134 Minn. 121 | Minn. | 1916
Two actions on a contractor’s bond tried together. There were findings and judgments for the plaintiffs. The defendant surety company appeals from the judgments. The defendant contractor does not appear on this appeal.
Two general questions are presented:
(1) Whether an action on the bond was barred by the provisions of the city charter pursuant to which it was executed, requiring notice to be given the contractor and surety within 90 days after the date of the last item furnished and suit to be brought within a year.
(2) If not, whether an extension to the contractor by the plaintiff of the time of payment, without the consent of the surety, released the surety without a showing that harm resulted; and whether resulting harm was shown.
The charter provided that no action should be maintained upon the bond, unless the claimant, within 90 days after furnishing the last item, served upon the principal and surety a written notice, specifying the nature and amount of his claim and the date of the last item, nor unless action was commenced within one year after such date. Neither of the plaintiffs gave notice within 90 days nor commenced an action within one year. The surety company claims that their causes of action are barred.
On December 3, 1913, the city ratified a new charter. The Constitution provides that upon its ratification a charter “shall, at the end of thirty days thereafter, become the charter of such city or village as a city, and supersede any existing charter and amendments thereof.” Const, art. 4, § 36. The charter became effective and superseded the former charter on January 3, 1913. Woodbridge v. City of Duluth, 121 Minn. 99, 140 N. W. 182. The new charter contained no condition requiring the giving of a notice or limiting the time within which an action might be brought nor any provision relative to bonds.
The suggestion is made that the bond was not effective after the repeal of the statute, which authorized and required it. Under our decisions a municipal corporation has no authority without a legislative grant of power to take contractors’- bonds for the benefit of those furnishing material, and contracts taken without authority are void. Breen v. Kelly, 45 Minn. 352, 47 N. W. 1067; Park Bros. & Co. v. Sykes, 67 Minn. 153, 69 N. W. 712; Eidsvik v. Foley, 99 Minn. 468, 109 N. W. 993. This holding is upon the ground of the legal incapacity of the city to act as trustee for the beneficiaries. The bond was a valid obligation when executed, and under it rights arose. The adoption of the new
The defendant contends that if the obligation of the bond survives the repeal of the charter the provision as to the 90-days’ notice and the bringing of an action within a year follows as a part of it, and applies when its enforcement is sought. If so, the plaintiffs are barred. Grant v. Berrisford, 94 Minn. 45, 101 N. W. 940, 1113, involved the St. Paul home rule charter which did not contain a provision like that now under consideration. The general statute contained a provision of like purpose but of different requirements. The question was whether a complaint on the bond must allege notice and the answer depended upon whether the charter or statute controlled. The court said: “The provision in the general law requiring notice within 90 days after the last item of labor or materials is done or performed, before bringing an action on the bond, is not analagous to a statute of limitations, but it is a condition precedent which must be performed before the right to bring an action on the bond accrues. Or, in other words, it is a condition or burden placed upon the beneficiaries of the bond which they must perform or remove before they can avail themselves of its benefits. It is as much so as would be the case if this provision of the general statute was set out as a proviso in the bond.” The direct holding was that the charter provision was exclusive. The statute in its present form is found in G. S. 1913, § 8249 (B. L. 1905, § 4539, as amended by Laws 1909, p. 501, c. 413, § 1). It provides that notice must be served within 90 days after the completion and acceptance of the contract and suit within one year after the notice.
The provision as to bringing an action within a year gives no trouble. It is a statute of limitation. A statute of limitation affects the remedy and not the right. 2 Dunnell, Minn. Dig. § 5587, and cases cited. The repeal of the statute leaves the action without a limitation. Lambert v. Slingerland, 25 Minn. 457; Kipp v. Johnson, 31 Minn. 360, 17 N. W. 957; Lunt v. Stevens, 24 Me. 534; Stewart v. Tennant, 52 W. Va. 559, 44 S. E. 223; San Francisco & F. Land Co. v. Hartung, 138 Cal. 223, 71 Pac. 337; Davis v. Mills, 121 Fed. 703, 58 C. C. A. 123. “It is conceded that no one has a vested right in any particular remedy, and that the legislature may change or modify the existing remedies for the enforcement and protection of contract rights so long as an adequate remedy remains.” State v. Krahmer, 105 Minn. 422, 117 N. W. 780, 21 L.R.A. (N.S.) 157. “No one can claim a right to the continuance of a mere statute of limitation until a cause of action against him is barred thereby.” State v. Foster, 104 Minn. 408, 116 N. W. 826.
Upon the repeal of the charter the similar provision of the general statute, G. S. 1913, § 8249 (E. L. 1905, § 4539, as amended by Laws 1909, p. 501, c. 413, § 1), giving a similar but different condition and a similar but different limitation, did not become applicable. The charter provision, as held in Grant v. Berrisford, 94 Minn. 45, 101 N. W. 940, 1113, was exclusive while in effect. When repealed the general statute was not operative upon rights accrued. Whether the general statute applies to contracts executed or performed after the repeal is not before us.
We hold that the effect of the adoption of the new charter was to abrogate or repeal the former one; that the obligation of the contract evidenced by the bond continued; that the repeal affected the remedy only and did not impair the obligation of the contract in a constitutional sense; that, the 90-day period and the year limitation not having run when the new charter became effective, suit could be brought without giving notice and after the year; and that upon the. repeal the general statute containing,a like condition and limitation did not apply to a prior ac crued cause of action.
A valid agreement between the principal and the creditor extending the time of payment, without the consent of the surety, releases him. Leithauser v. Baumeister, 47 Minn. 151, 49 N. W. 660; 28 Am. St. 336; Bandler v. Bradley, 110 Minn. 66, 124 N. W. 644; Farmers Supply Co. v. Weis, 115 Minn. 428, 132 N. W. 917; J. R. Watkins Medical Co. v. McCall, 116 Minn. 389, 133 N. W. 966; 3 Dunnell, Minn. Dig. § 9096, and cases cited. The reason is sometimes said to be that an extension deprives the surety, who is entitled to subrogation upon payment, of the right to sue immediately, and from this the law conclusively presumes injury." See Travers v. Dorr, 60 Minn. 173, 62 N. W. 269. The result does not come from a’ provision to that effect in the contract, for there is none. It comes from a rule of construction adopted by the law for the protection of sureties. They are favorites of the law. It permits the creditor to do nothing which will injure them; and it has come to presume that certain things result in injury and will not inquire. The rule of strictissimi juris is applied in their favor, and largely the reason is that their undertaking is gratuitous. The defendant is a paid surety. The coming of corporations authorized by statute to become sureties, receiving premiums for the risks they assume, brings a distinct change in the business of securing the performance of contracts. The law meets the changed business situation by the changed construction. The rule of construction applicable to the contract of a gratuitous surety, always so much the favorite of courts that every intendment is in his favor, does not apply when the surety is a paid surety. Their undertakings are in the nature of insurance contracts. Lakeside Land Co. v. Empire State Surety Co. 105 Minn. 213, 117 N. W. 431; Brandrup v. Empire State Surety Co. 111 Minn. 376, 127 N. W. 424; George A. Hormel & Co. v. American Bonding Co. 112 Minn. 288, 128 N. W. 12, 33 L.R.A. (N.S.) 513; Allen v. Eneroth, 118 Minn. 476, 137 N. W. 16. Our cases reflect the holdings of other courts. The unmistakable trend is as stated and the result is wholesome. Note to George A. Hormel & Co. v. American Bonding Co. [112 Minn. 288, 128 N. W. 12], in 33 L.R.A. (N.S.) 513, note
McDonnell filed his voluntary petition and was adjudged a bankrupt on November 19, 1913. He was discharged on February 12, 1914. The six months extension expired on August 20, 1913. From these facts harm does not conclusively appear.
Judgment affirmed.