Starbird v. . Barrons

38 N.Y. 230 | NY | 1868

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *232

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *233 The ruling of the judge upon the trial, excluding the evidence offered on the part of the plaintiff, by which he proposed to show that he was not responsible for the potatoes being frozen, was, it seems to me, manifestly erroneous. *234 This offer was first made in general terms, at folio 155 of the case, and rejected and an exception taken, and was again reported just at the close of the testimony, in the following form: "The plaintiff then offered to show that the defendants took charge of the boat at Schenectady, and undertook to guard the cargo, and to show that the potatoes froze by their default, and the plaintiff was not responsible for their freezing; this proof to be used on the question of demurrage." This offer was objected to and rejected, and the plaintiff excepted.

That the pertinency of this offered proof may be perceived, it is necessary to state, that, in the answer of the defendants, they had set up a counter claim, among other matters, for the sum of $200 "for loss on frozen and rotten potatoes;" and on the trial, one of the defendants was examined on this subject, and gave testimony, without objection, that the potatoes were frozen under the horse stable in the boat, five feet thick and two feet deep at the top, and that it took a long time to pick out the frozen ones, etc. The precise object, for which this evidence was given, was not stated, but it must have been offered in one of two aspects, or perhaps to subserve two purposes, to wit, either to create a counter claim to any damages the plaintiff may be supposed to have established, or to meet the claim for demurrage, by giving evidence, tending to show that any delay occasioned by the time required to unload the boat was caused in good part, if not wholly, by the carelessness and negligence of the plaintiff, in respect to the cargo. If in either view it was material, as it seems to have been considered, then it clearly was the right of the plaintiff to offer this rebutting and explanatory evidence. Although most of the testimony which was offered by the plaintiff to show his alleged damages was excluded by the judge, yet he was at liberty to claim, under the restricted rule of the court, that, for the space of five or six days that he was detained at Rochester, before the loading of his boat was completed, he was entitled at least to the value of the use of the boat for that period, for the jury might find upon the evidence that it was owing to no fault *235 of his that such delay occurred, but was solely chargeable to the defendants. If so, this claim could only be successfully met and overcome, by establishing on the part of the defendants, some counter claim that would offsett, and extinguish it, and upon hardly any other theory, than this, can the verdict, which is general for the defendants, be accounted for. It was, therefore, not only pertinent, but very material, that the plaintiff should be allowed to give evidence, which should meet and repel this counter claim, and show, that, under the circumstances proposed to be established by the evidence, it had no valid existence.

Upon the question of demurrage, also, for which it was in the second instance specifically offered, it was, it seems to me, equally pertinent. The jury might well, upon the evidence as it stood, be justified in concluding that the condition of the cargo was such, that greater expedition, than was made in discharging it, was not possible, and could not in fairness be demanded of the defendants. And yet, if it was true, that this state of things was brought about by the culpable default of the defendants themselves, and by a violation of their own prior undertaking to guard and secure the cargo against the occurrence of the very thing that caused the delay, the plaintiff was manifestly entitled to give this explanation, and thus meet and repel the claim to exemption, founded on the defendants' evidence. Upon both grounds, the testimony should have been admitted, and the exclusion was erroneous.

If I am right in this conclusion, the judgment must be reversed, and a new trial granted, and, in that event, it may be expedient that the other question principally discussed upon the argument should be passed upon by this court. Upon the trial, after the plaintiff had testified, that, by the contract, the defendants were to load the plaintiff's boat in three days from the 10th of November; that the necessity for this arose from the fact, that, in consequence of a break in the canal, which it would take two days to repair, a crowd of boats were lying west of the defendants' warehouse, and therefore it was essential that the plaintiff should be loaded *236 and be able to start in advance of this fleet, and thus gain time, which at that season was all important; that this fact was explicitly stated to the defendants, as the reason why it was necessary to be thus expeditious, and that, by the contract, it was imperative upon the defendants to get the plaintiff loaded within the time specified, the plaintiff offered to show, that, after Saturday, the 13th of November, and before he was ready to start, a crowd of boats had passed on east, ahead of him. This was objected to by defendants' counsel, as being too remote and as not material, and was rejected, and the plaintiff excepted. The offer was again repeated, coupled with an offer to show the damages caused by the delay to the plaintiff, and again rejected; and finally the plaintiff offered to prove that he went forward with all diligence, could get no further than Schenectady, in consequence of the ice, and that this was caused by the delay of the defendants at Rochester. This offer was objected to, on the ground of immateriality, and the objection was sustained by the court, and the plaintiff excepted. In passing upon these objections, we have of course the right to assume the existence of the facts which had been testified to, and that the jury would have found in accordance with them; and therefore, that it was proved, that the contract was absolute that the boat should be loaded in three days, and the defendants were informed of the precise state of things which made this necessary and imperative.

What, then, is the rule of damages applicable to such a case? Is it true, as the court in the opinion given at Special Term assume, that, as the defendants had failed to perform on their part, the plaintiff was not only at liberty, but it was his duty to refuse to undertake the performance of the contract on his part, and thus a right of action would exist, in which the only damages would be the difference between the ordinary rate of transportation of similar property and the rate agreed to be paid to the plaintiff, if the difference was in his favor, with the value of the use of the boat while held in readiness to receive a load within the three days provided for in the contract? *237

Beyond all doubt, the plaintiff was at liberty on the failure of the defendants to perform the engagement on which his depended, to rescind the contract, and claim at least such damages as are indicated in the opinion of the court; but whether, under such a state of things, that would be the entire measure of damages may well be questioned. But, I do not understand that a party is not at liberty, if he thinks he sees a fair prospect, or indeed, but a reasonable hope that he may still perform, notwithstanding the default of the other party, — to go on and complete his engagement, and earn the compensation to which in that event he will be entitled; and if he ultimately fails, despite a strenuous effort to perform, to accomplish the result, that he cannot claim all the damages, and repair the losses he has suffered by the default of the other party. While a party thus situated is at liberty to rescind a contract, he is not obliged to do so, and especially is he under no obligation to do this, when it is not probable that a rescission will offord him a remedy adequate to the damages he has sustained.

The principle which should govern such a case as this is no where more clearly stated than by Judge DENIO, in the case ofCross v. Beards (26 N.Y. 88), and it is, in my judgment, the true rule applicable here. "In every contract," he says, "between parties where the performance by one of them presupposes some act to be done by the other party prior thereto, or cotemporaneously, the neglect or refusal to perform such act, not only dispenses with the obligation which the other party was under to perform on his part, but where the circumstances are such, that a rescission of the contract will not afford an adequate remedy to the party who was ready to perform, he is entitled to a recompense against the delinquent, equal to the damages which such delinquency has caused him." Applying the principle here enunciated to this case, and I think the plaintiff had clearly the right to give the excluded evidence. It should be remembered that the period in question was very near the ordinary close of navigation; that it might very readily be assumed, that, if this contract had been abandoned, the plaintiff could have secured *238 no other cargo that he could have taken through to New York, as indeed the result in this case pretty clearly demonstrates, and the consequence, therefore, would have been, that he would have lost his entire freight to New York. The rule then, I think, is, that, while the plaintiff was at liberty to rescind the contract, he was not bound to do so, on the default of the defendants, but that it was his right and privilege to go on, and undertake the performance as diligently and faithfully as was possible, and thus doing, he was not limited to the rule of damages to which the court, by its ruling on the trial, confined him, but was entitled to recover all the damages, which, by the default of the defendants, he naturally and necessarily sustained.

That the special circumstances under which the contract in question was made have a bearing, not only upon its interpretation, but upon the rights of the parties under it, I think is very clear upon authority. Thus in Hadley v.Baxendale (9 Exch. 354; 26 Eng. L. and Eq. 398), the rule is thus stated by Baron ALDERSON: "If the special circumstances under which the contract was made were communicated by the plaintiff to the defendant, and thus known to both parties, the damages resulting from the breach of such a contract, and which they would reasonably contemplate, would be the amount of injury which would ordinarily follow from a breach of contract under those special circumstances so known and communicated."

So, where goods are purchased for a particular market, and that known to both parties, the damages are governed by the price in that market (Hargous v. Ablow, 5 Hill, 472); and the general rule long recognized in the courts of this State, and applied in numerous cases, is, that a party injured by the breach of a contract is entitled to recover all his damages, including gains prevented, as well as losses sustained, provided they are certain, and such as might naturally be expected to follow the breach. (See Griffin v. Colver, 16 N.Y. 489.)

Let us suppose this case had been reversed, and the defendants had brought an action against the plaintiff, claiming *239 damages for his failure to deliver the cargo in New York before the close of navigation, in the fall of the year. Can there be a doubt that the plaintiff would have been entitled to show the fact that he was detained by the neglect and default of the defendants, and in violation of their agreement, to load him in season to enable him to accomplish the voyage, and thus not only defeat the alleged claim of the defendants, but prove affirmatively the facts which entitled him to claim what he had lost by such default? And, if so, the right to recover these damages, by a suit instituted directly therefor, seems to me equally clear. It is within the principle established inStewart v. Ketteltas (36 N.Y. 388), that hindrances by one party to a contract, whereby the other is prevented from completing his part of the contract by the time stipulated, afford a legal excuse for non-performance, within such period. And, not only this, but as it seems to me, affords the party thus hindered, the right to redress for any damages he may have suffered by reason of such hindrance, delay or default. Thus, in the case cited, Stewart Howell were not only not bound to abandon their contract, on the failure of Ketteltas to perform seasonably on his part, but were permitted to go on, and claimed, and recovered their full compensation, although the work was not completed until long after the stipulated time. And the right to recover damages seems to me to stand upon the same substantial ground of principle.

The judgment should be reversed and a new trial granted with costs to abide the event.

Judgment reversed. *240

midpage