17 Mich. 342 | Mich. | 1868
"Wilson sued Stange for the value of certain iron work, which turned out on the trial to have been furnished under a written contract, containing only an agreement that Wilson should make “all the iron work, consisting of wrought and cast iron, according to plans furnished by C. W. Lloyd, architect, for Detroit and Milwaukee Railway Depot, for and in consideration of the sum of §5,0.00.” The time of furnishing the iron was not referred to, and the timé of payment was also left in blank. The only question properly
On the trial, the question was asked'on cross-examination of one of the plaintiff’s witnesses, “When the plaintiff had agreed to have said work done?” Another witness was asked on cross-examination, “Within what time it was that the plaintiff was to have the work in question done for the defendant?” Both of these questions were excluded, on the ground that parol proof could not be received, because the contract must speak for itself concerning the agreed time of performance.
The defendant below, in his defense, “offered to show by evidence that, at the time of making said written contract, it was agreed by parol that the work in question should be furnished by the plaintiff as fast as it might be required by the masons and carpenters, who should do the work on the building for which such work to be furnished by the plaintiff was intended; the defendant proposing, in making such offer, to follow up such evidence by testimony that the plaintiff had failed to furnish such work and materials a's so agreed, and failed to furnish them as fast as required by said masons and carpenters,” and to show consequent damage. This was also rejected.
It was claimed on the argument that this testimony was admissible on two grounds: First, To remedy a defect in the written agreement by parol; and, second, To show what was reasonable time.
There is no ground for maintaining that such proof is proper to complete or supplement the written agreement. It is very plain that an agreement to do a thing within a definite time can never be identical in spirit or substance with an agreement to do it within a time not fixed, and which in law is to be merely a reasonable time. And where the written contract is left in that indefinite shape, an
There is much more plausibility in the second ground, which maintains the admissibility of the evidence as bearing on the question of reasonable time. But it seems to me that it has no real tendency- to show what time was reasonable, either alone, or as a step in natural connection with any other proof, proposed or relevant.
The supplemental proof, which the defendant below proposed to introduce, was simply proof of a breach of this parol agreement, in not furnishing articles within the time as promised. That proof was undoubtedly competent to prove damages in case the court should find that it was unreasonable not to furnish the iron as fast as required by the workmen, but it could have no possible bearing on the reasonableness of their requisitions. Unless the proof of the parol agreement being made tended, to prove of itself that the time thus fixed Avas reasonable, independent of any binding force in the agreement, it Avas rightly ruled out.
It Avas argued that it had this tendency, because the fact that the parties were willing to agree upon such terms sliows they must have thought them reasonable. This is in fact claiming for the parol communications the full force of an agreement; and it would be a fair answer to such a claim to say, that, inasmuch as when they made their written agreement, by which only they were to be bound, they omitted this clause from it, it must follow that they were not willing to agree that it would be reasonable. And this is really the defect in the claim, that it confounds causes with consequences. If time is reasonable, it is because circumstances make it so, and not because it is so agreed; and if parties agree that it is reasonable, it must be presumed that they are so persuaded by the circumstances, which can
When a contract is to be performed within a reasonable time, the law implies that the parties contract in view of all the pertinent facts that may be mutually known to them, and it requires them to exercise such reasonable diligence as under all then and subsequently existing circumstances might be fairly expected. . When a court or jury is called upon to decide whether they have complied with what might have been reasonably expected, there must be proof of such facts as will show what ought to have been done. Where there has been an agreement, it must be complied with, whether reasonable or not, simply because the parties for a lawful consideration have seen fit- to make it. But where the promise made is no promise in law, it must be regarded as a nullity. To accept it in any shape as a basis or proof of obligation is to enforce it. TJpon the theory of this defense, if Stange had sued Wilson for not furnishing his iron in time, and this proof should be received as tending to fix that time, it would require counter - proof to prevent him from having the same benefit as if the parol agreement had been contained in the written. But the rule of law, which excludes parol evidence of agreements where there are writings, does so on the express ground that it must be presumed the writing contains all the parties were willing to adhere to. And it certainly seems unreasonable to allow, in the face of such a rule, any inference whatever that they were willing to adhere to anything else. And to prove, when a reasonable time is agreed upon, that at the same time it was understood what time would be reasonable, is equivalent to proving they agreed on that time either absolutely or conditionally, but it is no proof whatever of the only important point, which is whether the time was really reasonable. Opinions are excluded from evidence because they are conclusions which the court or jury are to draw for themselves. They are not usually binding upon parties
The only case which I have met with which appears to hold that such proof as was here offered tends, by showing what the parties thought, to prove what would be reasonable, is Cocker v. Franklin Manuf. Co. 3 Sumner, 530. The facts are not given so as to show very clearly how far the case is like this, but it would seem, from the language of Judge Story, to have been analogous. It was, however, a nisi prius ruling in a charge to a jury who disagreed, so that it never came up for deliberate review; and the only
On the other hand, this doctrine is opposed, not only by the principles underlying the rejection' of parol evidence to affect written contracts, but also by some cases, at least, which resemble this quite closely, although not absolutely parallel. In Greaves v. Ashlin, 3 Campb. 426, it was held that where a contract was silent as to the'time of delivery, evidence of a parol agreement to take the property at once, was inadmissible. Where articles are actually ready for delivery, a court certainly could not say there would, as matter of law, be anything unreasonable in immediate delivery, and the promise, therefore, was just as pertinent in that case as in this. In Simpson v. Henderson, Moo. and M. 300, a very similar principle was involved, and a similar conclusion was reached. In Lafarge v. Rickert, 5 Wend. 187, it was held that, where a contract was silent as to place of delivery, proof by parol of an agreed place was improper. In Williams v. Jones, 5 B. and Cr. 108, where an agreement by an attorney to take another into partnership mentioned no time for so doing, parol evidence that he was not then admitted, and that nothing was done till his admission, was rejected, although the effect was to render the written contract illegal.
There is in none of these cases, nor in any others that I have found (except the case in 3d Sumner), any intimation that - the proof, which was not valid to prove new terms to an agreement, was valid to affect it indirectly, by
I think there is no error in the record, and that the judgment should be affirmed, with costs.