The defendants C. A. and Frank C. Mueller, contracted with plaintiff to build for him a house. The contract provided that the house should be built according to certain drawings and specifications, and the work to be done “to the satisfaction of Alfred M. Baker, architect.” Paragraph twelve (12) of the contract reads: “Should the contractors at any time refuse or neglect to supply a sufficiency of properly skilled workmen, or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements on their part herein contained, such refusal or failure being certified by the architect, the owner shall be at liberty, after three days written notice to the contractors to provide any
The special defenses were, First: That the house was completed in 1893 to the satisfaction of Baker, the architect; that he so certified, and that in May, 1893, the plaintiff made final payment in accordance with the certificate of the architect. Second: That plaintiff took possession of the house in the spring of 1893, and that prior to the institution of this suit, to wit, in 1897, the Muellers had no notice or knowledge that any claim was
Upon a trial of the cause before the court a judgment was rendered in favor of the plaintiff for $357.50. The defendants' have appealed and complain of the action of the court in refusing instructions asked by them; that the damages assessed by the court are excessive, and that the evidence was not sufficient to justify the court in awarding substantial damages.
Before we proceed to the discussion of the chief assignments of error we will suggest that there was substantial evidence that the varnish called for in the contract was not used by the contractors; that a cheaper or inferior varnish was substituted; that in 1896 the plaintiff was compelled to have the inside woodwork and the outside doors of the house revarnished ; therefore the circuit court properly refused to direct a verdict for the appellants.
The appellants complain of the refusal of the court to give the following instruction: “The court declares the law to be, that under the provisions of paragraph 14 of the contract between the plaintiff and the defendants, C. A. and Prank Mueller, the final certificate and final payment of A. M. Baker, the architect employed by plaintiff, are conclusive evidence of the performance of the said contract against any claim of the owner. Therefore, if the court finds from the evidence that A. M. Baker, the architect of the plaintiff, did give to the defendants, C. A. and Prank Mueller, the final certificate in evidence, and if, upon the presentation of said final certificate, the plaintiff paid to the defendants, C. A. and Prank Mueller, the final payment due on account of the said contract, then plaintiff can not recover, unless the evidence further shows fraud or collusion between the architect and the said defendants, Charles
So in the case of Glacius v. Black,
In the case at bar the evidence tended to prove that the architect was absent while the varnishing was being done, and the evidence tended to prove further that the use of the cheaper or inferior varnish could not be detected when it was put on, but would only be developed by time. This being the proof we are of the opinion that the court did right in refusing the instruction • in the form in which it was asked.
The defendants make the further contention that under paragraph 12 of the contract above quoted,.they are not liable if the plaintiff failed to give the Muellers notice of the alleged breach of the contract, thus affording them an opportunity to remedy the defect in the work. They asked an instruction to that effect, which the court refused. That clause of the contract and the notice therein provided clearly refer to the time when the work is in progress, and not after its completion. As to defects, in the work which are subsequently discovered, the plaintiff was under no obligation to inform the Muellers. When the entire paragraph is read and considered no other construction of it is possible.
“Unquestionably the measure of plaintiff’s damages is the sum which he necessarily expended to make the varnishing of the wood work of his house to conform to the contract, whether such sum be more or less than the sum for which the defendants contracted to do the work. Wright v. Sanderson,
I can not give my consent to the foregoing discussion. I think that the true measure of plaintiff’s damages is the difference in value between the work as done and as it ought to have been done. It must be kept in mind that we are dealing with a building contract, and the law as applicable only to such contracts must be considered. I do not for a moment question the correctness of the rule stated in Haysler v. Owen,
In my opinion the judgment is wrong and ought to be reversed, but under the views expressed by Judges Bland and Bond, it must be affirmed. It is so ordered.
