225 A.D. 407 | N.Y. App. Div. | 1929
Defendant contracted to dredge 40,000 cubic yards of earth from the Hudson river in front of plaintiff’s premises
According to the terms of the contract with plaintiff, defendant was required “ to apply for and obtain any necessary permits from town, municipal, State or Federal authorities to complete the said work.” Defendant began work upon the contract, dredged 2,250 cubic yards of earth from the river in front of plaintiff’s premises and placed it thereon. The contract was abandoned when the United States Division Engineer declined to sanction the dumping of spoil into the river at the place dredged in front of plaintiff’s lands, from which point it was to be transferred to the uplands by hydraulic suction.
The circumstances connected with the refusal were that the Resident Assistant Engineer at Albany made the following indorsement upon defendant’s application: “ There is no objection to the proposed dumping excepting that it is not deemed advisable to dump the material eastward of the red line on the blue print. It is recommended that permission for the spoiling in question, subject to that proviso, be granted.” „ The Division Engineer, withholding his approval, wrote: “ In view of the complaints regarding shoaling of the Hudson River at Albany, I do not consider it advisable to grant this request, and the dumping grounds designated in the contract must be adhered to.” The determination of the Division Engineer could have been reviewed by the Chief Engineer, and his in turn by the Secretary of War.
Defendant would have violated a Federal statute if it had used the government spoil without permission. (Rivers and Harbors Act of 1905 [33 TI. S. Stat. at Large, 1147], § 4, approved March 3, 1905; now U. S. Code, tit. 33, § 419.) From this defendant argues that performance involved the commission of a crime, and that, therefore, the contract was invalid. This position is untenable. (Raner v. Goldberg, supra.) The opinion in that case (at p. 440) states “ the parties in mailing the contract or lease did not intend that the premises should be used for an illegal purpose. They intended that the demised premises should be used as a dance hall only when the lessee had obtained a license. A contract so made is not unlawful. (Shedlinsky v. Budweiser Brewing Co., 163 N. Y. 437.) ”
After ample notice to the defendant and its surety, plaintiff contracted for the performance of the work which defendant had abandoned. The new contractor was to dredge 37,750 cubic yards from the river in front of plaintiff’s premises, and the additional 100,000 cubic yards of filling material could be obtained from any
The first item was properly allowed. The second item was allowed at $13,000. The court fixed twenty-five cents a cubic yard as a reasonable price for 100,000 cubic yards of fill. The evidence most favorable to the defendant does not justify a lower price than forty cents a cubic yard. This item should be increased from $13,000 to $28,000. While under the new contract, plaintiff paid the same price for all the material, a trier of the facts would be justified in establishing a differential between the 37,750 cubic yards which involved submarine excavation, in which the resulting contour of the river bottom had to be regarded, and a definite amount of spoil taken from a limited area even though it was difficult, and the 100,000 cubic yards as to which the sole requirement was the production of filling material, and the dredging could be done at any place in the river advantageous in respect of location and ease of moving earth. The third item was properly disallowed. Nothing in the contract indicates that the parties had in mind the purposes for which the fill was to be made, and the complaint does not allege special damages. (Jutte v. Hughes, 67 N. Y. 267; Argotsinger v. Vines, 82 id. 308; Isman v. Loving, 130 App. Div. 845.) Even if defendant was chargeable with knowledge that the filling was to provide a foundation for oil tanks, the proper measure of damage would have been the value of the use of the tanks while plaintiff was deprived thereof in consequence of the delay. (Buff v. Rinaldo, 55 N. Y. 664; Hexter v. Knox, 63 id. 561; Cassidy v. LeFevre, 45 id. 562; Beisert v. City óf New York, 174 id. 196; 9 C. J. 793.)
Van Kirk, P. J., Hinman, Davis and Whitmyer, JJ., concur.
Judgment modified by increasing the amount of plaintiff’s damages to $31,630, with interest thereon from March 20, 1926, and as so modified affirmed, with costs to the plaintiff.