34 P.2d 1 | Wyo. | 1934
This is an action brought by the State Bank of Wheatland, a corporation, hereinafter referred to as the bank, against James F. Turpen and the Fidelity and Deposit Company of Maryland, a corporation, the latter hereinafter being referred to as the Surety or the Surety Company. The court entered judgment against the Surety Company for the sum of $13,304.56, and judgment against Turpen for a somewhat larger amount, and from the judgment so entered the Surety Company has appealed.
On July 2, 1929, Turpen entered into two contracts with the State of Wyoming for the construction of a bridge over Wind River on the Wind River-Shoshoni road. One was for the sub-structure, and the other for furnishing and erecting structural steel for a steel truss over the river. The latter is not in controversy *290 in this case, except incidentally. The contracts provided for monthly estimates and payments as the work progressed, 15% of the estimates to be retained until the work was fully completed; that before making final payment, the State Highway Commission should require the contractor to show that all debts were paid; that a notice should be given of the completion of the work and that the final estimate and the 15% retained should not become due and payable until after that time. Turpen gave a bond in the usual form, pursuant to Sec. 95-201, Rev. St. 1931, with the Fidelity and Deposit Company of Maryland as surety, which provided that it should be for the use of the obligee as well as for the use and benefit of all persons performing work or labor or furnishing any material in the execution of the contract, and that all labor and material furnished for the work should be paid. The surety had no assignment of the money arising under the contract and no agreement how it should be applied. Nor does our statute make any provision therefor, at least in specific terms. The contract was completed some time during the summer of 1930 and due notices of the claimants for work and material were filed. There is no controversy in this case as to the sums involved in the final estimate and the 15% retained by the state pursuant to the contract.
Prior to the commencement of the work, Turpen, who was unable to finance the project, made an arrangement with the State Bank of Wheatland, plaintiff herein, through Mr. Brice, its president, that money should be loaned him from time to time so as to be able to carry on and complete the work. It was thought at that time that Turpen would make a profit out of the contract in the sum of approximately $15,000. Brice agreed to make these loans, provided, however, that the bank would be made secure. He loaned Turpen, commencing with July 25, 1929, up to and including *291 January 10, 1930, the total sum of $23,500. The proceeds thereof were apparently all used on the contract in question. In addition thereto, the plaintiff took an assignment of the claim of the Colorado Builders' Supply Company, which furnished steel for the work in question, amounting to the sum of $5482.55 less $1132.78 paid thereon, and the balance due on that claim constitutes the first cause of action herein. Plaintiff also took five different assignments of claims of the Shoshoni Lumber Company for cement, lumber and other material furnished for the work. These claims are sued on in the second cause of action herein, and in the aggregate amount to $8159.77 less $999.52 paid thereon.
The State made certain payments to Turpen as the work progressed. Warrants were issued for them. Most of them were deposited in the plaintiff bank and credit given Turpen therefor. Two of them were issued directly to the bank. The others were sent directly to the bank and endorsed by Brice as agent for Turpen. The total amount of warrants thus deposited in the bank was the sum of $50,148.71, which, however, included $22,818.33 paid on the second contract herein, not in litigation here. Three of the loans made to Turpen by the bank, in the sum of $4500, principal, were, in the fall of 1929, charged to the borrower by debiting his account therewith. At the same time the debtor was also charged with a note of $521.65, on account of a loan made to him before the making of the contract in question herein. The other loans made by the bank, in the principal sum of $19,000, were paid out of the warrant of $22,818.33 above mentioned. The remainder of the money placed to Turpen's credit as above stated was checked out by him from time to time. All of it apparently was disbursed for labor and material under the contract in litigation except the note of $521.65 already mentioned, the sum of $2962.00 *292 for machinery, apparently used in connection with the contract, and the sum of $861.93, used by Turpen for his personal needs.
The defendant surety company pleaded payment, and that the plaintiff bank was seeking to split an entire cause of action originally held by the Shoshoni Lumber Company. This will be mentioned more in detail later, and other facts will be mentioned in connection with the discussion of points of law arising thereunder. It may be mentioned here, before proceeding further, that counsel for the surety company complains of the inadequacy of some of the evidence in connection with the assignments from the Shoshoni Lumber Company and the exhibits in connection therewith, and of some inconsistencies apparently exhibited therein. It would do no particular good to enter into a discussion in reference thereto. We have examined the various exhibits and papers connected therewith with care and have found that the items and amounts included in the various assignments have been shown with reasonable certainty. We shall, accordingly, proceed at once to the discussion of the legal principles involved in this case, and the facts in connection therewith.
1. The defendant pleaded, and it appears in the record that the Shoshoni Lumber Company, assignor of the plaintiff herein, on January 17, 1931, instituted an action against the defendants herein, for the sum of $1060 for goods and merchandise sold to the defendant Turpen in connection with the construction of the bridge referred to herein, and that a judgment was entered in that action in favor of the Lumber Company on July 6, 1932. It is claimed that the items embraced in that action, as well as the amounts assigned to plaintiff bank and sued on herein, were part of the same running account which the Lumber Company *293 had against Turpen, and that accordingly two suits, each for part thereof, violates the rule against splitting a cause of action. The witness Cox, manager of the Lumber Company, testified that the company had but one account against Turpen, commencing in the month of July, 1929, and ending April 7, 1930, part of that account being involved in the suit brought by the Lumber Company, the remainder in the case at bar; that the items involved in the two actions are however "entirely separate"; in other words, that those involved in the case at bar were not involved in that suit. The defendant Turpen testified that in July, 1929, he made arrangements with the Shoshoni Lumber Company for the purchase of the various supplies needed in connection with the bridge, and that the prices quoted were satisfactory to him; that he immediately bought two car loads of lumber, the remainder, including the cement, at various times as it was needed; that he would go and get the material from day to day and sometimes oftener; that the cement was bought on 10 days' time; that it was understood that he should settle for the other materials every thirty days, and if he did that, he would get two per cent discount. It may be that under the foregoing evidence, standing by itself, we should be forced to the conclusion that the whole account rested upon the agreement between the parties made in July, 1929, and that this was, in fact, the only agreement made. And if there were no other evidence, it may be that we would be compelled to hold with the defendant, at least as to the major portion of the account. But it appears that during the progress of the work, certain accounts were individualized by the Lumber Company and Turpen, and set apart by themselves, as shown by the assignments made to plaintiff bank. And while the rule of splitting a cause of action cannot be evaded by making partial assignments (1 C.J. 1110), nevertheless the rule exists for *294 the benefit of the debtor, and he can waive it. 1 C.J. 1108, 1109. There can be no doubt in this case that Turpen waived the rule. He did not set it up in this case, nor would he have been permitted to do so. He had the right to make a contract in the first instance, individualizing the accounts in the manner in which it was done subsequently, when the assignments to the plaintiff were made. In that case the defendant could not have complained. Thus individualizing the accounts could not have prejudiced it. And if Turpen had the right to do so in the first instance, it would seem that it must logically follow that he had a right to do so subsequently either by direct agreement to that effect or by what may be called ratification, at least if no greater burden would thereby be placed upon his surety than in the case where his agreement had been made in the first place. And no greater burden is perceived. It would seem that the defense here set up is one that is personal to Turpen, the principal, and since he has waived it, the surety cannot set it up. 50 C.J. 194-195; 21 R.C.L. 999.
2. As heretofore stated, the first cause of action is based on an assignment of the claim of the Colorado Builders Supply Company, which in August, 1929, furnished steel for the work in question in the amount of $5482.55. Part of this included freight, which was paid by Turpen, leaving the amount due to the seller the sum of $4349.77, the amount in suit herein. The bank remitted the amount of the bill, less freight charges, to the seller, taking an assignment of the account, as well as a receipt, and requesting that the latter be sent to Turpen, so that he could file it with the Highway Department and receive credit therefor in the next following estimate. Turpen filed the receipt, and in the estimate of August 31, 1929, was allowed for the steel at the contract rate, and this amount, less fifteen per cent retained, was included in the warrant issued upon *295 that estimate, pursuant to a claim, under oath, filed by Turpen. The total warrant issued was in the sum of $7547.56, which included the sum of $5049.62 for the steel above mentioned, and which, pursuant to an assignment made by Turpen, was issued and sent directly to the bank.
In connection with the second cause of action, involving accounts bought from the Shoshoni Lumber Company, it appears that the latter company made assignments to the plaintiff bank, on the dates shown thereon. It gave these assignments to Turpen. The latter forwarded them to the bank, and the bank thereupon sent a check to the Lumber Company. At the same time that the assignments were given, Turpen also gave his individual check, with the understanding, as the evidence shows, that these checks should be returned when the bank should send its check in accordance with the assignments made to it. The accounts were then marked paid. One of the assignments, for $1535, was for 2000 bags of cement bought in July, 1929. The receipt for this was filed with the state, with the knowledge, it seems, of the bank, and an allowance of $1585, less 15% thereof retained, was made to Turpen in the July estimate of $1491.75, the warrant for which was issued to Turpen and was deposited in the plaintiff bank. Apparently another item of cement was dealt with likewise. The situation in connection with these items of cement is, accordingly, similar to the situation in connection with the steel bought from the Colorado Supply Company. Various contentions are made by reason of these facts, and we shall proceed to consider them separately.
(a) In the first place, it is claimed that the bank, by these transactions, in fact made loans to Turpen and paid the material men, and that such loans are not covered by the bond given by the surety company herein. The conclusion, doubtless, is correct, if the *296
premises are. It does not seem to be questioned that the accounts for labor and material furnished in connection with the contract herein were assignable, giving the assignee the same rights as the assignors. And it has been so held. Maryland Casualty Co. v. Philbrick and Nicholson,
(b) It is claimed that Turpen would not have received an allowance for the steel and the cement heretofore specifically mentioned except for the filing of the receipts therefor, and that the "connivance on the part of Brice" to have these filed, "contemplated and in fact involved Turpen in a violation of his contract." We have, however, not been able to discover wherein the contract was violated by reason of the facts herein shown. The evidence shows that the steel and the cement for which allowance was made by the state was on the ground at or near the bridge, and all finally went into the work undertaken by Turpen. An agent of the State Highway Commission, it is true, testified that no allowance would have been made for these items, at the time that they were made, if it had not been for the receipts which were filed with the commission. In fact, Turpen thought the same. But that can have no weight as against the contract in the case *297 at bar. It provides, in so far as pertinent here, as follows:
"Monthly payments based upon approximate estimates of the amount of and value to the State of expense incurred during the preceding month, as computed by the Engineer, shall be made to the contractor during the progress of the work on or before the 20th day of each calendar month * * * provided also that such monthly estimates need not be paid unless the contractor shall furnish the State Highway Commission an affidavit showing a complete list of all just debts contracted, the amounts paid thereon, and the amount owing by the contractor on such debts, including labor, subcontractors, materials, feed bills, board and grocery bills contracted or incurred in the performance of this contract."
It may be noted that the highway commission had the right, if it was not its duty, to make an allowance for property of value to the state, and it can hardly be doubted that cement and steel on the ground was of such value. There was no requirement here, as counsel for the surety claims, that Turpen should first pay for these items, if on the ground, in order to have an allowance therefor, or that he should file a receipt showing payment. There was given a discretion not to make such allowance unless an affidavit was filed showing all the facts. Whether such affidavit was filed or not is not shown by the record. We take it, by inference, that none was filed, and we think that this was immaterial, when the state highway commission waived it. See Metropolitan Cas. Ins. Co. v. Brick Tile Co., (Okla.)
"We do not see, therefore, how the advancement to the contractor could possibly have caused injury to the defendant, and it was calculated to benefit the defendant, in that it enabled the contractor to proceed with work, the performance of which the defendant had guaranteed. It is well settled that the rule ofstrictissimo juris, ordinarily applied in relief of an individual surety, is not applied in case of compensated sureties, and that where a bonding company, for a monetary consideration, has insured against failure of performance of a contract, it must show that it has suffered some injury by reason of departure from the strict terms of the contract, before it can for that reason be discharged from its liability."
(c) It is argued that the filing of the receipts should operate as an estoppel. But in order to have that effect, some prejudice to the surety company must have resulted. 21 C.J. 1205. But none appears in the record. As far as we can tell, the filing of these receipts had no effect whatever either one way or the other upon the surety company. It is argued that the *299 surety had a right to rely on them. But it does not appear that it did. We are unable to conjecture, in view of these facts, upon what basis we could hold the existence of an estoppel here, and no basis has been pointed out by counsel.
(d) It is argued that the course pursued by the bank in taking assignments was a fraud upon the surety. In that connection the good faith of Brice, the president of the plaintiff bank, is assailed. He is accused of an unconscionable and diabolical scheme to defraud the surety. We have not been able to discover any evidence in the record in support thereof. It appears throughout that he was but attempting to protect the bank against loss, and that, of course, was his primary duty, if he could do so legally. It is true that he relied upon the fact that the surety would make good any proper claim not otherwise paid, but there was nothing wrong in that. Turpen was a stockholder in plaintiff bank in some small amount, but there is nothing in the record to indicate that this influenced Brice to engage in any improper conduct. Nor did he have anything to do with the bond in question except to countersign it at the special request of the surety company. Counsel argues that it was inconsistent with good faith for the bank to receive assignments and then fail to apply in satisfaction thereof the warrants which included the amounts covered by the assignments. But counsel has overlooked, or has deliberately rejected the explanatory facts appearing in the record. Turpen, like most of us, was not overburdened with riches. He could not build the bridge without financial assistance. In fact, he did not have a dollar with which to carry on the work. The surety company must have known that. If it did not, its agents must have been frightfully negligent in blindly entering into the suretyship on behalf of their principal. The bank agreed to help Turpen, provided that it was secured. There *300
were, under the circumstances, but three courses which could be followed in order to carry out both of these purposes; the bank could take an assignment of every item that went into the work, and then apply the warrants received upon the amounts so advanced, or second, it could take an assignment of but part of the items, and advance money to Turpen for the purpose of paying the labor and other items, depending for the payment thereof on the warrants that would be issued by the state, or third, it could take an assignment of the amounts due from the State to secure it for advances made. The third course has been the course usually followed by banks in like cases, and the extreme hazard thereof, unless in combination with the first course, is shown by the innumerable cases in which it has been held that a surety is subrogated to the rights of the owner in preference to that of the bank as to any unpaid sums. 60 C.J. 777-781. The plaintiff in this instance chose to follow the second course in preference to the first, for the obvious reason that to have followed the latter would have entailed a great deal of trouble on its behalf. And that trouble is the simple explanation why the bank permitted Turpen to check against the account for whatever he needed, although it may be said in that connection, that Turpen's checks were watched, an attempt was made to prevent him from squandering money, and some of the checks given for the latter's personal needs were turned down, and little, if any, money was in fact squandered. Whatever else may be said as to the course which the bank pursued, the evidence does not show any moral wrong on Brice's part. There was no intentional fraud. The only item in connection with which the bank could possibly be charged with unjust dealing is in connection with the $521.65 note, which was paid out of money paid by the state on the contract in question here. But that isolated transaction *301
shows no intentional fraud. Defendant has cited us to Detroit Fidelity Surety Co. v. Equipment Company, (D.C.)
"The surety nevertheless has an interest in the conduct of the job, and has the right to fair treatment and full information. But if information is desired, he must ask it. There is no duty on persons with whom the contractor may deal to give particular notice of the dealing to the surety. The surety is represented by the contractor in the ordinary business of the job. The bank was not bound to notify the surety company of the arrangements it in good faith had made with the contractor to carry on the work."
And in the case of Maryland Casualty Co. v. School District,
"The surety company complains because it was not notified of the financial embarrassment of the contractor, but there was no duty resting upon the indemnified to notify the surety as a matter of law."
3. So far, then, we have not been able to find any just reason for reversing the case. But counsel argues that the money to be paid under the contract in question was a trust fund so long as it remained in the hands of the state, and that when the plaintiff bank had knowledge of the source of the money which it received, it was its duty to apply it upon the indebtedness which arose out of the contract, namely, the assigned claims sued on herein, and that this was particularly true with the money paid directly to the bank, in that the payment thereof was consistent with and in execution of the trust. If all the money due from the state was a trust fund, as counsel claims, his conclusion should, perhaps, follow. But was it? It is generally held that a surety has an interest in the *303
reserved percentage withheld by the owner — here the State — and that when such surety pays, under a contract like that at bar, claims for material and labor that went into the work, it is subrogated to the rights of the owner in the amount so withheld, and its rights are superior to the rights of a bank which has loaned money to a contractor and has taken an assignment of the amounts due or to become due under the contract. This is upon the theory that the reserved percentage is just as much for the benefit of the surety as of the owner, and that such bank is a volunteer. Prairie State Nat. Bank v. United States,
"Even if this were proved * * * the bank's assignment would protect it in accepting payment. It was twenty days before a default was declared by the board. The bank had no notice of the prior unrecorded assignment to the surety, and therefore we see no basis for asserting that the surety had a prior equity in payments due to Lloyd (the contractor) under the terms of the contract. The district court was correct in allowing the bank to retain this payment."
The Livingston case is also squarely opposed, as we see it, to prior and later Michigan cases, namely, People v. Powers,
The only cases, accordingly, in point herein, are those which deal with money already paid out on a contract pursuant to monthly estimates, payable as the work progresses, and the question is whether there is a lien or trust also as to such money, which can be pursued in the hands of a third party to whom the money has been paid. We might say in that connection that counsel seeks to draw a distinction between the money which was paid directly to the contractor and then turned over to plaintiff bank, and the money which was paid directly to the latter. Two warrants were issued directly to it. This was done after the contractor had signed and filed an affidavit for the claim therefor, and had directed in writing that the warrants should be issued directly to the bank. These warrants were not treated differently from other warrants made out to Turpen, but sent directly to the bank and endorsed by Brice as agent for Turpen. All were deposited to Turpen's credit. This course was *310
apparently pursued so that the money might reach the bank more quickly, saving the contractor some interest. It would seem to be clear that there can be no material difference whether Turpen signed the warrants after they were issued to him, or whether he directed them to be issued directly to the bank. A difference of a few hours or days in obtaining his signature cannot, in reason, make any difference in the application of the legal principle involved herein. State v. Miller,
It has been distinctly stated, in some cases, that the money paid out in monthly estimates does not constitute a trust fund, yet not disputing that such money might be applied inequitably as to the surety. Third National Bank v. Fidelity Surety Company, (C.C.A.)
In all these cases courts have groped about and endeavored to discover and declare the principle of justice and equity which should govern, but have not been able to come to an agreement. If a party has a special interest in a fund out of which payment is to be made, *312
for instance an owner who in fact owns the fund, there is much to be said in favor of holding that in such case the payment made should be applied on the indebtedness which otherwise might be enforced by a mechanic's lien. But the cases even on that point are in conflict. Note 41 A.L.R. 1298. The same may be said when such special interest arises by reason of an assignment to the surety, known to others, of the funds out of which payments are to be made, as was true in Southern Surety Co. v. Bank,
For the reasons pointed out, and others, a number of the courts have seen no justification in holding that a surety has an equitable lien on funds like those involved herein, at least after it has been paid out, and have believed it to be for the public interest, in the absence of a contract to the contrary, to permit such funds to be freely applied in the commercial world as the contractor may see fit. They hold that such funds are the property of the contractor, and they hence apply the rule stated in 48 C.J. 663 that "the exercise of the right of appropriation of payments belongs exclusively to the debtor and creditor and that no third person can control or be heard for the purpose of compelling a different appropriation from that agreed upon by them," or made by the creditor in the absence of direction on the part of the debtor, in accordance with the general rule. 48 C.J. 642. Counsel for the surety seems to argue at times that these cases have no application here. We do not understand upon what theory that can be said. We think they are directly in point. The monthly estimates were, notwithstanding the contention to the contrary, paid unconditionally, and went into "trade" when they were turned over to the bank just as effectually as if turned over to anyone else. The bank, in so far as it was assignee of claims, stood in the same position as a materialman. And the *316
ultimate question is whether it was compelled to apply the money which it received in such claims. If not, then it could, of course, apply it on loans owing it by the contractor, or permit the latter to check it out. The latest case on the subject is Metropolitan Casualty Ins. Co. v. United Brick Tile Co., (Okla.)
"We are constrained to hold that the contract price is subjected to no equity in favor of the surety as against materialmen furnishing material for the construction of said project unless such equity arises in a proper manner by contract between the surety and said contractor, of which contract the materialmen are required by other provisions of law to take notice. The purpose of requiring the execution of said bond was to relieve materialmen of anxiety concerning payment of the indebtedness for furnishing material used in the construction of public works. The bond is an unconditional guaranty of payment and the compensated surety places itself in the position of peril voluntarily and assumes the risk incident to the default of the contractor in paying his obligations. To hold otherwise would strike down the manifest purpose of said bond and would enable contractors engaged in public works to thwart the just claims of materialmen who are creditors."
The Minnesota court, which, as stated, has held that a bank loaning money to a contractor has at times a superior right even to a reserved percentage also has *317
indeed held that the equitable lien of the surety extends to all the money agreed to be paid on a contract, the lien dating from the date of the suretyship. Barrett Bros. Company v. County of St. Louis,
"The position of appellant assumes that a surety has a right that the earnings of the contractor under his contract shall be applied upon the labor and material going into the structure when no such agreement is stated in the bond or provided by statute. Our public contractor's bond contemplates that the contractor will receive and disburse his money as suits his convenience. The original contractor in this instance could have protected itself by requiring a bond from the subcontractor. It may have done so. Where the bond is furnished the surety must recognize the possible occurrence of what here did occur as one of the perils of its business. In other words one who becomes surety takes the risk that honest payment of unsecured debts may leave a deficiency which the surety must make good. * * * * The authorities that hold contrary to our view do so upon the theory that such moneys are impressed with an equity in favor of the surety that entitles it to have the money applied in payment of liabilities incurred by the contractor under the contract. If such an equity exists as against a creditor, who has a current account arising out of the contract and also an account incident to some other and prior transaction, that prevents the creditor and his debtor agreeing that moneys which the creditor has received from payments under a particular contract shall be applied upon such prior indebtedness, it would seem that upon the same logic and reason, if this same creditor's *318 claim consisted exclusively of the old account, he could not safely accept such moneys, with knowledge of their source, upon the old account. The money should still be subject to such equity in favor of the surety, and, if the rule is followed to its logical conclusion, the surety in case of loss could recover payment from the general creditor. This leads to an instability in commercial business that does not have our approval. * * * * Most contractors and subcontractors must necessarily use some of their money that they receive in payment of obligations, not incurred in the particular contract from which their money is received. When they receive their money unconditionally it is their own and they may do with it as they please. * * * * The business of sureties is inherently one of constant peril, and their imperative watchfulness for their general protection makes it less burdensome for them to guard against the emergency here under consideration, and our view tends more to the stability of ordinary business."
The rule of this case was again applied in the later case of Radichel v. Surety Co.,
Similar is the case of Jefferson v. Church,
"The debt was paid to the contractors on their contract with the church. * * * When this money was so received by them, it was their money, and they were at liberty to use it as their own, and apply it in payment of such debts as they chose; and so also, in the absence of an express stipulation or arrangement between the parties interested in respect to its application, communicated to the plaintiffs (the materialmen) at the time the latter were at liberty to apply it as they did."
The case of Grover v. Board,
"After the bond was given the only relation there was between the contractors and the lumber company was the ordinary one of debtor and creditor, and, as far as the surety company is concerned, the money paid to the contractors by the state was their own, and they could do with it as they pleased. The surety company could claim nothing by way of subrogation to the rights of the state as the state had paid in full for the *320 work, and there was no fund or security in its hands, which any claimant could reach. * * * For a valuable consideration the surety company gave this bond guaranteeing that the labor and material furnished should be paid for. The giving of such a bond relieves the laborer and materialman from looking after liens or other security. The owner is then at liberty to pay his contractor when he pleases without liability to any subcontractor, and the contractor is free to draw his money from the owner and pay it out as he may choose. The duty of the lumber company and the liability of the surety company are measured by the terms of the bond. There is nothing in it, as we have seen, which requires that money received by the contractor for the structure shall be applied on the claims of those furnishing labor and material, but there is an absolute and unqualified guarantee that all indebtedness for labor and material shall be paid."
The case of George H. Sampson Co., plaintiff, v. Commonwealth,
"There having been no agreement or understanding between the parties as to the application of the money, the plaintiff could apply it as it saw fit, and the fact that the surety company was liable on a portion of the plaintiff's entire demand against the contractors did not give it the right to have the whole amount received by the plaintiff applied to that portion. * * * * The surety company could have protected itself by a provision *321 in the stipulation signed by it and the other parties interested in regard to payment by the commonwealth, but not having done so it cannot now object to the application which has been made by the plaintiff. The result is that the surety company is liable for the balance that remains due on the plaintiff's demand."
In the case of Kane v. Bank, (C.C.A.)
"We are not advised of any statute which requires that payments duly made to a contractor for public work be handled by him in any special way, or be given any particular application. No such contractual obligation appears in this case. In the absence of statute or stipulation otherwise the general responsibility of the contractor is credited in contracting with him, and his general resources are drawn on by him in executing the contract. Money or checks paid to him as the work progresses are the property of the contractor unincumbered by any trust, much as are payments to others for goods manufactured or services performed. The contractor's banker may receive such checks and is not bound to see to their application, nor to ascertain the state of the contractor's account with each contract; nor, if he knows it, need he govern himself in any wise with reference thereto. No wrong is done to the contractor's surety in recognizing the contractor's full title to such checks by taking them on deposit with all the consequences ordinarily attaching to such deposit."
The case of State v. Miller,
"The argument of the surety company is, substantially, that the company had an equitable lien on all sums due by the highway department to Miller under the contract which the surety company had bonded, and that the bank was therefore obliged to apply all such funds received by the bank for Miller's account in the payment of debts which the surety company was responsible for, rather than to debts which Miller alone owed the bank. In support of the argument, the attorneys for the surety company cite several decisions rendered on the equity side of the federal courts, in contests between ordinary creditors of a contractor, on the one hand, and the surety on his bond, on the other hand, each claiming a preference in the distribution of a fund due the contractor under his contract. Those decisions are not authority in this state. There is no such thing as an equitable lien in Louisiana — no lien at all unless it is created by statute. Besides, the bank *323 is claiming not as an ordinary creditor of the contractor, but as subrogee of those whose claims the surety company guaranteed the payment of, and whom the surety company could not compete with in the distribution of funds due to the contractor in virtue of the contract. * * * There was no fraud in this case on the part of the bank, and none is charged by the surety company. The bank was not under any contractual obligation to the surety company, did not occupy any fiduciary relation with the surety company, and was not obliged, either morally or otherwise, to apply the payments received from the highway department for Miller's account to the advantage of the surety company and the correlative disadvantage of the bank."
The case of Southern Surety Company v. Bank, (C.C.A.)
"A study of the record and the charge of the learned trial judge leads us to the conclusion that the action of the court below was proper. Bonds of the character of the one here involved are to be liberally construed. * * * A compensated surety can only be relieved where the circumstances clearly justify relief. * * * Here we can *324
find nothing in the evidence that proves that the bank did anything improper or anything other than what it should have done in a proper effort to protect its interests. The surety company evidently knew, or, by proper inquiry upon which it was put, could have known, the exact situation. The money with which the bank paid the material and labor claims, and for which it took a proper assignment, went for the carrying out of the project. The assignee of a labor or material claim takes all the rights of the assignor against the contract bond. Title Guaranty Trust Co. v. Crane,
The case does not distinctly state that the money paid to the bank was paid to it directly by the highway department, but in view of the fact that it had an assignment of all future estimates, we take it that that was true. Hence this case, and the Louisiana case, and Third Nat. Bank v. Fidelity Surety Co., supra, effectually dispose of the contention heretofore mentioned, that a distinction should be drawn between payments made directly to the bank, and payments made to the contractor and then turned over to the bank. See further on this subject, and as supporting the view of the foregoing cases, People v. Powers,
And this general view has been approved and adopted by the American Law Institute in its Restatement of the Law of Contracts. In Sec. 387 of that work is stated the general rule of the application of payments when a creditor has two or more debts which are owing him, and which is similar to what is stated in 48 C.J. 642. In illustration of the rule is given the following:
"A contracts with B to erect a building and gives B a bond with sureties to secure the payment of claims for labor and materials. In the jurisdiction where the contract is made laborers and materialmen can enforce such a bond to satisfy their claims. B makes payments to A on account of the building as the work progresses. A, with money so obtained, pays C to whom he is indebted not only for materials furnished for the construction of B's building, but also for other materials. A gives no direction for the application of the payment. C can apply it to other claims than that for materials furnished for B's building, although he is aware of the source from which the money is derived."
In Section 388 of that work it is stated that if the payor is under a duty to a third person to devote money paid by him in a particular way, it must be so applied if the creditor knows or has reason to know this duty, and in illustration thereof is given the following:
"A enters into a contract with B to construct a building, to be completed free of liens. Under the contract payments are due from B from time to time. C furnishes labor and materials toward the construction of the building under a subcontract with A. C has a mechanic's lien on the building for the labor and materials. B makes payments to A as they become due *326 under his contract. A is indebted to C not only under the subcontract with reference to B's building, but also on other accounts. A pays C money received from B. C knows that it has been so received. A, on making the payment, directs its application to a matured claim on one of the other accounts. The direction is effective, since A is under no duty to B to use the payments made by B in a particular way."
We should, perhaps, before closing refer to Southern Surety Company v. Bank,
We find, accordingly, two irreconcilable views, under one of which the bank should have satisfied the assignments sued on herein from the money which it received. Under the other there was no such duty on the bank, since there was none on Turpen to apply the funds received in any particular manner. The latter view is that approved by the Law Institute. Under it, the bank had the right to apply part of the funds received on only one of the debts which it held — the loans to Turpen, which were not secured, and neither Turpen nor the bank owed the duty to the surety company to prevent the withdrawal by the former of the remainder of the funds. We have not heretofore had the occasion to pass upon the points involved in this case, and the question is therefore fairly before us whether to approve or repudiate the view of the Law Institute thereon. We have examined about all of the numerous cases that have, directly or indirectly, any bearing herein. We think, after carefully weighing the arguments on all sides, that we should follow the Institute's view, if for no other reason than that of uniformity, which is of importance to sureties as well as to others. The judgment of the trial court must, accordingly, be affirmed, and it is so ordered. We may add, that this view is in harmony with that taken by the Federal District Court of this district on a similar question arising in a suit in which the surety company herein sought to recover from the plaintiff bank herein the amount of the warrant of $22,818.33 mentioned in the statement of facts, *328 issued for the steel truss under the second contract heretofore mentioned.
Affirmed.
KIMBALL, Ch. J., and RINER, J., concur.