SQUARE D COMPANY v. C. J. KERN CONTRACTORS, INC., and SIX ASSOCIATES, INC.
No. 8328SC468
Court of Appeals of North Carolina
(Filed 21 August 1984)
70 N.C. App. 30
The majority has not discussed, and apparently has not considered, defendant‘s assignment of error relating to damages. If the trial court did not err in denying defendant‘s motions for a directed verdict and judgment notwithstanding the verdict, in my opinion, the defendant is entitled to a new trial because the record discloses a manifest miscarriage of justice with respect to the issue of damages. Under the circumstances of this case it is clear to me that the cost of replacing a three-and-one-half ton air conditioning unit, which is in no way defective and is no more than four-and-one-half years old, with a new four ton unit is not the correct measure of damages.
1. Corporations § 22; Seals § 1— corporate seal on contract — 10-year statute of limitations inapplicable
In an action to recover for breach of contract and negligence on the part of defendant general contractor in the construction of a building, there was no merit to plaintiff‘s contention that the jury could have found that the contract between plaintiff owner and defendant contractor was under seal because the corporate seal was placed on the contract, and the trial court properly granted summary judgment for defendant, since the mere affixation of a corporate seal to a document does not automatically raise it to the status of an instrument under seal; the contract in question contained no recitals or other evidence of an intent to create an instrument under seal; and defendant‘s president averred that the corporate seal was placed on the contract for the purpose of indicating that its execution was duly authorized by the corporation and to confirm that he, as an individual, was not a party to it.
Plaintiff‘s action to recover for the alleged negligence of defendant architects in designing and inspecting a wall was barred by the statute of limitations where defendants completed their work for plaintiff prior to 1 January 1974 and plaintiff filed its complaint on 16 March 1982, more than six years from the last act or omission giving rise to the action.
Judge PHILLIPS dissenting.
APPEAL by plaintiff from Lewis, Robert D., Judge. Orders entered 7 January 1983 in Superior Court, BUNCOMBE County. Heard in the Court of Appeals 12 March 1984.
Long, Parker, Payne & Matney, P.A., by Ronald K. Payne and Mary Elizabeth Arrowood, for plaintiff appellant.
Brooks, Pierce, McLendon, Humphrey & Leonard, by James T. Williams, Jr., and Reid L. Phillips, for C. J. Kern Contractors, Inc., defendant appellee.
Kennedy, Covington, Lobdell & Hickman, by F. Fincher Jarrell, for Six Associates, Inc., defendant appellee.
WHICHARD, Judge.
I.
The trial court granted summary judgment in favor of defendants, a contractor and an architectural firm, on the ground that plaintiff‘s claims against them were untimely filed. We affirm.
II.
Count One of the complaint, which plaintiff filed on 16 March 1982, alleged the following:
In 1972 plaintiff entered a contract with defendant C. J. Kern Contractors, Inc. (Kern), as general contractor, for construction of an addition to a building on lands which plaintiff owned. Kern completed the construction pursuant to the contract.
On or about 1 November 1980 plaintiff, through its agents and employees, began to notice lateral bowing in a wall of the addition. The bowing was caused by Kern‘s deviations, in several respects, from the contract specifications. The structural integrity
As a direct and proximate result of Kern‘s deviation from the contract specifications and its breach of the contract, plaintiff incurred damages in repairing and stabilizing the wall in an amount in excess of $150,000. The defects in the wall, and breach of Kern‘s contract, were not apparent or discoverable until the damage occurred and the wall “bowed out.”
Count Two of the complaint made essentially the same allegations, except that the defects in plaintiff‘s wall were attributed to Kern‘s negligence in construction rather than to its breach of contract.
Count Three of the complaint alleged the following: In 1971 plaintiff entered a contract with defendant Six Associates, Inc. (Associates) for the provision of basic architectural services. Under the terms of that contract Associates subsequently undertook to provide architectural services on the construction by Kern of the addition to the building on plaintiff‘s land. Associates was negligent in designing the wall in question, and in the inspection of its construction, in specified respects. As a result of Associates’ negligence plaintiff incurred damages in repairing and stabilizing the wall in excess of $150,000.
Plaintiff prayed that “it have and recover, jointly and severally, of each of the Defendants . . . the sum of $150,000.00 . . . and the costs of [the] action.”
III.
Pursuant to
The parties stipulated that affidavits and evidence forecast by discovery could be considered by the court, and that Kern‘s motion could be treated as one for summary judgment. The pertinent matters outside the pleadings which the court considered included:
- An affidavit from the head of Associates’ Structural Engineering Department averring that Kern completed the addition to plaintiff‘s building prior to 1 January 1974, and that Associates completed all work performed under its contract with plaintiff prior to 1 January 1974.
- Plaintiff‘s admission, in response to Associates’ request, that Associates completed all work performed under its contract with plaintiff prior to 1 January 1974, except that “‘as built’ drawings may have been supplied in 1974.”
- Plaintiff‘s admission, in response to Kern‘s request, that Kern‘s acts or omissions in construction of the addition occurred more than six years prior to institution of this action.
- The deposition of plaintiff‘s plant engineering manager, who was responsible for “coordinating and working directly with” Kern and Associates, which stated:
It was late in 1973 when most of the work had been accomplished. The construction was finished by 26 November 1973. The “punch list may not have been completed” by then, “but in any event those items on the punch list were finished by January 1 of ‘74.”
The bowing of the wall was brought to his attention in the fall of 1980 by the maintenance foreman. When he looked at the wall he could see that its whole length had been caulked previously.
He was familiar with a loss report filed with Affiliated FM Insurance Company in November 1980. The report stated that four years earlier employees had complained about cold air, and caulking had been provided “at the wall at floor level.” The year before he gave the deposition employees again complained and the wall again was caulked.
- The loss report filed for plaintiff with Affiliated FM Insurance Company, which showed a “date of loss” of 1 November 1980 and a “date inspected” of 24 November 1980, and which stated that “[a]pproximately four years ago, [plaintiff‘s] employees [had] complained about cold air at the east side of the building,” and that “[c]aulking was provided at the wall at floor level.”
- An affidavit from Kern‘s president, who executed the contract on Kern‘s behalf, averring that Kern‘s corporate seal was placed on the contract for the purpose of indicating that its execution was duly authorized by the corporation and to confirm that he, as an individual, was not a party to it; that at no time was there any discussion or other communication between the parties or their agents regarding whether the contract would be a “sealed” instrument within the meaning of
G.S. 1-47(2) , or for any other purpose; and that neither he nor Kern ever intended that the contract would be a “sealed” instrument within the meaning ofG.S. 1-47(2) , or for any other purpose. - An affidavit from an employee of plaintiff averring that the defects alleged in plaintiff‘s complaint were not discovered until November 1980. Attached to the affidavit was the original contract between plaintiff and Kern which showed execution by Kern‘s president and affixation of Kern‘s corporate seal.
The court considered “the pleadings, admissions, answers to interrogatories, stipulations of counsel, affidavits, depositions, and other matters of record“; found that there was no genuine issue of material fact and that Kern was entitled to judgment as a matter of law; and entered summary judgment for Kern. In a separate order it treated Associates’ motion as one for summary judgment; found that there was no genuine issue as to any material fact and that Associates was entitled to judgment as a matter of law; and entered summary judgment for Associates.
Plaintiff appeals.
IV.
CONTRACTOR
[1] Plaintiff‘s sole argument for reversal of the summary judgment in favor of Kern is that the jury could have found the contract between plaintiff, as owner, and Kern, as contractor, to be under seal, and thus subject to
Because our review is limited to questions presented in the briefs, N.C.R. App. P. 28(a), plaintiff in effect concedes that unless this argument has merit, the trial court ruled correctly. A recent
The mere affixation of a corporate seal to a document does not automatically raise it to the status of an instrument under seal.
Because the routine use of a corporate seal is merely to demonstrate authority to execute a document, the mere presence of a corporate seal, without more, does not convert the document into a specialty. A document is not considered a specialty unless there is evidence of intent to create an instrument under seal in the document itself such as a recital that the instrument would be under seal, or the words “corporate seal” or “affix corporate seal.”
Blue Cross, supra, 61 N.C. App. at 362, 301 S.E. 2d at 465-66.
The contract here contains no recitals or other evidence of an intent to create an instrument under seal. The only forecast of evidence on this question, the affidavit of Kern‘s president, expressly denied the existence of such intent. The president averred that Kern‘s corporate seal was placed on the contract for the purpose of indicating that its execution was duly authorized by the corporation and to confirm that he, as an individual, was not a party to it. He further averred that at no time was there any discussion or other communication between the parties or their agents regarding whether the contract would be a “sealed” instrument within the meaning of
In the absence of recitals or other evidence in the contract itself of intent to create an instrument under seal, and confronted with clear, uncontroverted evidence that no such intent existed, the trial court did not err in refusing to deny Kern‘s motion for summary judgment on the ground that the contract was a sealed instrument subject to the ten year statute of limitations. Insofar as the sealed instrument question was determinative, summary
V.
ARCHITECT
[2] A. Associates’ motion to dismiss, which was treated as a motion for summary judgment, was made “on the grounds that the plaintiff‘s action is barred by the applicable statute of limitations including
- No action to recover damages based upon or arising out of the defective or unsafe condition of an improvement to real property shall be brought more than six years from the later of the specific last act or omission of the defendant giving rise to the cause of action or substantial completion of the improvement.
- For purposes of this subdivision, an action based upon or arising out of the defective or unsafe condition of an improvement to real property includes:
. . . .- Actions against any person . . . who performs or furnishes the design, plans, specifications, surveying, supervision, testing or observation of construction
- The limitation prescribed by this subdivision shall apply to the exclusion of
G.S. 1-15(c) ,G.S. 1-52(16) andG.S. 1-47(2) .
The uncontroverted forecast of evidence established that Associates completed its work for plaintiff, and that plaintiff‘s building was completed, prior to 1 January 1974. Plaintiff filed its complaint on 16 March 1982, “more than six years from the later
B. We note that
The result would be the same, however, under the original version of the statute, which was enacted in 1963 and was in effect when plaintiff contracted with Associates and Associates performed its work for plaintiff. See Act of June 19, 1963, ch. 1030, § 1, 1963 N.C. Sess. Laws 1300, 1300-01; Lamb, supra, 308 N.C. at 426, 302 S.E. 2d at 872. Regardless of which version of
C. Associates has contended that
D. Plaintiff contended in the trial court, and contends on appeal, that if
VI.
For the foregoing reasons, the summary judgments in favor of Kern, the contractor, and Associates, the architect, are
Affirmed.
Chief Judge VAUGHN concurs.
Judge PHILLIPS dissents.
SQUARE D COMPANY v. C. J. KERN CONTRACTORS, INC., and SIX ASSOCIATES, INC.
No. 8328SC468
Court of Appeals of North Carolina
(Filed 21 August 1984)
70 N.C. App. 30
Judge PHILLIPS dissenting.
A written contract that has the defendant‘s seal on it is some proof, it seems to me, that the contract is under seal. Plaintiff having produced such a contract, a factual issue was raised, I think, and its case should not have been dismissed on defendant‘s word that the seal did not mean what it appeared to. If a seal or any other part of a written contract has no prima facie standing until buttressed by a sworn affirmation that it truly represents or
As to the statute of limitations or statute of repose issue, though the majority opinion is in accord with an unanimous decision of our Supreme Court, I nevertheless respectfully, but firmly, dissent. In my opinion, the General Assembly had no rational basis for immunizing architects and builders against all legal liability just six years after improvements are made to real estate. If
