St. John's University v. Butler Rogers Baskett Architects, P.C.St. John's University v. Butler Rogers Baskett Architects, P.C.
Ordered that the orders are affirmed insofar as appealed from, with one bill of costs.
The Supreme Court properly denied, as untimely, the first motion of the defendant Langan Engineering and Environmental Services, Inc., P.C. (hereinafter Langan) for summary judgment dismissing stated portions of the complaint since Langan failed to demonstrate good cause for not filing the motion before the expiration of the 120-day deadline set forth in
The Supreme Court also properly denied Langan‘s second motion for summary judgment as violative of the rule against successive motions for summary judgment (see Blanche, Verte & Blanche, Ltd. v Joseph Mauro & Sons, 91 AD3d 693 [2012]; Kimber Mfg., Inc. v Hanzus, 56 AD3d 615 [2008]).
Eng, P.J., Dickerson, Hall and Lott, JJ., concur.