157 N.Y.S. 447 | N.Y. App. Div. | 1916
Lead Opinion
The trial court, found, and the correctness of this finding is unquestioned, that the assignment by the contractor to the Royal Company of all moneys “due or to grow due” by virtue of the contract between the contractor and the city of New York, although absolute in form, was given to and accepted by the Royal Company as security for advances made and to be made by it to the defendant Acme Asphalt and Granite Paving Company. In other words, it was intended to create, in effect if not in legal parlance, a lien or mortgage upon the fund set apart or appropriated by the city of New York for payment of the sums to be earned under the contract.
The crucial question in the case then is, as pointed out by Mr. Justice Laughlin, whether.such an assignment, in the case of a municipal contract, should be held to fall within the meaning of the words “mortgage or other incumbrance” as used in section 13 of the Lien Law (Consol. Laws, chap. 33; Laws of 1909, chap. 38). The portion of the section material to the question reads as follows: “A lien for materials furnished or labor performed in the improvement of real property shall have priority over a conveyance, judgment or other claim against such property not recorded, docketed or filed at the
I freely concede, if the Legislature intended by this clause to give to laborers or materialmen priority over sums advanced, after the filing of the lien, upon a general assignment of moneys due and to become due under the contract, that the language adopted to express that intention was not happily chosen, and the words “mortgage” and “incumbrance,” when strictly construed, are not appropriate to such an assignment even if intended merely as security for future advances. But in construing a statute, and especially a remedial one like the Lien Law, we should not always confine ourselves to the strict legal definition of the terms used, but are at liberty to seek out the intention of the Legislature and to give effect to that intention, if by any reasonable construction the language used will permit us to do so.
It is quite obvious, as has been repeatedly pointed out by this court and the Court of Appeals, that it has been the intention of the Legislature to assimilate, so far as practicable, the regulations as to liens in respect to private real property and liens in respect to improvements upon public municipal contracts. (Brace v. City of Gloversville, 167 N. Y. 452; Herrmann & Grace v. City of New York, 130 App. Div. 531; 199 N. Y. 600.) One difference which necessarily exists is as to the subject-matter to which .a lien applies. In the case of private real property the lien applies directly to the property improved; but in the case of a public improvement, since it would be intolerable that public property should be incumbered with liens in favor of contractors and others, it is provided that the lien shall attach to the moneys in the hands of the municipality set apart or appropriated for the payment of the sums due or to become due upon the contract for the improvement, and a corresponding difference is made as to the offices in which liens, claims, assignments and incumbrances of every nature are to be filed or recorded.
In short, in the case of a public improvement the money due or to become due from the municipality under the contract for the improvement is substituted for and stands in the place of
The history of the Lien Law and its development shows a great and constantly increasing degree of consideration by the Legislature for the claims of laborers and materialmen, one evidence of which is to be found in section 13 itself, which as to liens upon real estate gives to liens for labor and materials unquestioned preference over advances made after the filing of such liens, no matter how absolute in form the incumbrances upon the real estate may be. It seems quite unreasonable to suppose that it was the intention of the Legislature to extend to laborers and materialmen engaged upon public improvements less protection than it clearly extended to the same persons engaged upon private work. No plausible reason suggests itself why such an invidious distinction should have been intended, and there seems to be every reason why it should not.
Does the language of section 13 of the Lien Law constrain us so to construe it as to discriminate against laborers and materialmen engaged, upon public improvements ? In my opinion it does not. Conceding that the word “ incumbrance ” is not a happy one to express the idea of a lien upon a fund of money, still it may, I think, be properly construed in this case to include such a lien.- Undoubtedly the right of the contractor to be paid for the work done under the contract was a property right. The assignment of the money due or to grow due thereunder created a lien upon the fund, which would ripen into a right of collection by the assignee only in case the assignor failed to repay the advances. In this sense the assignment may properly, I think, be considered as an “ incumbrance ” upon the fund; that is to say, a claim upon it which would stand in the way of a collection and enjoyment of the fund by the contractor until he had removed the lien by payment.
The word “ incumbrance ” is generally used in the books with reference to real estate, and has been defined as a right or interest in land which may subsist in another to the diminution of the value of the land to the owner. (Wetmore v. Bruce, 118 N. Y. 319; Dieterlen v. Miller, 114 App. Div. 40.) In a
The judgment appealed from should be affirmed, with costs to the respondent Fredenburg & Lounsbury as against the Royal Company, and to said Royal Company as against the appellant the Hildreth Granite Company.
Clarke, P. J., and McLaughlin, J., concurred; Laughlin and Page, JJ., dissented.
Dissenting Opinion
On the 23d day of July, 1913, the city of New York entered into a contract in writing with the Acme Asphalt and Granite Paving Company for regulating and repaving Second avenue from Sixtieth street to Sixty-first street, and from Sixty-third street to Seventy-fourth street, borough of Manhattan, New York. An abstract of the contract contained in the record shows that the estimated cost of the work was $90,870, and that by the terms of the contract ninety per cent was to be paid in installments on engineer’s certificates as the work progressed, and the balance was to be paid on engineer’s final certificate. The contract was completed and accepted on the 16th day of February, 1914, and the total amount earned by the contractor and due from the city was the sum of $86,438.98.
On the 14th day of August, 1913, the Acme Company, as party of the first part, and the Royal Company, as party of the second part, entered into a contract in writing under seal and acknowledged, reciting that said contract for regulating and repaving Second avenue had been let to the Acme Company; that the Acme Company was desirous of procuring financial assistance to “help it carryout said contract and to pay for material and labor and expenses tobe incurred in carrying out and completing said contract,” and that the Royal Company had agreed to procure and advance money to the Acme Company for that purpose, and the Royal Company thereby agreed to advance to the Acme Company the sum of $85,000 “for the purpose of enabling” it to go on with said work, and to advance said amount in such sums at such times as might be required by the Acme Company, and the Acme Company thereby agreed to pay the Royal Company a commission of five per cent “upon all sums so procured and advanced.” The final paragraph of the agreement obligated the Acme Company to assign, transfer and set over to the Royal Company “ all sums due and to grow due upon said contract for paving, between first party and the City of New York hereinbefore referred to, the amount of Eighty-five thousand ($85,000.00) Dollars.” The Acme Company on the same day duly executed and delivered to the Royal Company an assignment also under seal and duly acknowledged, of the “money
The trial court found and held that the assignment was not intended to be absolute, but was merely intended as security for moneys advanced under the agreement; and the decision of the trial court proceeded upon the theory that the assignment in no manner protected the assignee with respect to commissions as against subsequent lienors. The agreement did
The controlling question in the case, therefore, is presented by the contention of counsel for the Eoyal Company, appellant, that the assignment gave it the right to the entire amount of the moneys due and to grow due thereafter on the contract, and that there was no fund to which the liens subsequently filed could attach; and if he be right in that contention it will not become necessary to consider any other question with respect to the rights of lienors, for no lien was filed until long after the filing of the assignment.
Counsel for the lienors contend that an assignment is an incumbrance, within the contemplation of the provisions of the first sentence of section 13 of the Lien Law (Consol. Laws chap. 33; Laws of 1909, chap. 38), which, so far as material, is as follows: “A lien for materials furnished or labor performed in the improvement of real property shall have priority over a conveyance, judgment or other claim against' such property not recorded, docketed or filed at the time of filing the notice of such lien; over advances made upon any mortgage or other incumbrance thereon after such filing; * * That is the theory upon which the judgment at Special Term
The trial court found the balance due to the Boyal Company from its assignor both for advances and for commissions, but instead of directing a personal judgment therefor, provided in the conclusions of law that the Boyal Company might apply to the court at the foot of the decree to.be entered for judgment against its assignor for the amount of such deficiency. The Boyal Company did not appeal from this part of the decree, and its assignor did not appear on the appeal. Counsel for the Boyal Company requests this court to grant the deficiency judgment, but since it has not presented that question by the appeal, I think it should be left where the decision of the trial court left it without a modification of the judgment in that respect.
It follows, therefore, that the judgment in so far as appealed from by the Hildreth Granite Company should be affirmed, and as to the appeal of the Boyal Company the judgment should be modified by directing the payment of the balance of the fund to the appellant the Boyal Company, with costs to said appellant against the appellant the Hildreth Granite Company and the respondents the plaintiff and Fredenburg & Lounsbury, and that the findings and conclusions of law of the trial court be modified accordingly.
Page, J., concurred.
Judgment affirmed, with costs to the respondents Fredenburg and Lounsbury as against the Boyal Company, and to said Boyal Company as against the appellant the Hildreth Granite Company. Order to be settled on notice..
Amd. by Laws of 1887, chap. 430, and Laws of 1895, chap. 678.— [Ref.