263 P. 376 | Cal. Ct. App. | 1928
Plaintiff sued upon a contract whereby the defendants agreed to pay him the sum of $5,000 if they failed to commence the drilling of an oil well before a fixed day. Plaintiff had judgment and the defendant Lundeen alone has appealed on a typewritten transcript under section 953 et seq. of the Code of Civil Procedure.
At the time of the execution of the undertaking plaintiff held a lease from the title owners of a lot of land 30 x 130 feet located in the Signal Hill oil field in the county of Los Angeles. This lease called upon plaintiff to "spud in and commence the actual drilling of a well" within forty days after delivery to him of a certificate showing title to the premises vested in the lessors, to continue drilling with reasonable diligence until oil was found in paying quantities, or until the well should reach a depth of thirty-five hundred feet, and to pay the lessors as royalties sixteen and two-thirds per cent of the proceeds received from the sale of all oil, gas or other hydrocarbon substances extracted. On December 9, 1922, plaintiff and defendants Lundeen and Lee executed an "oil and gas contract" whereby these defendants agreed to commence the drilling of a well upon the premises and to perform all the provisions of plaintiff's lease which were to be performed by him and to pay plaintiff thirty per cent royalty, out of which he was to pay the royalties stipulated to the original lessors. The undertaking upon which the suit is based was executed the same day and, as a part of the same transaction, the plaintiff gave to the defendants certain writings wherein he specified the time for the commencement of work as thirty days after "I show you clear title" and also an easement to the 30 x 60 feet west of the lot described. This date was left blank at the time of signing the oil and gas contract and also in the undertaking, but the date "25th of January, 1923," was later inserted by agreement, that date being thirty days after certificate of title and easement were shown to defendants. The defendants actually commenced to "spud in" on February 7, 1923, thirteen days after the time called for in their contract and, in order to protect himself from a forfeiture of the lease, plaintiff procured from the owners of *346 the land an extension of time for performance under his lease.
At the beginning of the trial plaintiff amended his complaint by adding the allegation that at the time of entering into the undertaking "it was impracticable or extremely difficult to estimate the amount of damages which would accrue to plaintiff by reason of the default or failure of defendants, Lee and Lundeen, to spud in an oil well on said property as required . . . for the reason that there was not then, nor at any other time or now, any method or means by which it may be ascertained as to the amount of oil that would be lost to plaintiff by reason of the delay," and for the further reason that plaintiff's lease with the owners of the property would expire on February 3, 1923, unless said work had been commenced. The issue was thus drawn whether the undertaking came within the provisions of section
On the appeal from the judgment the appellant states his grounds to be that the findings are not supported by the evidence and that the findings do not support the judgment. He does not specify any particular finding which he claims to be unsupported and does not state wherein the findings as a whole fail to support the judgment. The respondent has taken up the burden of printing the evidence tending to show that the contract came within the rule of section
[1] The case comes within the rule that if the actual damages are uncertain, or are of a purely speculative character, and the contract furnishes no data for their ascertainment, the provision will, as a rule, be held to be one for liquidated damages. (8 R.C.L., p. 569; Escondido Oil etc. Co. v. Glaser,
[2] The character of the contract, whether it is to be construed as calling for liquidated damages or a penalty, is to be determined according to the circumstances existing at the time the contract was made, and the fact that at the time of the breach conditions have so changed that it would then be practicable and not difficult to fix the actual damage does not affect the character of the contract. (Hanlon Drydock etc. Co.
v. McNear,
In his reply brief the appellant has advanced new grounds upon which he insists that the judgment must be reversed. Without exception the arguments are based upon false premises unsupported by evidence from the record. They are all to the same effect — that because such and so is the case the contract is not one coming within the purview of section
Judgment affirmed.
Koford, P.J., and Sturtevant, J., concurred. *349
A petition by appellant to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on March 12, 1928.
All the Justices present concurred.