194 Mo. App. 440 | Mo. Ct. App. | 1916
This is a suit to enforce two mechanic’s liens. Plaintiff recovered and defendants prosecute the appeal.
The first lien asserted is for the amount of $577 and the second for the amount of $297. The first lien hot-
In making its case, plaintiff introduced the original contract between the owners of the property and the construction company, which required the completion of the building by the original contractor on or before September 23, also that the fire doors, when installed, should be approved by the St. Louis Fire Prevention Bureau.
It is argued that no recovery should be allowed, for that it does not appear the terms of this contract were complied-with. It is'to be said, in this connection, that no delay is pointed out attending the conduct of plaintiff, but it does appear the original contractor did not complete the building, which was due on September 23, until probably about the first of December thereafter. Plaintiff installed the doors, as is usual, when the other work was about completed, and, according to all of the evidence, before the building was completed by the original contractor. ' .
It is earnestly argued that, as the contract between the owners and the construction company required the doors to be approved by the St. Louis Fire Prevention Bureau, plaintiff is not entitled to recover because there is no evidence that they were so approved, but obviously this is a misconception of the record. There is- an abundance of evidence to the effect that, after the doors were installed, the Fire Prevention Bureau inspected them and made certain requirements, all of which were complied with by plaintiff, and that no further complaint was made thereafter. Moreover, defendant introduced
Touching the argument to the effect that plaintiff did not show the doors were installed within the time limited in the contract for the completion of the building —that is, September 23 — it is to be said that there is no possible merit in this. In the first place, whatever delay was occasioned in the construction of the building — and of this there appears to be no particular complaint, in the record — was entailed in some manner by the L. B. Wright Construction Company. There is some evidence that the building was completed in November, and there is some evidence that it was completed about December \ and some, after December 25, but all of the evidence is, that the matter of installing the doors was necessarily deferred until the other work was about completed. The doors were installed, according to defendants’ evidence, when they moved .into the building, but all of the evidence shows that this was subsequent to September 23.
Another argument is to the effect that the contract required the jackknife doors to be installed according to the plans and specifications and that such plans and specifications are not in evidence. Because of this it is said plaintiff has. failed to show a compliance with the contract, but it is enough -to say of this that 'the matter was not referred to at the trial, and, indeed, defendants’ evidence all goes to the effect that the doors were perfect-—indeed, extremely satisfactory in every respect.
In the lien account there are some items with respect to the hours of labor employed in installing the doors, and the evidence is rather meager with respect to the hours of labor. It is argued both liens must fail because of this, but the point is without merit, for the contract, the lien papers, and, indeed, the entire record, disclose that the fire proof doors and the angle sills and also the jackknife doors were to be installed at set figures, which include labor as well as the material in the doors. The evidence is abundant that the doors were installed according to the contract and at the price agreed upon, also that the price was a reasonable one. All of the items in connection with the installation of the doors and angle sills, including the labor, were lienable. This court, on a similar question, has heretofore said:
“A charge is not a ‘lumping’ one where it includes only lienable items which are the subjects of an express contract for a given price which (in case of a subcontract) is also shown to be the reasonable value thereof.” [Holland v. Cunliff, 96 Mo. App. 67, 80, 69 S. W. 737.]
The debatable question in the case relates to the matter contemplated in plaintiff’s fourth instruction. It appears that plaintiff undertook to install the slide fire doors for the general contractor at the agreed price of $525. Shortly thereafter it was ascertained that the doors would not be fire proof unless angle sills were
“IV The jury are instructed that the several items of $525 and $52 for work and materials embraced in the lien account of $577 were not furnished under one contract, but under two different contracts, and if said lien account was filed within four months after the completion of the work under either or both of such contracts, then as to such of the contracts so completed within four months from the filing of said account, said lien account was filed within the time required by law.”
This instruction recognizes and treats with the matter of installing the fire doors at $525 as one contract
“It is the law that where there are separate contracts between a building contractor and an owner for the performance of different jobs, in order for a lien account filed by the contractor, to be good for the entire work, it must be filed within the statutory period after the completion of the work under each contract.” [See Darlington Lumber Co. v. Harris, 107 Mo. App. 148, 153, 80 S. W. 688.]
This instruction first concedes that there were two separate contracts — one at $525 and one at $52 — for work and materials embraced in the account of $577. After so doing, it directs the jury that if the lien account was filed within four months after the completion of the work, under either one of these or both of these contracts, “then, as to such of the contracts so completed within four months,” the lien was filed in time. The instruction appears to be well enough. The judgment ought not to be reversed for this, when it appears from the letter of the Vivianos in evidence that they actually required plaintiff to make certain corrections about this particular work some time after December 23, so as to clearly extend the time — that is, by completing their task on fire proof doors and sills — for filing the lien, under all of the authorities with which we are familiar. Besides the case last above cited, see, also, Darlington Lumber Co. v. Smith Bldg. Co., 134 Mo. App. 316, 114 S. W. 77. In this connection, it is to be said that what plaintiff undertook to do in the first instance was to install fire doors and it turned out that, to render them fire proof, it was necessary that angle sills — that is, metal sills—
In this view, the judgment should be affirmed notwithstanding the criticism to the instruction. It is so ordered.