Two actions on a contractor’s bond tried together. There were findings and judgments for the plaintiffs. The defendant surety company appeals from the judgments. The defendant contractor does not appear on this appeal.
Two general questions are presented:
(1) Whether an action on the bond was barred by the provisions of the city charter pursuant to which it was executed, requiring notice to be given the contractor and surety within 90 days after the date of the last item furnished and suit to be brought within a year.
(2) If not, whether an extension to the contractor by the plaintiff of the time of payment, without the consent of the surety, released the surety without a showing that harm resulted; and whether resulting harm was shown.
The charter provided that no action should be maintained upon the bond, unless the claimant, within 90 days after furnishing the last item, served upon the principal and surety a written notice, specifying the nature and amount of his claim and the date of the last item, nor unless action was commenced within one year after such date. Neither of the plaintiffs gave notice within 90 days nor commenced an action within one year. The surety company claims that their causes of action are barred.
On December 3, 1913, the city ratified a new charter. The Constitution provides that upon its ratification a charter “shall, at the end of thirty days thereafter, become the charter of such city or village as a city, and supersede any existing charter and amendments thereof.” Const, art. 4, § 36. The charter became effective and superseded the former charter on January 3, 1913. Woodbridge v. City of Duluth,
The suggestion is made that the bond was not effective after the repeal of the statute, which authorized and required it. Under our decisions a municipal corporation has no authority without a legislative grant of power to take contractors’- bonds for the benefit of those furnishing material, and contracts taken without authority are void. Breen v. Kelly,
The defendant contends that if the obligation of the bond survives the repeal of the charter the provision as to the 90-days’ notice and the bringing of an action within a year follows as a part of it, and applies when its enforcement is sought. If so, the plaintiffs are barred. Grant v. Berrisford,
The provision as to bringing an action within a year gives no trouble. It is a statute of limitation. A statute of limitation affects the remedy and not the right. 2 Dunnell, Minn. Dig. § 5587, and cases cited. The repeal of the statute leaves the action without a limitation. Lambert v. Slingerland,
Upon the repeal of the charter the similar provision of the general statute, G. S. 1913, § 8249 (E. L. 1905, § 4539, as amended by Laws 1909, p. 501, c. 413, § 1), giving a similar but different condition and a similar but different limitation, did not become applicable. The charter provision, as held in Grant v. Berrisford,
We hold that the effect of the adoption of the new charter was to abrogate or repeal the former one; that the obligation of the contract evidenced by the bond continued; that the repeal affected the remedy only and did not impair the obligation of the contract in a constitutional sense; that, the 90-day period and the year limitation not having run when the new charter became effective, suit could be brought without giving notice and after the year; and that upon the. repeal the general statute containing,a like condition and limitation did not apply to a prior ac crued cause of action.
A valid agreement between the principal and the creditor extending the time of payment, without the consent of the surety, releases him. Leithauser v. Baumeister,
McDonnell filed his voluntary petition and was adjudged a bankrupt on November 19, 1913. He was discharged on February 12, 1914. The six months extension expired on August 20, 1913. From these facts harm does not conclusively appear.
Judgment affirmed.
