State ex rel. General Electric Supply Co. v. Jordano Electric Co.State ex rel. General Electric Supply Co. v. Jordano Electric Co.
The issue before us is whether CMHA is entitled to a setoff against the funds in escrow to remedy Jordano’s failure to perform its contract with CMHA. For the reasons that follow, we hold that CMHA is entitled to the setoff and the court of appeals correctly affirmed the trial court’s grant of partial summary judgment to CMHA.
To determine the rights of the parties we must examine the statutory scheme set out in R.C. Chapter 1311 concerning mechanics’ liens filed by subcontractors, materialmen, laborers, and mechanics on escrow payments to contractors on public projects. The pertinent statutes are
Once the principal contractor receives notification from the owner or lien claimant that a statement has been filed,
Finally,
The parties followed the above described procedure in this case: GESCO, COD, and Fairfield filed their statements, the amount due Jordano was placed in escrow, Jordano failed to dispute the claims, and GESCO resorted to mandamus to recover its past due payments. The plan proceeded smoothly, and even though Jordano and Merchants were unable to pay the lien claimants, the escrow funds provided an alternate source of funds for at least partial payment. The difficulty arose only when CMHA claimed a setoff.
The purpose of this statutory scheme is to protect subcontractors, materialmen, and the like from defaulting principal contractors: “
What is also clear from the case law is that the rights of GESCO, COD, and Fairfield as lien claimants are subordinate to those of the principal contractor, Jordano. In Bullock v. Horn (1886),
The lien claimants do not dispute the fact that Jordano did not earn the final payment that CMHA paid into escrow. Jordano has no claim to that payment since the bankruptcy court provided in lifting the automatic stay that Jordano’s estate abandoned its interest in the subject matter of this action. Standing in the shoes of Jordano, then, the lien claimants have no right to the escrow funds in the face of CMHA’s claim to a setoff.
The lien claimants assert, however, that the 1963 and 1975 amendments to
Before it was amended in 1963,
The 1963 amendment provided for sums to be detained from interim payments to the principal contractor to satisfy the mechanics’ liens. According to GESCO, COD, and Fairfield this amendment represents a recognition by the legislature that interim payments become due to the principal contractor before a project is completed and that when they become due the lien claimants become entitled to the aggregate sum of their claims. GESCO, COD, and Fairfield argue, then, that the 1963 amendment accelerated the time for fixing the lien claimants’ rights to the detained portion of interim payments. It is argued that at the time the owner determines to disburse a subsequent (interim) payment to the principal contractor, the owner has determined that the entire payment, including that portion detained for lien claimants, is earned by the contractor, and the lien claimants’ rights in the detained portion are fixed. From that moment, according to appellants, the owner may not claim a setoff against the detained funds.
GESCO and the other appellants further maintain that by the 1975 amendment creating the escrow scheme, the legislature intended that the public owner lose its interest in the funds as soon as the payment is placed in escrow and it becomes available for distribution. Appellants argue that this
Dinneen simply does not address the issue raised in this case because the owner in Dinneen did not claim a setoff. The owner in Dinneen had merely contended that mandamus did not lie until a court had issued an order directing whom the owner should pay and what portion of the escrow funds each lien claimant should receive. Id. at 84,
As for appellants’ argument that the 1963 and 1975 amendments to
The statute that does apply here is
The parties do not dispute CMHA's assertion that Jordano failed to rewire Sullivant Gardens according to the terms of its contract with CMHA, nor do they deny that it was necessary for CMHA to compensate another contractor for substitute performance. The escrow payment to Jordano constituted consideration for Jordano’s performance of the bargained-for electrical work. Provision 37b of
There is no question that GESCO, COD, and Fairfield lived up to the terms of their agreements with Jordano. The lien claimants faithfully followed the statutory scheme intended to protect them from Jordano’s breach of its contracts with them. Unfortunately, because the funds in escrow are insufficient to compensate all the innocent parties to this action, the claims of GESCO, COD, and Fair-field must yield to CMHA’s right to a setoff, in keeping with the provisions of
Judgment affirmed.