delivered the opinion of the court:
Plaintiff Springfield Heating and Air Conditioning, Inc. (Springfield), appeals the trial court’s dismissal of its second amended complaint pursuant to section 2 — 615 (735 ILCS 5/2 — 615 (West 2004)) and section 2 — 619 (735 ILCS 5/2 — 619 (West 2004)) of the Code of Civil Procedure. Springfield contends on appeal that the trial court erred in dismissing its foreclosure of a mechanic’s lien count on the basis of constructive fraud because no evidence demonstrating Springfield’s intent to defraud was established by defendants Oak-wood, LLC, and Southeast Contractors, LLC. 1 Springfield also claims that the trial court erred in dismissing its counts for unjust enrichment and quantum meruit as alternative theories of liability against Oakwood because Oakwood retained the benefits of Springfield’s plumbing services without compensating Springfield for those services. For the reasons stated below, we affirm in part and reverse in part.
The following facts are relevant to the instant appeal. Springfield’s business consists of providing materials, services, labor and equipment relating to construction services, including air conditioning, plumbing and heating services. Southeast provides general contracting services. Oakwood owns the properties commonly known as 3947-55 King Drive and 401-415 E. Oakwood (collectively referred to herein as “property”).
On March 31, 2005, Southeast as the general contractor entered into a “Standard Form of Agreement Between Contractor and Subcontractor” with Springfield as the subcontractor. Southeast was the general contractor for improvements Springfield made at the property, which totaled $465,000.
On September 19, 2005, Southeast terminated its relationship with Springfield. At that time, the unpaid balance relating to the improvements Springfield made to the property totaled $289,302. On December 1, 2005, Springfield filed a contractor’s claim for lien for each parcel of property in the trial court alleging that on March 31, 2005, Springfield entered into a contract with Oakwood to provide plumbing services at the property. Springfield claimed that it began providing the plumbing services on April 15, 2005, and by September 19, 2005, Springfield completed 85% of the contracted for services, which totaled $198,000. Springfield further alleged that Oakwood requested additional services and materials, which it provided at a value of $121,302. Springfield alleged that the total amount outstanding after credits was $289,302. Springfield filed a contractor’s claim for lien to recover the full unpaid balance of $289,302 with interest at 5% per annum from September 19, 2005, on each of the two properties.
On December 5, 2005, Springfield filed a complaint to foreclose the two mechanic’s liens. In response, Oakwood and Southeast filed a section 2 — 615 motion to dismiss because Springfield failed to allege that it served Oakwood with notice of its mechanic’s liens within 90 days following the completion of work at the property. The trial court granted the dismissal without prejudice. On September 15, 2006, Springfield filed an amended complaint, which included an unjust enrichment count and a quantum meruit count against Oakwood in addition to the count to foreclose the two mechanic’s liens. The trial court again dismissed the complaint on the grounds that Springfield failed to allege that it served Oakwood with notice of its mechanic’s liens within 90 days.
On April 19, 2007, Springfield filed a second amended complaint to foreclose on the two mechanic’s liens and for other relief, including the unjust enrichment and quantum meruit counts against Oakwood. This time, Springfield alleged that it notified Oakwood of Springfield’s mechanic’s liens. Oakwood and Southeast filed a combined section 2 — 615 and 2 — 619 motion to dismiss Springfield’s complaint. Oak-wood and Southeast sought dismissal under section 2 — 619(e)(9) on the grounds that Springfield sought enforcement of two separate and identical mechanic’s liens each for $289,302 creating an appearance of an encumbrance twice as much as the amount owed. Oakwood and Southeast also sought dismissal under section 2 — 615 for Springfield’s unjust enrichment and quantum meruit counts on the basis that the sole remedy of a subcontractor against an owner of real estate is under the Mechanics Lien Act (Act) (770 ILCS 60/0.01 (West 2006)). On September 20, 2007, the trial court dismissed with prejudice Springfield’s mechanic’s lien claims based on a constructive fraud theory. The trial court also dismissed the unjust enrichment and quantum meruit counts brought against Oakwood since Springfield failed to comply with the Act, which then precluded recovery under equitable doctrines. Springfield timely appealed the trial court’s dismissals pursuant to sections 2 — 615 and 2 — 619.
A motion to dismiss under section 2 — 615 “challenges the legal sufficiency of a complaint based on defects apparent on its face.” Heastie v. Roberts,
A motion to dismiss under section 2 — 619 “admits the legal sufficiency of the plaintiffs claim but asserts ‘affirmative matter’ outside of the pleading that defeats the claim.” Czarobski v. Lata,
Springfield first contends on appeal that the trial court erred in dismissing its foreclosure of a mechanic’s lien count from the complaint because the mechanic’s liens were enforceable and no evidence of an intent to defraud existed. Springfield claims that the trial court erred in finding that the mechanic’s liens amounted to “constructive fraud.” Springfield maintains that the liens contain an inadvertent error and not an intentional error intended to deceive anyone or to obtain an amount in excess of what was due and owing to it. Springfield claims that section 7 of the Act protects an honest lien claimant who makes a mistake rather than a dishonest claimant who knowingly makes a false statement. Peter J. Hartmann Co. v. Capitol Bank & Trust Co.,
Oakwood and Southeast respond that Springfield created the appearance of constructive fraud by filing two separate liens totaling $578,604.52, which was an amount substantially greater than the balance of $289,302.26 owed to Springfield. Rather than allocating the total balance outstanding between the two parcels of property or filing a blanket lien, Oakwood and Southeast note that Springfield filed a lien on each property for the balance outstanding creating the appearance that the total amount encumbered on the two parcels was $578,604.52. Oakwood and Southeast claim that overages in liens may be considered constructive fraud where the amount in error was too significant to be considered a mere mistake. Marsh v. Mick,
We agree with Springfield’s contentions because an intent to defraud was not established here. As an initial matter, we turn our attention to Oakwood and Southeast’s forfeiture claim that Springfield did not raise the lack of evidence regarding its intent to defraud at the trial court. Forfeiture of an issue is a limitation on the parties and not on this court. Smith v. Menold Construction, Inc.,
The parties agree, as does this court, regarding the factual basis of the instant case. Instead of prorating and allocating a portion of the total amount due to each of the two parcels of property, Springfield filed a separate lien on both parcels of property for the total amount outstanding resulting in the appearance that each parcel was encumbered for more than the amount outstanding. The trial court found the overstatement akin to constructive fraud, relying primarily upon this court’s decision in Lohmann Golf Designs, Inc. v. Keisler,
Subsequent to the trial court’s decision in the instant case, this court decided Cordeek Sales, Inc. v. Construction Systems, Inc.,
Also, in Cordeek, this court relied upon its earlier decision in Peter J. Hartmann Co. v. Capitol Bank & Trust Co.,
Moreover, turning specifically to the statutory language of section 7 of the Act, we note that section states, in pertinent part: “[n]o such lien shall be defeated to the proper amount thereof because of an error or overcharging on the part of any person claiming a lien therefor under this Act, unless it shall be shown that such error or overcharge is made with intent to defraud.” (Emphasis added.) 770 ILCS 60/7 (West 2006). An “[ijntent to defraud may be inferred from documents containing overstated lien amounts combined with additional evidence.” Cordeck,
In light of section 7 of the Act’s express language, as well as this court’s recent holdings in Cordeck and Hartmann, we conclude that an express showing of an intent to defraud must be established by evidence in addition to and apart from an overstatement included in a lien. As such, the trial court erred in dismissing Springfield’s count to foreclose the mechanic’s liens and we remand the cause for further proceedings. We express no opinion on the merits of the case and instead limit our conclusion within the scope of deciding the issue under a motion to dismiss analysis.
Next, Springfield claims that the trial court erred in dismissing its unjust enrichment and quantum meruit claims as alternative theories of liability. Springfield contends that the trial court erred in finding that a mechanic’s lien was Springfield’s exclusive remedy against Oakwood. Springfield maintains that the complaint sufficiently pled allegations supporting unjust enrichment and quantum meruit claims. Springfield claims that count III established that Oakwood would benefit from materials, services, and labor provided by Springfield and would be unjustly enriched if Springfield was not compensated for labor, services and materials furnished at the property. In count iy Springfield claims that Oakwood accepted and enjoyed the benefits of Springfield’s labor and materials and that it would be unjust for Oakwood to retain the benefits for the work performed and material furnished at the property without compensating Springfield for such services and materials. Thus, Springfield claims that the second amended complaint adequately pled the elements of unjust enrichment and quantum meruit.
Oakwood and Southeast respond that a subcontractor’s sole remedy against the owner of real estate is under the Act. Oakwood and Southeast claim that since Springfield was Southeast’s subcontractor, Springfield has an adequate remedy at law because it possessed the right to sue Southeast for the breach of contract. Oakwood and Southeast claim that Springfield sought enforcement of its mechanic’s hen as a subcontractor, and Oakwood was not a party to the transaction between Springfield and Southeast to provide plumbing work at the property. Thus, Oakwood and Southeast maintain that Springfield’s equitable claims required dismissal.
We agree with Oakwood and Southeast that the trial court did not err in dismissing Springfield’s unjust enrichment and quantum meruit claims. As a general rule, relief under an unjust enrichment theory is inapplicable “where the entire work is contracted for and placed under a general contractor who has the power to employ whom he chooses, because in such circumstances the owner has the right to presume that work is being done for and on behalf of the contractor.” Premier Electrical Construction Co. v. La Salle National Bank,
Accordingly, the judgment of the trial court is affirmed in part and reversed in part.
Affirmed in part and reversed in part; cause remanded.
O’BRIEN, P.J., and NEVILLE, J., concur.
Notes
Oakwood, LLC, and Southeast Contractors, LLC, are appellees to this appeal and filed a combined brief.
