizant, however, that “[i]n most commercial transactions it may be assumed that there is some inequality of bargaining power, and this Court cannot undertake to write a special rule of such general application as to remove bargaining advantages or disadvantages in the commercial area, nor do we think it necessary that we undertake to do so.”
“Substantive unconscionability involves unfairness in the contract itself and whether a contract term is one-sided and will have an overly harsh effect on the disadvantaged party. The factors to be weighed in assessing substantive unconscionability vary with the content of the agreement. Generally, courts should consider the commercial reasonableness of the contract terms, the purpose and effect of the terms, the allocation of the risks between the parties, and public policy concerns.”
We recognized in Brown I that “[n]o single, precise definition of substantive unconscionability can be articulated”
With these general guidelines in mind, we now turn to the circuit court’s determination that the petitioners’ arbitration clauses were inequitable, unconscionable and unenforceable because they would result in piecemeal litigation. It is axiomatic that an arbitration agreement is a contract usually between just two parties. However, lawsuits — particularly construction lawsuits— are often multi-party affairs. As one legal commentator perceived, enforcing an arbitration agreement between two parties of a multi-party lawsuit virtually guarantees an inefficient and inconsistent outcome:
Arbitration should be quick, easy, and efficient. Instead, by sometimes omitting crucial parties, AIA arbitration may foster inefficiency and inconsistency. Although the legal system is better suited to handle multiparty disputes, the contractor and owner generally are committed to two-party arbitration under the AIA contract.
The AIA arbitration contract may exacerbate inherent complexities of construction litigation by insisting on two-party arbitration while other parties litigate their similar claims. As a result, the owner and prime contractor are at odds with each other at the inception of the dispute, when they should be working together to solve their problems. Ultimately, the result is that crucial parties need not arbitrate, and the parties must present the same evidence, the same witnesses, and the same arguments before two fact-finding tribunals, often with conflicting decisions and without res judicata as to many of the other crucial parties. This is a failure that neither the arbitration rules nor the laws of most states are prepared to solve.
A treatise on construction arbitration agreements observed that neither the facts of the instant case, nor the legal quandaries presented by the parties’ arguments, are that uncommon:
Construction disputes often involve more than two parties. A construction defect, for example, an inadequately operating air-conditioning system, could be the fault of the architect, the mechanical engineer, the general contractor, the mechanical subcontractor, the electrical subcontractor, or the manufacturer of the air-conditioning equipment.
When presented with situations where an entire controversy cannot be resolved by arbitration because not all the parties have agreed to arbitrate the dispute, courts seek to consolidate arbitration proceedings. Failing to consolidate proceedings, some courts order piecemeal resolution of the dispute, usually requiring arbitration first and litigation later. Other courts have applied a balancing test that sometimes results in nullification of the arbitration agreement.32
The circuit court recognized the legal quandary in both of its orders.
*497 Given that arbitration would be insufficient to resolve all of [Glenmark’s] claims against all Defendants named in this action, and that the cross-claims filed by various Co-Defendants against [the petitioners] would survive, an important policy underlying arbitration — namely speedy resolution of the conflict and conservation of the parties’ resources — is not applicable in these circumstances.... The Court finds persuasive [Glenmark’s] argument that it must be allowed to present evidence of each Defendant’s role in the specification, selection, installation and maintenance of the subject HVAC system, so that the degree of each Defendant’s contributing culpability can be considered and allocated. As a result, the Court finds that compulsory arbitration would result in an unnecessarily delayed “piecemeal” resolution of this conflict and the waste of judicial resources.
We find that the circuit court’s orders are eminently reasonable, logical and just. They are also, unfortunately, directly contrary to the United States Supreme Court’s interpretations of the Federal Arbitration Act.
The Supreme Court has interpreted the FAA “to require that if a dispute presents multiple claims, some arbitrable and some not, the foi'mer must be sent to arbitration even if this will lead to piecemeal litigation.”
In accordance with the holdings of the Supreme Court, we hold that the FAA requires that if a lawsuit presents multiple claims, some subject to an arbitration agreement and some not, the former claims must be sent to ai’bitration — even if this will lead to piecemeal litigation. A trial court may not issue a blanket refusal to compel arbitration of some of a party’s claims, merely because the party has other claims which are not subject to the ai’bitration agreement, or because other parties in the lawsuit are not subject to the arbitration agreement.
After examining both of the circuit court’s orders, we find that the circuit court overstepped its authority. The circuit court’s blanket refusal to enforce the petitioners’ arbitration clauses — merely because it would be inequitable and inefficient to Glenmark, to the petitioners, and to the remaining defendants — ran afoul of the FAA The FAA permits courts to protect parties from grossly unfair, unconscionable bargains; it does not permit courts to protect commercial litigants from stupid or inefficient bargains willingly and deliberately entered into.
We now consider the arbitration agreement of each petitioner, and examine wheth
C. The Morgan Keller AIA Agreement
In its October 19, 2011 order denying petitioner Morgan Keller’s motion to compel arbitration, the circuit court found that the arbitration clause was procedurally and substantively unconscionable. Respondent Glen-mark argued, and the circuit court agreed, that the clause was procedurally unconscionable because boilerplate language in the AIA A101-1997 and A201-1997 documents established an overly complex procedure for dispute resolution. After reviewing the record, we disagree.
Glenmark’s complaint indicates that this was a $7.5 million contract. Both Glen-mark and Morgan Keller were commercially sophisticated parties familiar with large construction projects. While the AIA contract is a form, it was not drafted by Morgan Keller and offered to Glenmark on a “take-it- or-leave-it” basis. The form was in an electronic format, and the parties were free to amend and alter the form, and did. (For instance, the parties altered a paragraph to state that any arbitration is to occur in Morgantown, West Virginia.) While the dispute resolution process devised in the AIA contract is complex, the terms creating the process were not themselves hidden or unduly complex for commercial entities. And we see nothing in the record to indicate that the contract was formed in a manner or setting that prevented Glenmark from having a reasonable opportunity to understand the terms of the arbitration clause. We reject the circuit court’s determination that Morgan Keller’s arbitration clause was procedurally unconscionable.
The circuit court also found that the Morgan Keller arbitration agreement was substantively unconscionable. The circuit court’s decision was based, in part, on the finding that the arbitration agreement would result in piecemeal litigation, a finding we rejected earlier in this opinion. The circuit court also found that because the Morgan Keller agreement limited Glenmark’s right to recover consequential damages, the agreement precluded the plaintiff from effectively vindicating its rights.
After reviewing the AIA arbitration clause in the Morgan Keller contract, we reject the circuit court’s finding that it was substantively unconscionable. The arbitration clause is not one-sided; it limits the rights of both Morgan Keller and Glenmark to recover consequential damages.
Our law requires a showing of both procedural and substantive unconseionability, at
D. The York Petitioners’ Maintenance Agreement
To reiterate, Glenmark has asserted two different legal positions for recovery from the two York petitioners. First, Glenmark claims that as its office building was being constructed in 2003 and 2004, the York petitioners designed, manufactured, and/or installed an HVAC system that was defective and not fit for the ordinary purposes of the building. Second, after the building was constructed, Glenmark signed a maintenance agreement in December 2004 under which the York petitioners would perform routine maintenance on the HVAC equipment. Glenmark claims that the York petitioners breached this agreement after December 2004, and carelessly performed maintenance bn the system.
The parties agree that only the maintenance agreement contains an arbitration clause. The York petitioners assert that they are entitled to a writ of prohibition to compel all of Glenmark’s claims (those that pre-date and post-date the maintenance agreement) to be submitted to arbitration. The circuit court rejected this assertion, and determined that only Glenmark’s claims arising from the maintenance agreement and which post-date the agreement were covered by the arbitration clause. The circuit court refused to extend the arbitration clause to encompass causes of action arising from the specification, selection, design, manufacture, or installation of the HVAC system, all of which occurred before the maintenance agreement was signed. We agree.
The arbitration clause contained within the maintenance agreement states that, “All claims, disputes and controversies arising out of or relating to this contract, or the breach thereof, shall, in lieu of court action be submitted to arbitration[.]” By its terms, the contract applies only to “professional maintenance services on the air conditioning system” owned by Glenmark. The contract explicitly excludes “repairs, parts, installation or service calls made at the customer’s request.” As we stated in Brown /, “parties are only bound to arbitrate those issues that by clear and unmistakable writing they have agreed to arbitrate. An agreement to arbitrate will not be extended by construction or implication.”
In its October 5, 2011 order, the circuit court went on to find that the York petitioners’ arbitration clause was unconscionable and, therefore, unenforceable. The circuit court found that the arbitration clause was proeedurally unconscionable for one reason: that it was a form contract of adhesion. We reject this conclusion because, while adhesion contracts are worthy of additional scrutiny,
The circuit court next determined that the York petitioners’ maintenance agreement was substantively unconscionable because it limits Glenmark’s “compensatory, special, indirect, consequential or incidental damages.”
Our law requires a showing of both procedural and substantive uneonseionability, at least in some small measure. Neither has been shown. Accordingly, we find that Glen-mark failed to establish that the York petitioners’ arbitration agreement was unconscionable. The circuit court therefore erred in refusing to enforce the agreement to compel Glenmark to arbitrate its claims arising from the post-construction maintenance agreement. The writ of prohibition sought, as moulded, is warranted.
IV. Conclusion
For the foregoing reasons, the writ of prohibition, as moulded, is granted.
Writ granted as moulded.
. The remaining four defendants are KA, Inc., the architectural firm that designed the building and oversaw its construction; Thorson Baker & Associates, Inc.; Comefri U.S.A., Inc.; and City Plumbing and Heating.
. AIA Document A201-1997, "General Conditions of the Contract for Construction,” ¶ 4.6.1.
.As the circuit court stated to counsel for the two York petitioners:
If I grant your motion for arbitration ... that means that you and Glenmark will participate in arbitration. As I see it there are 1, 2, 3, 4 other defendants.... A bunch whose claims need to be arbitrated to see what degree of culpability, if any, each of those defendants has with regard to the damages that Glenmark claims. If they are not participating in the arbitration, then those issues would still have to be litigated and they would be litigated here in circuit court ...
Now, that to me flies in the face of the stated policy behind arbitration and the reason why arbitration is looked upon favorably, and that is to avoid large costs of litigation.
. See, State ex rel. Saylor v. Wilkes, 216 W.Va. 766, 613 S.E.2d 914 (2005); State ex rel. Dunlap v. Berger, 211 W.Va. 549, 555, 567 S.E.2d 265, 271 (2002).
. Syllabus Point 1, Crawford v. Taylor, 138 W.Va. 207, 75 S.E.2d 370 (1953).
. Syllabus Point 4, State ex rel. Hoover v. Berger, 199 W.Va. 12, 483 S.E.2d 12 (1996).
. Syllabus Point 9, Brown v. Genesis Healthcare Corp., 228 W.Va. 646, 724 S.E.2d 250 (2011) ("Brown I")
. Syllabus Point 2, State ex rel. TD Ameritrade, Inc. v. Kaufman, 225 W.Va. 250, 692 S.E.2d 293 (2010).
. 9 U.S.C. § 2.
. Syllabus Point 9, Brown I.
. See Peabody Holding Co., LLC v. United Mine Workers of America, Intern. Union, 665 F.3d 96, 102 (4th Cir.2012) ("As in any garden-variety contractual claim, the intent of the contracting parties guides our analysis.”).
. Brown I, 228 W.Va. at 671, 724 S.E.2d at 275.
. Volt Information Sciences, Inc. v. Board of Trustees of Leland Stanford Junior Univ., 489 U.S. 468, 476, 109 S.Ct. 1248, 103 L.Ed.2d 488 (1989)
. Rent-A-Center, West, Inc. v. Jackson, 561 U.S. -, -, 130 S.Ct. 2772, 2776, 177 L.Ed.2d 403 (2010).
. Id., (citing Buckeye Check Cashing, Inc. v. Cardegna, 546 U.S. 440, 443, 126 S.Ct. 1204, 163 L.Ed.2d 1038 (2006) and Volt Information Sciences, 489 U.S. at 478, 109 S.Ct. 1248).
. Prima Paint Corp. v. Flood & Conklin Mfg. Co., 388 U.S. 395, 404 n. 12, 87 S.Ct. 1801, 18 L.Ed.2d 1270 (1967).
. Brown v. Genesis Healthcare Corp., 228 W.Va. 646, 724 S.E.2d 250 (2011) (“Brown I"), vacated on other grounds by Mannet Health Care Center, Inc. v. Brown, 565 U.S. -, -, 132 S.Ct. 1201, 1204, 182 L.Ed.2d 42 (2012).
. See Brown v. Genesis Healthcare Corp., 229 W.Va. 382, 729 S.E.2d 217 (2012) (“Brown II").
. Syllabus Point 12, Brown I. See also, Syllabus Point 2, Ashland Oil, Inc. v. Donahue, 159 W.Va. 463, 223 S.E.2d 433 ("[P]rovisions of an agreement ... which, if applied strictly, are so one-sided as to lead to absurd results, will be declared unconscionable.").
. Syllabus Point 3, Troy Min. Corp. v. Itmann Coal Co., 176 W.Va. 599, 346 S.E.2d 749 (1986).
. Syllabus Point 4, Art’s Flower Shop, Inc. v. Chesapeake and Potomac Telephone Co. of West Virginia, Inc., 186 W.Va. 613, 413 S.E.2d 670 (1991).
. Syllabus Point 2, Orlando v. Finance One of West Virginia, Inc., 179 W.Va. 447, 369 S.E.2d 882 (1988).
. Brown I, 228 W.Va. at 681, 724 S.E.2d at 285.
. Syllabus Point 20, Brown I.
. Syllabus Point 17, Brown I.
. Ashland Oil, Inc. v. Donahue, 159 W.Va. 463, 474, 223 S.E.2d 433, 440 (1976).
. Syllabus Point 19, Brown I.
. Brown I, 228 W.Va. at 684, 724 S.E.2d at 288.
. Id., 228 W.Va. at 683, 724 S.E.2d at 287 (quoting Hayes v. Oakridge Home, 122 Ohio St.3d 63, 69, 908 N.E.2d, 408, 414 (2009)).
. Id., 228 W.Va. at 684, 724 S.E.2d at 288.
. Thomas E. McCurnin, "Two-Party Arbitrations in a Multiple-Party World,” 26 Construction Lawyer 5 (Winter, 2006).
. James Acret, Construction Arbitration Handbook % 5:1 (2nd Ed.2006).
. The proper name for the legal quandary is the "intertwining doctrine.”
Narrow arbitration provisions give rise to the prospect of determining disputes in more than one forum, because some disputes may fall within the narrow clause and others outside. This can create inefficiencies and, if the claims are sufficiently interrelated, can create a potential for inconsistent outcomes. The same undesirable results could occur in situations where broad arbitration clauses are used but the dispute involves numerous parties, some of which are obligated to arbitrate and others who are not. Prior to 1985, courts often addressed this situation by exercising what they believed was discretion in deciding that, in the event that arbitrable and nonarbitrable claims were sufficiently intertwined, arbitration would be denied in favor of resolving all the claims in one forum. The exercise of discretion in these circumstances was known as the “doctrine of intertwining.”
Philip L. Bruner, Patrick J. O'Connor, Jr., 6 Bruner & O’Connor on Construction Law § 20:58 (2002). As we discuss later, as a result of two decisions of the United States Supreme Court in 1983 and 1985, the intertwining doctrine has all but disappeared from arbitration jurisprudence.
. KPMG LLP v. Cocchi, 565 U.S. -, -, 132 S.Ct. 23, 24, 181 L.Ed.2d 323 (2011) (per curiam), citing Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. 213, 217, 105 S.Ct. 1238, 84 L.Ed.2d 158 (1985).
. KPMG LLP v. Cocchi, 565 U.S. at -, 132 S.Ct. at 24.
. Moses H. Cone Memorial Hosp. v. Mercury Const. Corp., 460 U.S. 1, 20, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983).
. Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. at 217, 105 S.Ct. 1238 (quoting Dickinson v. Heinold Securities, Inc., 661 F.2d 638, 646 (7th Cir.1981)).
. Dean Witter Reynolds, Inc. v. Byrd, 470 U.S. at 217, 105 S.Ct. 1238.
. See, e.g„ Brown I, 228 W.Va. at 683, 724 S.E.2d at 287 ("[M]utuality of obligation is the locus around which substantive unconscionability analysis revolves.”).
. See, e.g., In re: American Express Merchants' Litigation, 667 F.3d 204 (2nd Cir.2012) (quoting In re American Express Merchants' Litigation, 554 F.3d 300, 315 (2nd Cir.2009) and Green Tree Financial Corp.-Alabama v. Randolph, 531 U.S. 79, 92, 121 S.Ct. 513, 148 L.Ed.2d 373 (2000)) ("[Wjhen a party seeks to invalidate an arbitration agreement on the ground that arbitration would be prohibitively expensive, that party bears the burden of showing the likelihood of incurring such costs.” Plaintiffs presented evidence establishing that the out-of-pocket cost of individually arbitrating their dispute would be prohibitive — "just for the expert economic study and services, would be at least several hundred thousand dollars” to recover average damages of $5,252 — effectively depriving plaintiffs of the statutory protections of the antitrust laws.)
. The limitation on consequential damages was added to the AIA documents as a result of Perini Corp. v. Greate Bay Hotel & Casino, Inc., 129 N.J. 479, 610 A.2d 364 (1992). In Perini, a construction manager was paid $600,000 to oversee renovation of a hotel casino. When completion of the project was delayed for four months, the casino filed an arbitration proceeding seeking consequential damages in the form of lost profits. A panel of arbitrators awarded the casino $14.5 million. Following Perini, the AIA amended its form documents to provide for a waiver of the parties' consequential damages. See Werner Sabo, Legal Guide to AIA Documents, § 4.85 at 521 (5th Ed.2008).
. Syllabus Point 10, Brown I.
. Syllabus Point 18 of Brown I states:
A contract of adhesion is one drafted and imposed by a party of superior strength that leaves the subscribing party little or no opportunity to alter the substantive terms, and only the opportunity to adhere to the contract or reject it. A contract of adhesion should receive greater scrutiny than a contract with bargained-for terms to determine if it imposes terms that are oppressive, unconscionable or beyond the reasonable expectations of an ordinary person.
.Brown I, 228 W.Va. at 682, 724 S.E.2d at 286 (citation omitted).
. The York petitioners' maintenance agreement states, in part:
Limitations of Liability ...
In no event shall Company liability for direct or compensatory damages exceed the pay-merits received by Company from Customer under this contract, nor shall Company be liable for any special, indirect, consequential or incidental damages of any nature.