The suit is by the appellee against appellant as surety on a road contractor's bond executed pursuant to statute. Gen. Acts 1927, p. 356, § 28. The contractor had sublet a portion of the road work to one Myrtle Boyd. The subcontractor owned and operated, in the progress of this work, a "tractor and steam shovel," which constitutes a single machine composed of many parts. While engaged in the work this machine became damaged and disabled, and its repair is referred to as a "hurry up job."
The shaft or axle, which was from six to eight feet long and about six inches in diameter, broke and had to be replaced. It cost $65. The old parts, such as sprockets and the like, were placed back on this new shaft and the tractor put in condition to proceed with the work. The oil pump also required attention, but labor was all that was necessary for its adjustment, no material being used therefor. The work was referred to as a "running repair * * * fixed while it is in action." Plaintiff did the work and furnished the material, working "night and day" a period of sixty hours, until the job was finished. The work and material amounted to a total of $188, all of which represented labor except the $65 for the shaft. The value of the machine was $16,000.
The original contractor, as a witness for defendant, testified that on "a value basis the shaft was just insignificant and small in comparison to the value of the entire equipment or machinery, but it was very essential to its operation." The same witness also stated that after the repair the machine was used in the work for only ten working days when the subcontractor abandoned the job and the machine was moved away.
Appellant insists the machine was a part of the subcontractor's equipment and its repair does not come within the protection of the bond, placing much reliance upon Union Indemnity Co. v. State,
In Union Indemnity Co. v. State, supra, it was pointed out that questions as to allowance for repairs on the contractor's equipment are attended with much difficulty dependent upon the facts in each particular case, and it was there held that "such extraordinary repairs," as there involved, for the purpose of which the equipment was shipped to another state, did not come within the protection of the bond.
In a later case (United States F. G. Co. v. Benson Hardware Co.,
The cases of Clifton v. Norden,
We indulge no discussion here further than to note the expression "small and incidental repairs" must necessarily have a relative meaning and bear relation to the value of the machinery so under repair. Illustrative is the instant case where a machine valued at $16,000 becomes disabled while in use and hasty repair becomes necessary that the work may proceed with proper speed, and by continuous labor for sixty hours the repair is effected and the work progresses. All of the old parts were used with the exception of a shaft or axle which had to be replaced at a cost of $65. There was no general overhauling, but only such work done and repairs made as to again place the machine in workable condition. All of which may properly be classed as work done in the performance and execution of the contract, and the fact that the replaced shaft or the machine may outlast the job is not the test of liability in cases of this character as pointed out in the case of United States F. G. Co. v. Benson Hardware Company, supra. The total repair bill, including the shaft, was $188, and as compared to the value of this machine ($16,000), and considered in connection with all the facts here presented and without dispute, may well be said to come within the meaning of a small and incidental repair protected by the bond.
It appears that the subcontract was made in the name of Myrtle Boyd, though the verbal agreement had been with the husband, C. H. Boyd, both husband and wife being present at the time, but when reduced to writing was put in the name of the wife on account of outstanding obligations of the husband. It is without conflict, however, that the work was in charge of the husband, and it was under agreement with the husband that plaintiff did the work. In legal effect the contract was with the subcontractor, the wife, made by and through her authorized agent, the husband, and we see no obstacle in the way of plaintiff's recovery by reason of the situation above outlined.
The reasonableness and correctness of plaintiff's account are not questioned, and, as we are persuaded the undisputed proof entitled plaintiff to recover, it results as our conclusion that the court correctly gave the affirmative charge in his favor. The judgment is therefore due to be affirmed, and it is so ordered.
Affirmed.
ANDERSON, C. J., and BOULDIN and FOSTER, JJ., concur.
