238 F. 657 | 6th Cir. | 1917
The defendant in error (hereinafter, called plaintiff) sued plaintiff in error (whom we shall call defendant), together with the Interurban Construction Company, for breach of a contract by which plaintiff agreed to do certain grading for the construction of an extension of defendants’ line from its terminus at Sebring, Ohio, to Salem, Ohio. At the conclusion of the testimony, taken on a trial by jury, plaintiff was required to elect as to which defendant it would prosecute, and elected to proceed against the railroad .company. Plaintiff had verdict and judgment, and defendant’s motion for a new trial was overruled. The errors assigned relate to the introduction of testimony, the denial of motions for direóted verdict, and for new trial, the refusal of requests to charge and the
“in the corporate name, in like manner and with like effect as before such dissolution or expiration; but so far only as shall he necessary or proper for collecting the debts and claims due to the corporation, converting its property and assets into money, prosecuting and protecting its rights, enforcing its liabilities, and paying over and distributing its property or assets, or the proceeds thereof, to those entitled thereto.”
These statutory provisions for winding up and distributing the assets are not exclusive. Donnally v. Hearndon, 41 W. Va. 519, 526, 23 S. E. 646. And suits either for or on behalf of the corporation pending at the time of the dissolution are expressly held not abated thereby, Lumber Co. v. Ward, 30 W. Va. 43, 54, 3 S. E. 227; Board of Education v. Berry, 62 W. Va. 433, 442, 59 S. E. 169, 125 Am. St. Rep. 975. Stiles v. Coal Co., 47 W. Va. 838, 847, 35 S. E. 986, is not, in our opinion, an authority to the contrary. In the later case of Lumber Co. v. Coal Co., 66 W. Va. 696, 702, 66 S. E. 1073, 1075 (29 L. R. A. [N. S.], 1101), the court said that “the prosecution and defense of actions, respecting valid contracts, do not constitute doing business within the meaning of the statutes,, restricting the right of foreign corporations,” and that among the rights not taken away by the revocation of the right to do business was the right to sue upon a valid contract, and also the right to make defense in any action instituted against it. True, the corporation there involved was a foreign one, but the statutory provisions in the respect here involved are the same; and in the still later case of Comstock v. Lumber Co., 69 W. Va. 100, 102, 71 S. E. 255, 256 (which involved a domestic corporation whose charter had been forfeited), it was held that the phrase “ ‘exercise or attempt to exercise any power’ under the charter, must be read as if it said carry on
The record would, we think, support a finding that the construction company was used with respect to the extension in question, 'for the purpose (among others) of enabling the controlling stockholders in the railroad company (who were the controlling stockholders in the construction company) to obtain a personal profit to themselves out of the building of the extension by acquiring a large block of railroad company stock, which went, with certain bonds given by the railroad company, to the construction company in connection with this ' construction. The force of these considerations is not necessarily overcome by the facts that the construction company maintained a legal and independent corporate existence; that the
It is urged that McGinty’s testimony referred to- was not corroborated, and that it was discredited by his acquiescence in the written contract, by his making the additional contracts hereafter referred to, by subletting parts of the work as under the construction company, by proceedings taken to obtain a subcontractor’s lien against that company as well as the railroad company, and in other ways. But these considerations affect merely the weight of the evidence, which, taken together, we think sufficient to sustain a finding, not only that plaintiff believed in good faith that its contract was in reality with the railroad company, but that the construction company for the convenience of the railroad company, and with the knowledge of everybody interested in the transaction, was, with respect to the contract in question, “masquerading, acting for and put forth substantially as” the railroad company.
The remaining criticisms relate to specific items of plaintiff’s demands.
Plaintiff insists that the assurance in question was the inducing causé of the contract, and was a collateral agreement. It is conceded that if the agreement was of the latter nature, it was admissible, but such nature is denied. The jury was instructed, in effect, that if they found that the contract was made on defendant’s assurance that it would remove the tracks, and that defendant subsequently agreed verbally to pay 'the additional reasonable value of the work occasioned by their maintenance, recovery could be had. It is conceded that the work could not have been done with the tracks in place unless they were blocked up. Plaintiff claims to have kept 30 or 40 men doing such work and transferring the tracks from side to side. It is clear 'that, by tire strict letter of the contract, plaintiff could have done its work without supporting the tracks, thereby suspending operation of the railroad, unless the tracks were removed. Defendant denied any agreement, before the contract was made, to remove, the tracks, and denied an agreement to pay additional compensation, claiming that defendant itself actually supported and moved the tracks during the excavation work. It is evident, however, that, both parties expected that the excavation should not interfere with traffic, defendant claiming to- have secured right of way, for the temporary use of the tracks, before the contract in question was made. On this subject the contract did not purport to speak. We think it was thus competent to show the circumstances surrounding the making of the contract, including the assurance claimed as inducement to its making.
The third cause of action is for excavating for masonry, under a verbal contract, the amount claimed being $853.33. To this claim, the statute of limitations was pleaded. The particular excavation in question seems to have been finished at a date which was in fact more than six years before suit was begun. Plaintiff claims, however, that the right of action accrued August 2, 1904 (the date when the entire work done by plaintiff for defendant was completed), which would be within six years. The controlling question is whether there was evidence substantially tending to show an understanding that the excavation in question was not to be paid for until the entire work done by plaintiff for defendant was completed. We think an implication of such understanding was,- in view of all the evidence, at least permissible, and that it was not error to submit such question of fact to the jury.
The requested instruction as to the engineer’s functions correctly embodied the applicable law. Memphis Trust Co. v. Brown-Ketchum Iron Works (C. C. A. 6) 166 Fed. 398, 93 C. C. A. 162; Second National Bank v. Pan-Amer. Bridge Co. (C. C. A. 6) 183 Fed. 391, 105 C. C. A. 611.
We also think the sheet mentioned imported prima facie the engineer’s approval, for the specifications provided for its being given only “when, in the opinion of the engineer, the contractor shall have finally completed all the work contemplated under the contract and specifications.” There was testimony that the engineer had expressed himself to plaintiff as satisfied with its performance. And while we do not hold that the giving of this sheet was conclusive of the engineer’s satisfaction, we think it fairly deducible from his testimony
“the work had been completed [afterwards saying “by somebody”], and I supposed somebody would want a basis on which to make the statement, so I proceeded to make it out. That in my opinion was intended by me to be the final estimate; that covers the completed work.”
He testified, further, that all the work' included in the statement was done by plaintiff, with certain exceptions to which he had previously referred, testifying, in that connection, to deficiencies in-yardage, etc., necessary to complete the contract, and that to supply these deficiencies would cost $1,020.60. While we are disposed to- think defendant should have been recompensed for the loss incurred in completing plaintiff’s contract according to the engineer’s judgment, notwithstanding the expense was in form incurred by the interurban company (for, under the theory on which recovery was permitted, defendant in the end bore whatever loss there was in that respect), yet we think defendant not prejudiced by either the instruction or the modification of instruction referred to, provided credit is given for the amount of such loss. We also think that such necessary expense should be limited to the amount stated by the engineer; for, while there was testimony that the amount was greater than the figures given by the engineer as necessary for that purpose, the engineer’s figures as to the unit basis of prices are not discredited, defendant’s claim, as we understand it, being that the engineer failed to include as necessary work which defendant thought necessary to completion, Morley testifying:
“I agree with [the engineer] in that the work was not completed. I don’t agree with [him] as to what he said was the extent in which the work was not completed. I don’t' think he covered the whole thing in his testimony.”
It need scarcely be said that the engineer’s conclusions as to what 'was necessary are equally binding on defendant as on plaintiff. Our conclusion is-that whatever prejudicial error may have been committed in respect to the contract under consideration -will be cured by deducting from the verdict the sum of $1,020.60, with included interest thereon. It may be that' had plaintiff supplied all these deficiencies it would have been entitled to further allowance under the contract. It may-also be that the jury deducted the amount stated in whole or in part. But the record is not clear enough in our opinion to justify as basis of a remittitur a deduction of a less amount.
6. We think the defenses of payment and of abandonment (except so far as the latter may be involved in what we_ have already said) were properly submitted, and under appropriate instructions.
The motion for new trial was addressed to the sound discretion of the court, and we find nothing indicating an abuse of discretion in denying the motion.
If before the mandate goes down plaintiff makes, in the court below, a remittitur of $1,020.60, with interest at 6 per cent, from August 2, 1904, to April 4, 1914, and files with the clerk here a certified copy of such remittitur, the judgment so modified- will be affirmed, but with costs to plaintiff in error; lacking such remittitur, the judgment will be reversed and a new trial awarded.
otRer cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes-
©=»For other cases see same topic & KEY-NUMBER In all Key-Numbered Digests & Indexes
<S=>Por other cases see same topic & KEY-NUMBER in all Key-Numbered Digests & Indexes