68 Ohio St. 3d 377 | Ohio | 1994
Lead Opinion
The issue in this case is whether National acted contrary to law in replacing its West Raymond mill with a like-kind mill without obtaining a PTI from the OEPA. Resolution of this issue hinges on an interpretation of certain administrative rules promulgated by the Director of OEPA.
Former R.C. 3704.03(F)
“[N]o person shall cause, permit, or allow the installation of a new source of air pollutants * * * or cause, permit, or allow the modification of an air contaminant source * * * without first obtaining a permit to install from the director. * * * ” (Emphasis added.)
“Install” and “installation” are defined in Ohio Adm.Code 3745-31-01(1) as “to construct, erect, locate, or affix any air contaminant source or any treatment works.” “Air contaminant source” means “each separate operation or activity that results or may result in the emission of any air contaminant.” Ohio Adm.Code 3745-31-01(D). See, also, R.C. 3704.01(C). Particulate matter, such as dust, is within the definition of “air contaminant.” Ohio Adm.Code 3745-31-01(C). See, also, R.C. 3704.01(B).
Ohio Adm.Code 3745-31-01(K) defines “new source” as “any air contaminant source * * * for which an owner or operator undertakes a continuing program of installation or modification or enters into a binding contractual obligation to undertake and complete, within a reasonable time, a continuing program of installation or modification, after January 1, 197k * * *•” (Emphasis added.)
Essentially, the requirement of a PTI, with respect to a new source review, can be triggered by the “installation” or “modification” of an air contaminant source that was installed or modified after January 1, 1974. For the most part, a “modification” does not occur unless there is a physical change or deviation in the method of operation of an air contaminant which increases emissions allowable under applicable law, or results in the release of a contaminant into the air that was not previously emitted. Ohio Adm.Code 3745-31-OKJ). The precise focus in this case is not whether a “modification” has in fact occurred but, rather, whether the replacement of the Raymond mill in 1987 with a virtually identical mill constituted the “installation” of an air contaminant source, as that term is defined and set forth in relevant administrative rules.
Appellee asserts, and the court of appeals concluded, that the replacement Raymond mill was “installed,” as defined in Ohio Adm.Code 3745-31-01(1), and, therefore, the mill constituted a “new source of air pollutants” within the meaning of Ohio Adm.Code 3745-31-02(A). National and amici curiae extensively challenge the appellee’s and the court of appeals’ interpretation of Ohio Adm.Code 3745-31-02(A) and they especially take issue with the contention that the replacement of the like-kind Raymond mill amounted to the “installation” of a “new source” of air contaminants. National asserts that “installation,” as defined and used in the rules, does not include like-kind replacement of a piece of equipment which is a component of a complex manufacturing operation. National suggests that the OEPA should have focused on whether the replacement of the mill resulted in a “modification” of an air contaminant source as opposed to whether the replacement amounted to the “installation” of a new source of air contaminants.
In considering the parties’ contentions, the trial court determined that Ohio Adm.Code 3745-31-02(A) does not govern the replacement of any air contaminant source but, rather, requires a PTI only for the installation of a new source of air contaminants or the modification of an air contaminant source. The trial court
As set forth above, “install,” as defined in the administrative rules, means to construct, erect, locate, or affix any air contaminant source. Ohio Adm.Code 3745-31-01 does not, however, provide a definition of the terms “construct,” “erect,” “locate” or “affix.” According to Black’s Law Dictionary (6 Ed.1990) 542, “erect” and “construct” are synonymous terms. “Construct” is defined as “[t]o build; put together; make ready for use * * * [and] is distinguishable from ‘maintain,’ which means to keep up, to keep from change, to preserve.” Id., Black’s at 312. Further, “construction” is defined as “ * * * [t]he creation of something new, as distinguished from the repair or improvement of something already existing. * * * ” (Emphasis added.) Id. See, also, United, States v. Narragansett Improvement Co. (D.R.I.1983), 571 F.Supp. 688, 693 (“The uniform conclusion is that ‘construction’ imports the creation of something new and original that did not exist before.”). In addition, the word “locate” means “ * * * [t]o decide upon the place or direction to be occupied by something not yet in being * * *.” (Emphasis added.) Black’s at 939.
Literally construed, the word “installation,” as defined in Ohio Adm.Code 3745-31-01(1) and used in Ohio Adm.Code 3745-3l-02(A), connotes the establishment or formation of something that has yet to be in existence. The term, however, does not explicitly or implicitly refer to the replacement of a virtually identical (like-kind) component of a complicated manufacturing scheme.
In reaching our conclusion, we are conscious of the long-accepted principle that considerable deference should be accorded to an agency’s interpretation of rules the agency is required to administer. See State ex rel. Brown v. Dayton Malleable, Inc. (1982), 1 Ohio St.3d 151, 155, 1 OBR 185, 189, 438 N.E.2d 120, 123. See, also, Jones Metal Products Co. v. Walker (1972), 29 Ohio St.2d 173, 181, 58 C.C.2d 393, 398, 281 N.E.2d 1, 8. Further, this court has stated on previous occasions that an administrative rule that is issued pursuant to statutory authority has the force of law unless it is unreasonable or conflicts with a statute covering the same subject matter. Youngstown Sheet & Tube Co. v. Bindley (1988), 38 Ohio St.3d 232, 234, 527 N.E.2d 828, 830. Here, appellee interprets the word “installation” to embrace the replacement of a like-kind part of a rather complex manufacturing process, thereby requiring National to undergo the rigors of a new-source review. The interpretation of “installation” proposed by appellee is, in our opinion, unreasonable.
It is interesting to note that following the trial court’s ruling the OEPA proposed that Ohio Adm.Code 3745-31-01(D) be amended to negate the interpretation reached by the trial court. Included in the appendix of National’s brief is a
Appellee’s interpretation of “installation” here is interesting in light of the requested revisions by the OEPA and Waltermeyer. If the definition of “installation” is as clear as appellee presently urges there would be no need for a clarification to “solidify” the OEPA’s position. Further, to allow appellee to broadly interpret a rule that the OEPA has tacitly admitted is less than all-inclusive would be tantamount to unannounced rulemaking in violation of R.C. Chapter 119. See, generally, Brost v. Ohio State Med. Bd. (1991), 62 Ohio St.3d 218, 581 N.E.2d 515. See, also, R.C. 3704.04.
Appellee further implies that a decision that National was not required to obtain a PTI as a condition to replacing the Raymond mill diminishes the OEPA’s authority to further the purposes of R.C. Chapter 3704. However, this implication lacks merit when one considers the broad discretionary powers conferred upon the OEPA by the General Assembly.
The broad range of powers given to the Director of OEPA by the General Assembly are delineated in R.C. 3704.03. In essence, the OEPA has been given authority to develop programs and implement standards for the prevention, control and abatement of air pollution consistent with the federal Clean Air Act, Section 7401 et seq., Title 42, U.S.Code. R.C. 3704.03(E); see, also, R.C. 3704.02(A)(2). In carrying out its responsibilities, the OEPA acts as a guardian of the law. More specifically, the OEPA can exercise its authority and designate a representative to inspect any facility (public or private), at any reasonable time, to ensure that the facility is in full compliance with applicable law. R.C. 3704.03(L). Along with the discretion to inspect, the authorized representative can take samples, conduct tests and examine records or reports with respect to any emission of air contaminants. Id. Also, prior to the issuance of a PTI or renewal of a PTO, the OEPA can require the applicant “to install such equipment and conduct such tests and analyses as the director finds reasonable and necessary to determine adequately the amount and content of any emissions from such sources, the ambient air quality at the proposed site and in areas that may be affected by emissions from such sources, and any violation or potential violation of Chapter 3704. of the Revised Code or the regulations or orders promulgated thereunder.” R.C. 3704.031. A person who violates any rule
There is no question that Ohio’s Air Pollution Control Law has some sharp teeth. The OEPA has been provided with the authority and the means to effectuate the goals of Ohio’s Air Pollution Control Law.
We are aware of and in complete agreement with the purposes of R.C. Chapter 3704, and commend the Director of OEPA for his efforts in promulgating rules to further protect and enhance the quality of air in this state. Ohio’s Air Pollution Control Law was enacted to allow the Director of OEPA to adopt rules and maintain standards for the prevention, control and abatement of air pollution consistent with the federal Act. R.C. 3704.02(A)(2). Of equal importance, R.C. Chapter 3704 was also established for the purpose of protecting and enhancing Ohio’s air resources “so as to promote the public health, welfare, and economic vitality of the people of the state.” (Emphasis added.) Former R.C. 3704.-02(A)(1). Am.Sub.S.B. No. 258, 138 Ohio Laws, Part I, 847, 849. (The current version adds “productive capacity” to this list of things to be protected.) To reflect this purpose, the General Assembly has repeatedly stated that actions required by the OEPA must not only be technically feasible but economically reasonable. See, e.g., R.C. 3704.03(1) and (R).
As is evident, the General Assembly intended to strike a balance between the prevention, control and abatement of air pollution and excessive regulation or unwarranted interruption of a business to the point where it can no longer function competitively at a local, national or even worldwide level. Obviously, the balance sought by the General Assembly can be lost if the quest for clean air is accompanied by excessive regulation. Excessive regulation can disrupt vital functions of a business, threatening the company’s very existence. Similarly, exposing a business to regulations not explicitly covered by statute or rule could have an equally detrimental impact. R.C. Chapter 3704 sets forth the role a business, as an employer, plays in society. Indeed, the goal for clean air should not, unless there is no other solution, lead to possible lost jobs or irrecoverable employment opportunities.
We also note that appellee, in concluding that the court of appeals’ decision would not have a detrimental impact on businesses in this state, states that “[b]usinesses are not going to have to cease operations simply because they choose to repair or replace a piece of equipment. Yet, they will have to plan
We believe that absent a precise and reasonable directive from the General Assembly or a reasonable rule properly promulgated by the Director of OEPA on the subject, a business entity should not be forced to encounter the potential costs and delays associated with a PTI.if a component of a manufacturing process becomes inoperable and the component is replaced with a like-kind piece of equipment. Thus, we hold that a like-kind replacement of a piece of equipment that is a component of a complex manufacturing operation involving the emission of an air contaminant does not constitute “the installation of a new source of air pollutants” within the meaning of Ohio Adm.Code 3745-31-02(A).
Keeping in mind the purposes of R.C. Chapter 3704, we must strive to reach a balance between promoting and enhancing clean air and protecting and encouraging economic growth and opportunities for the people of this state. This requires that business entities not be subjected to an interminable task of dealing with excessive regulation or requirements not explicitly covered by statute or rule. Therefore, any uncertainty with regard to the interpretation of R.C. Chapter 3704 and rules promulgated thereunder should be construed in favor of the person or entity (manufacturer or otherwise) affected by the law. Here, the mere replacement of the Raymond mill with a like-kind Raymond mill did not constitute the “installation” of a new source of air pollutants as that term is used in Ohio Adm.Code 3745-31-02(A). If the General Assembly or the Director of OEPA wishes to bring “replacement” within the ambit of “installation,” they must use the proper channels.
Accordingly, the judgment of the court of appeals is reversed. The judgment of the trial court is reinstated.
Judgment reversed.
. R.C. 3704.03(F) was amended, effective December 22, 1992, Sub.H.B. No. 359, and October 29, 1993, Am.Sub.SJB. No. 153.
Dissenting Opinion
dissenting. While I agree with the majority’s assessment that the agency’s interpretation would produce some harsh results in this case, I do not believe that it is the function of this court .to assay the wisdom of a policy choice made by the agency entrusted to make such a decision.
This case presents two questions: (1) whether the Raymond mill at National’s limestone plant may be ranked as an “air contaminant source”; and, if so, (2) whether the term “installation” can be construed to encompass like-kind replacement. Although the majority’s analysis is focused entirely on the issue of whether like-kind replacement constitutes an “installation,” its ultimate holding inexplicably includes a factual determination that the Raymond mill at National’s limestone plant is “a piece of equipment that is a component of a complex manufacturing operation.” (Emphasis added.) The majority, therefore, makes a sub silentio finding that the Raymond mill does not rank as an “air contaminant source.” It is necessary, therefore, to consider both prongs of the definition of “new source,” i.e., “air contaminant source” and “installation.”
I. Standard of Review
Although the majority gives lip service to “the long-accepted principle that considerable deference should be accorded to an agency’s interpretation of rules the agency is required to administer,” it does not pay homage to that principle.
The General Assembly has enacted in R.C. Chapter 3704 a technical and complex regulatory scheme to comply with the federal Clean Air Act, Section 7401 et seq., Title 42, U.S.Code, and to deal with the problems of air pollution that confront Ohio. It has entrusted the OEPA with the responsibility of administering the statute, and has delegated to it certain policy-making authority. In contrast, “[j]udges are not experts in the field, and are not part of either political branch of the Government.” Chevron U.S.A., Inc. v. Natural Resources Defense Council, Inc. (1984), 467 U.S. 837, 865, 104 S.Ct. 2778, 2793, 81 L.Ed.2d 694, 717. Thus, where the legislature “has not directly addressed the precise question at issue, the court does not simply impose its own construction on the statute, as would be necessary in the absence of an administrative interpretation. Rather, if the statute is silent or ambiguous with respect to the specific issue, the question for the court is whether the agency’s answer is based on a permissible construe
In determining whether the agency’s interpretation is permissible under the statute, the United States Supreme Court in Chevron, supra, explained that:
“When a challenge to an agency construction of a statutory provision, fairly conceptualized, really centers on the wisdom of the agency’s policy, rather than whether it is a reasonable choice within a gap left open by Congress, the challenge must fail. In such a case, federal judges — who have no constituency— have a duty to respect legitimate policy choices made by those who do. The responsibilities for assessing the wisdom of such policy choices and resolving the struggle between competing views of the public interest are not judicial ones: ‘Our Constitution vests such responsibilities in the political branches.’ TVA v. Hill, 437 U.S. 153, 195 [98 S.Ct. 2279, 2302, 57 L.Ed.2d 117, 147] (1978).” Chevron, 467 U.S. at 866, 104 S.Ct. at 2793, 81 L.Ed.2d at 717.
Instead of respecting these principles, the majority steadfastly violates them. Concerned with the “sharp teeth” of Ohio’s Air Pollution Control Act, the majority takes it upon itself “to reach a balance between promoting and enhancing clean air and protecting and encouraging economic growth.” In so doing, the majority, in direct contrast to every tenet of agency deference, actually proposes that “any uncertainty with regard to the interpretation of R.C. Chapter 3704 and rules promulgated thereunder should be construed in favor of the person or entity (manufacturer or otherwise) affected by the law,” and that the balance should tip in favor of the business entity “absent a precise and reasonable directive from the General Assembly or a reasonable rule properly promulgated by the Director of OEPA on the subject.” As a result, the majority has turned the principle of agency deference on its head in order to substitute its policy choices for the policy choices made by the agency entrusted to make such choices.
II. Air Contaminant Source
Since the majority has failed to explain the basis of its finding that National’s Raymond mill is “a piece of equipment that is a component of a complex manufacturing operation,” it has left its reasoning to speculation. The majority tells us neither why the Raymond mill itself falls short of being a “separate operation or activity,” nor what the “complex manufacturing operation,” of which the Raymond mill is a “component,” consists of. In any event, it is clear that it is permissible, both legally and factually, for the OEPA to rank the Raymond mill as an air contaminant source.
The EPA now gives the states the option of adopting the following plantwide definition of “stationary source” in their state implementation plans:
“Stationary source means any building, structure, facility, or installation which emits or may emit any air pollutant subject to regulation under the Act.
“Building, structure, facility, or installation means all of the pollutant-emitting activities which belong to the same industrial grouping, are located on one or more contiguous or adjacent properties, and are under the control of the same person (or persons under common control) * * *.” Sections 51.165(a)(1)® and (ii) (Part D permit requirements for state implementation plans), and 51.166(b)(5) and (6), Title 40, C.F.R.
The EPA, however, continues to approve state implementation plans that deviate from the plantwide definition if the state “specifically demonstrates that the submitted definition is more stringent, or at least as stringent, in all respects.” Sections 51.165(a)(1) and 51.166(b), Title 40, C.F.R. See, also, Section 7416, Title 42, U.S.Code.
In clear contrast to the EPA-authorized plantwide definition of “stationary source” as a combination of “all of the pollutant-emitting activities which belong to the same industrial grouping,” the General Assembly and the OEPA have chosen to define an “air contaminant source” as “each separate operation or activity.” (Emphasis added.) R.C. 3704.01(C); Ohio Adm.Code 3745-31-01(D). In turn, the OEPA has consistently interpreted R.C. 3704.01(C) and Ohio Adm.Code 3745-31-01(D) to allow for the ranking of individual pieces of equipment as sources of air pollution subject to PTI review.
In fact, the PTI regulations compel the conclusion that there are times when an operation or activity will consist entirely of a single piece of equipment. Ohio Adm.Code 3745-31-03(A)(l) contains a laundry list of new air contaminant sources that are exempted from a PTI review. Many of the sources in this list are specifically identified as equipment. By negative implication, this listing evinces an intent to allow individual pieces of equipment to be ranked as air contaminant sources if not excepted. If the definition of “air contaminant source” precluded the ranking of equipment as a source, there would be no need to exempt certain specific types of equipment.
Clearly, it is improper for this court to find as a matter of law that the only operation or activity taking place at National’s limestone plant is the entire “complex manufacturing operation.” To do so is to incorporate into the statute and regulation the very plantwide definition of “air contaminant source” that the General Assembly and the OEPA chose not to adopt. Further, the record in this case clearly reveals sufficient facts to support the finding made by the OEPA that the operation or activity of grinding at National’s plant is a separate operation or activity consisting entirely of the Raymond mill. The production of hydrate begins with the extraction of dolomitie limestone from the earth through the use of explosives. The extracted limestone is crushed and screened, then burned in kilns at approximately 2,300 degrees Fahrenheit. The result is dolomitie quicklime. When the quicklime cools, it is screened and fed into a hydrator, where it is mixed with water to form hydrate. The .hydrate is then fed into the Raymond mill, where it is ground into finer material in accordance with customer specifications. It is at this point in production that the air-polluting particles at issue in this case are generated. The only reason that these particles are not released at the site of the mill is that they are trapped, along with the rest of the hydrate, in an air stream that circulates through an essentially closed-air system, and are routed to a baghouse where they are filtered out before the air is emitted into the atmosphere.
III. Like-Kind Replacement Versus Installation
The majority concludes that “[t]he interpretation of ‘installation’ [as including ‘replacement’] proposed by appellee is, in our opinion, unreasonable.” In reaching its conclusion, the majority selectively extrapolates dictionary definitions of the terms “construct,” “construction” and “locate” to illustrate that “[l]iterally construed, the word ‘installation,’ as defined in Ohio Adm.Code 3745-31-01(1) and used in Ohio Adm.Code 3745-341-02(A), connotes the establishment or formation of something that has yet to be in existence.” (Emphasis sic.)
As the majority points out, the terms “construct” and “construction” mean the creation of something new, as distinguished from the repair or improvement of something already existing. See Webster’s Ninth New Collegiate Dictionary (1983) 281; Black’s Law Dictionary (6 Ed.1990) 312. This, however, does not disclose whether the replacement of an entire air contaminant source is to be considered a mere repair or improvement, or whether it is to be considered as the creation of something new. Depending upon the statutory or contractual context of their use, the terms “construct” and “construction” can mean “replacement” as opposed to repair or improvement; and the terms “replace” and “replacement” can mean the comparable exchange of something new for something old or worn out, as opposed to the maintenance or repair of something existing. See 8A Words and Phrases (1951) 470; 37 Words and Phrases (1950) 11; Webster’s Ninth New Collegiate Dictionary, supra, at 999.
It would indeed be an interesting display of linguistic gymnastics were a member of the majority to attempt to convince the carpet salesperson, who replaced his worn-out carpet with like-kind carpet, that installation charges are unwarranted because the word “ ‘installation’ connotes the establishment or formation of something that has yet to be in existence.”
Clearly, the use of such common, ordinary meanings is woefully inadequate to decisively classify replacement sources of air pollution as falling outside the definition of “installation.” The majority’s conclusion, resting as it does on such a precarious foundation, is unstable at best.
One of the stated purposes of Ohio’s Air Pollution Control Act is to enable the state, through the Director of Environmental Protection, to develop a program that is consistent with the federal Clean Air Act. R.C. 3704.02(A)(2) and
“The provisions of Chapter 3704. of the Revised Code, all regulations adopted pursuant to Chapter 3704. of the Revised Code, and all permits * * * shall, to the extent reasonably possible, be construed to be consistent with the federal Clean Air Act * * *.” Am.Sub.S.B. No. 258, 138 Ohio Laws, Part I, 847, 849.
The federal Clean Air Act embodies a construction/modification dichotomy similar to the OEPA’s installation/modifieation dichotomy set forth at Ohio Adm.Code Chapter 3745-31. As relevant here, the Clean Air Act provides for various sets of requirements applicable to newly constructed or modified stationary sources of air pollution.
Like Ohio’s regulations, the federal Act makes its permitting provisions applicable to new sources of air pollution. Sections 7410(A)(2)(D), (2)(I) and (4), Title 42, U.S.Code.
In enacting the Clean Air Act, particularly the Clean Air Act Amendments of 1977, Pub.L. 95-95, 91 Stat. 685, Congress had fully considered the proper political “balance between promoting and enhancing clean air and protecting and encouraging economic growth” which the majority of this court has taken upon itself to reconsider. The House Committee Report succinctly specifies that the section of the Act governing nonattainment areas seeks “the dual goals of attaining air quality standards and providing for new economic growth.” H.R.Rep. No. 95-294, 2 U.S.Code Cong. & AdmimNews (1977) 1077, 1091. The report goes on to explain that:
“In revising its plan to permit new growth, the * * * State plan * * * must require permits for the construction and operation of new or modified major sources. Additionally, the owner or operator of a prospective new source (or modification) must demonstrate that all sources owned by him * * * are in compliance or on a schedule for compliance. The source must also demonstrate that the issuance of a permit will not cause or contribute to concentrations of any air pollutant, for which national ambient air quality standards have not been promulgated, which would pose a significant risk to health.” Id.
“A major weakness in implementation of the 1970 Act [Clean Air Amendments of 1970, Pub.L. 91-604, 84 Stat. 1676] has been the failure to assess the impact of emissions from new sources of pollution on State plans to attain air quality standards by statutory deadlines. States have permitted growth on the assumption that a deadline was sufficiently distant so that future emissions reductions could be made to compensate for the initial increase. It can now be seen that these assumptions were wrong. Some mechanism is needed to assure that before new or expanded facilities are permitted, a State demonstrate that these facilities can be accommodated within its overall plan to provide for attainment of air quality standards.” S.Rep. No. 95-127 (1977) 55.
With these considerations in mind, Senator Muskie made the following poignant remarks in submitting the Conference Committee Report:
“I should note that the test for determining whether a new or modified source is subject to the EPA interpretative regulation — and to the permit requirements of the revised, implementation plans under the conference bill — is whether the source will emit a pollutant into an area which is exceeding a national ambient air quality standard for the pollutant — or precursor. Thus, a new source is still subject to such requirements as ‘lowest achievable emission rate’ even if it is constructed as a replacement for an older facility resulting in a net reduction from previous emission levels.
“A source — including an existing facility ordered to convert to coal — is subject to all the nonattainment requirements as a modified source if it makes any physical change which increases the amount of any air pollutant for which the standards in the area are exceeded.” (Emphasis added.) 123 Cong.Rec. (1977) 26847.
In light of the foregoing legislative history of the Clean Air Act, it is obvious that, after giving thoughtful consideration to the competing interests of clean air and economic growth, Congress intended for replacement sources to be governed by the regulations applicable to newly constructed sources.
The majority, in an effort to bolster its position, states that “[i]t is interesting to note that following the trial court’s ruling the OEPA proposed that Ohio Adm.Code 3745-31-01(D) be amended to negate the interpretation reached by the trial court” and that a letter by Donald E. Waltermeyer, an OEPA employee, proposed a further change of “adding the words ‘ “new or replacement” prior to “air contaminant source” in the definition for “Install.” ’ ” The majority deduces therefrom that “[i]f the definition of ‘installation’ is as clear as appellee presently urges, there would be no need for a clarification to ‘solidify’ the OEPA’s position.”
“The Ohio EPA Division of Air Pollution Control, has always considered the act of replacing an existing air contaminant source as being one that requires a Permit to Install. This has always been Ohio EPA’s interpretation of the rules, even when the new equipment is identical to the equipment being replaced.”
Based on the foregoing, I would find the OEPA’s interpretation to be a permissible one and affirm the decision of the court of appeals.
. In his uncontroverted affidavit, Robert F. Hodanbosi, Manager of the Air Quality Modeling and Planning Section of the Division of Air Pollution Control in the OEPA, states:
“I have consistently determined, since I began my current duties as Manager in the Division of Air Pollution Control in 1978, that sources like the ‘nev/ Raymond Mill * * * are new sources * * * which must obtain permits to install, as required by O.A.C. Rule 3745-31-02.”
. After the replacement of the Raymond mill, Congress enacted the Clean Air Act Amendments of 1990, effective November 15, 1990. See Pub.L. 101-549, Title VII, Section 711(b), November 15, 1990,104 Stat. 2399, 2684. The 1990 amendments made no substantive changes that are relevant to the case sub judice. All citations in this dissenting opinion are to the Clean Air Act prior to the 1990 amendments.