This case is before the court on the accelerated docket pursuant to App.R. 11.1 and LocApp.R. 25.
Defendants-appellants, URS Consultants (“URS”), and Zannoni Heckman and Payto Partnership, Inc. (“ZHP”), argue that the trial court erred by denying their joint motion to stay the proceedings pending arbitration. Plaintiff, St. Vincent Charity Hospital, Inc., responds that the trial court was correct because URS, not being a signatory to the contract, cannot enforce an arbitration clause in the contract. We affirm the judgment of the court below. The relevant facts follow.
St. Vincent contracted with ZHP for ZHP to provide design and construction management services in connection with the construction of the Rockside Ambulatory Surgery Suite project. ZHP is a design firm of architects. After work had commenced, URS, a design firm of architects and engineers, began to work on this project for St. Vincent. Regarding the relationship between the parties at this point, the parties agree that (1) certain principals and employees left ZHP and joined URS, (2) URS began providing services to St. Vincent for this project, (3) employees of ZHP continued to work on the project, and (4) St. Vincent made certain payments directly to URS.
The contract between St. Vincent and ZHP contained the following arbitration clause:
“7.1 Claims, disputes or other matters in question between the parties to this Agreement arising out of or relating to this Agreement or breach thereof shall be subject to and decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise.”
On February 15, 1995, St. Vincent filed a complaint against ZHP and URS regarding the construction of the surgery center. The complaint alleged (1) breach of contract, (2) negligent performance under the contract, and (3) breach of express and implied warranties. On June 16, 1995, defendants filed a joint motion to stay the proceedings because the controversy was within the scope of
“1. Whether the trial court improperly ruled that the claims raised in the complaint of plaintiffs-appellees are not arbitrable.
“2. Whether the trial court erred when it denied defendants-appellants’ joint motion to stay proceeding pending arbitration, which was filed pursuant to Section 2711.02 of the Ohio Revised Code.”
Generally, Ohio law favors arbitration as an efficient and economical alternative dispute resolution mechanism.
Schaefer v. Allstate Ins. Co.
(1992),
The court in
Didado v. Lamson & Sessions Co.
(1992),
“A clause in a contract providing for dispute resolution by arbitration should not be denied effect unless it may be said with positive assurance that the subject arbitration clause is not susceptible to an interpretation that covers the asserted dispute. In examining such a clause, a court must bear in mind the strong presumption in favor of arbitrability, and any doubts should be resolved in favor of coverage under the arbitration clause.” (Citations omitted.)
In
Kline v. Oak Ridge Bldrs.
(1995),
Defendants argue, on the other hand, that “[i]n examining an arbitration clause, a court must bear in mind the strong presumption in favor of arbitrability and resolve all doubts in favor of arbitrability.”
Neubrander v. Dean Witter Reynolds, Inc.
(1992),
There being no evidence of a contract between URS and St. Vincent, we do not reach this stage of resolving ambiguities. The record in the case at bar is limited. The contract between ZHP and St. Vincent contained an arbitration clause. However, it is undisputed that URS was not a party to this contract. An appellant bears the burden of showing error on appeal by reference to matters in the record.
Knapp v. Edwards Laboratories
(1980),
Judgment affirmed.
Notes
. Ignoring the format prescribed in App.R. 16, appellants have presented their assignments of error in the form of questions.
