42 Minn. 222 | Minn. | 1889
1. It seems to us, to use the language of the court below, that defendants’ case “has nothing to rest on.” The “notice to proposers” for the construction of plaintiff’s shops contained plans and specifications of the buildings; also estimates by plaintiff’s en
2. Both parties have discussed the second assignment of error as if the offer referred to was of evidence that Patterson had furnished material for extra work not specified in the plans. We find nothing in the record to indicate that such was the offer, but we will treat it as the parties both seem to have understood it. The contract expressly gave the company the right to extend the contract so as to cover any additional work of the same nature that might be ordered by its chief engineer; also- the right to make any such alterations or omissions of any of the work specified in the drawings as the chief engineer might consider desirable or necessary. It was solely with reference
3. In the absence of all the evidence, we must assume that it fully justified the finding of the trial court that all the extra or additional work done by Patterson was similar to that specifically mentioned in the contract, and hence covered by it. The defendants, upon the authority of Lautenschlager v. Hunter, 22 Minn. 267, make the point that plaintiff could not avail itself of the provisions of the contract to exclude the evidence referred to in the first and second assignments of error, unless specially pleaded. No such point seems to have been made in the court below; but the court finds, as a fact, that after the work was completed the chief engineer made a final estimate showing the whole amount of compensation payable to the plaintiff under the contract, including all extras. The presumption is that this was justified by the evidence, and that such evidence was admitted without objection, and that the parties voluntarily consented to try all issues covered by the findings of the court, whether within the pleadings or not.
To the suggestion that the sureties were released by the failure of the plaintiff to withhold from Patterson 15 per cent, of the approx
Order affirmed.
ÍTote. ' Amotion for a'reargument of this case was denied January 3, 1890.