delivered the Opinion of the Court.
The State Engineer and Division Engineer for Water Division No. 3 appealed a judgment of the water court approving an application by Bradley for a change of water right and ordering the issuance of a well permit. Bradley sought to change the point of diversion of an existing water right from a well in a corner of his property to a well in the center of his property. Because the evidence in the record does not support the water court's conclusion that granting the application will neither enlarge the existing right by expanding Bradley's historic use nor result in injury to other vested rights, the judgment of the water court is reversed.
I. FACTS AND PROCEDURAL BACKGROUND
This dispute arises from an attempt by David W. Bradley to improve his method of irrigating 150 acres of farmland he owns in the San Luis Valley. In 1999, Bradley applied for a permit to construct a new well, to be used as an alternate point of diversion for an existing water right. The State Engineer denied the application on the grounds that he was unable to determine that unappropriated water was available for withdrawal by the proposed well and that the vested water rights of other appropriators would not be materially injured. Bradley then filed a pro se application with the water court for Water Division No. 3 for a determination with respect to a change of water right, specifically a change in point of diversion. The water referee denied that application, indicating simply that Bradley had failed to meet his burden of proof regarding historic use. Bradley then filed this protest with the water court, and the State and Division Engineers intervened.
At the one-day hearing, the only testimony came from a hydrographic expert with the Division Engineer's Office and the applicant's brother, who was qualified as an expert in civil engineering. The hydrographic expert's testimony focused on the effect of the proposed change on the overappropriated Closed Basin and Rio Grande systems of the San Luis Valley.
Bradley's groundwater right was decreed by the water court in 1974 for irrigation purposes at a flow rate of 1,200 gallons per minute, 5.34 acre-feet per day, with an appropriation date of August 81, 1988; however, the evidence indicated that in addition to groundwater, Bradley had always irrigated his land with water from two surface rights,
Beginning in 1997 or 1998, Bradley largely abandoned his long-established practice of flood-irrigating through ditches and began delivering both his surface and underground water to two newly purchased center-pivot sprinklers by placing the water into a ditch, transporting it to a holding pond near the sprinklers, and pumping it into the sprinklers as needed. It was therefore clear that the acreage in question had always been irrigated by some combination of surface and well water.
The water court was clearly cognizant of the importance of differentiating the amount of surface water from the amount of well water historically used to irrigate the acreage in question, but it was also concerned about the difficulty and expense of quantifying the historic use of the particular water right for which a change in the point of diversion was requested. Noting that one of the goals of the Water Rights and Determination Act of 1969
The State and Division Engineers appealed the water court's ruling directly to this court.
II. APPLICATIONS TO CHANGE THE POINT OF DIVERSION
Although a water right in Colorado is usufructuary in nature, with ownership of the water itself remaining in the public, it is nevertheless a property right. Santa Fe Trail Ranches v. Simpson,
One of the incidents of a water right is the right to change the point of diversion.
Although a decree does not confer, but rather confirms a pre-existing water right (or in the case of conditional applications, gives the applicant the opportunity to develop the right and obtain a priority date that relatеs back to the date of the first step), Shirola,
In the past, we have explained this limitation by noting that "over an extended period of time a pattern of historic diversions and use under the decreed right at its place of use will mature and become the measure of the water right for change purposes." Midway Ranches,
An absolute decree, whether expressed in terms of a flow rate or a volumet-rie measurement, is itself not an adjudication of actual historic use but implicitly is further limited to actual historic use. In order to determine that a requested change of a water right is merely that, and will not amount to an enlargement of the original appropriation, actual historic use must therefore, in some fashion and to some degree of precision, be quantified. As we have previously observed, onee an appropriator exercises the right to change a decreed water right, he runs the real risk of requantification of the right based upon actual historic consumptive use at an amount less than his original decree. Midway Ranches,
The acreage under irrigation is a common basis of measuring the use of water in the adjudication of priorities, Farmers Res. & Irr. Co.,
It is well-established that the applicant for a change of water right bears the burden of proving by a preponderance of the evidence that the requested change will not injure other users. Farmers Res. & Irr. Co.,
III. VALIDITY OF THE WATER COURTS ORDER
In its order, the water court made a number of factual findings from the evidence but failed to suggest how any of those findings led to its conclusion that the applicant had met his burden with regard to historic use and lack of injury. Not only do the court's factual findings and the undisputed evidence from the applicant's own expert fail to support the conclusions reached by the court; they demonstrate with near certainty that the requested change would amount to an enlargement of the applicant's original water right and would be injurious to other vested rights.
Bradley's property has been served by at least three distinct water sources for over sixty years. The record contained no suggestion that the well had ever been the sole source of water for the acreage in question, even during the two years since the implementation of the center-pivot sprinklers.
The inadequacy of the applicant's presentation was not due merely to a lack of precision or accuracy in quantifying historic use. It resulted from a conceptual failure to distinguish aсtual historic use from the face amount of the decree, and therefore a failure to even attempt to establish the historic use of the well-water, separate and apart from historic use of the applicant's surface water. In approving the request, the water court appears to have conflated the historic use of the land аs a whole with the historic use of the groundwater. Admirable as the applicant's attempt to improve the efficiency of his irrigation technique may have been, a water right is a property right, which can be sold or further changed onee it is established. An enlargement of the applicant's right would at the very least have the effect of advancing his priority to any аdditional water over that of junior appropriators, and in the overappropriated systems of the San Luis Valley it would necessarily be injurious to other vested rights.
IV. CONCLUSION
Because the record does not support the water court's conclusion that the applicant met his burden of proof with regard to the historic use of the water right for which he sought a changе or the lack of injury to other vested rights, the water court's order must be reversed. The case is remanded for further proceedings consistent with this opinion, including the possible presentation of additional evidence or modification of the application.
Notes
. Section 37-92-302(1)(b), 10 C.R.S. (2001), allows the State Engineer to oppose applications for determinations оf a water right or changes to a water right.
. A general description of the geographic, geologic, and hydrologic features of the San Luis Valley is set forth in Alamosa-LaJara Water Users Protection Ass'n v. Gould,
. The surface water was represented by 20 shares of the Rio Grande Canal and 20 shares of the Santa Maria Reservoir Company.
. See title 37, art. 92, 10 C.R.S. (2001).
. The Act permits approval of an application for a change of water right оnly if such a change will not injuriously affect the owner of or persons entitled to use water under a vested water right or a decreed conditional water right, and in cases in which a statement of opposition has been filed, it prescribes a formula for the parties to propose to the referee or water court a ruling or decree with terms and cоnditions that will prevent any such injurious effect. See § 37-92-305(3), 10 C.R.S. (2001).
. The court of appeals lacks jurisdiction over "water cases involving priorities and adjudications." See § 13-4-102(d), 5 C.R.S. (2001).
. A "change in water right" includes "a change in the type, place, or time of use, a change in the point of diversion, a change from a fixed point of diversion to alternate or supplemental рoints of diversion, [or] a change in the means of diversion,. ..." § 37-92-103(5).
. The duty of water has been defined as:
[ITIhe measure of water, which, by careful management and use, without wastage, is reasonably required to be applied to any given tract of land for such period of time as may be adequate to produce therefrom a maximum amount of such crops as ordinarily are grown thereof. It is not a hard and fast measurement, but is variable according to conditions.
See In re Steffens,
. The term "historic use" refers to the "historic consumptive use," see, e.g., Farmers Res. & Irr. Co. v. City of Golden,
