St. Tammany Manor, Inc. v. Spartan Building Corp.St. Tammany Manor, Inc. v. Spartan Building Corp.
Richard L. Muller, Mandeville, for appellant.
Before REDMANN, GULOTTA and CIACCIO, JJ.
GULOTTA, Judge.
In this building contract dispute, the sole issue is whether interest on an arbitration award commences from the date of substantial completion or the date the arbitration award was made. The trial judge concluded the interest commenced from the date of the award. We affirm.
On September 26, 1980, Spartan Building Corporation entered into a contract with St. Tammany Manor, Inc. for the construction of a lodge. The stipulated completion date was September 26, 1981. At the time the contract was substantially completed, a dispute arose as to the amount owed. St. Tammany claimed a retainage in the sum of $291,212.65 for “items of construction which were either deficient, incomplete or remained to be performed by the contractor.” Spartan, on the other hand, contended that the balance owed on the contract was $172,986.75.
The matter was submitted to an arbitration panel and an award was rendered by the arbitrators on January 18, 1984, which provided that “St. Tammany Manor, Inc.... pay Spartan Building Corp.... ($172,986.75) and that Spartan pay St. Tammany ($27,344.00).” The award further provided that St. Tammany pay interest on the net amount owed from September 30, 1981, the apparent substantial completion date, until paid.
St. Tammany subsequently filed a petition requesting that the arbitration award be modified to provide that interest commence from the date of the arbitration award (January 18, 1984) instead of the date of substantial performance as determined by the arbitrators. In a separate suit, Spartan sought to have the award confirmed. The cases were consolidated and a summary judgment was rendered modifying the interest part of the arbitration award to reflect that interest commences from the date of the award.
Prior to 1985
The same rule is applicable in our case. Our holding in City Stores is dispositive of the issue in the instant case.
Having so concluded, we affirm the judgment of the trial court.
AFFIRMED.
REDMANN, C.J., dissents.
REDMANN, Chief Judge, dissenting.
“A. Where there was an evident material miscalculation of figures or an evident material mistake in the description of any person, thing, or property referred to in the award.
“B. Where the arbitrators have awarded upon a matter not submitted to them unless it is a matter not affecting the merits of the decision upon the matters submitted.
“C. Where the award is imperfect in matter of form not affecting the merits of the controversy.”
“It is well settled in both state and federal courts that an award may be challenged only on the grounds specified in the statute. The court cannot substitute its conclusion for that of the arbitrator.” Firmin v. Garber, 353 So. 2d 975 (La.1977).
None of the statute‘s grounds exists here. The trial court violated
The lesson of Firmin is that, no matter how “debatable” an award (Firmin so described a $7,821.60 award to an architect whose bill had been only $3,800), the statute controls. “To hold otherwise would defeat the purpose of arbitration: the speedy resolution of disputes outside the court system.” Id. at 978.
The judgment appealed from should be reversed and an order granted confirming the arbitrators’ award as issued.