48 So. 966 | Miss. | 1909
delivered the opinion of the court.
The ease of Peck-Hammond Company v. Williams, 77 Miss. 324, 27 South. 995, controls this case perfectly. The court erred, therefore, in holding the contrary view. The judgment should have awarded the appellants the whole of the value of the amount furnished by them; and the other parties, as correctly held by the court, so far as priority is concerned, would be entitled to the balance in the order in which they served notice upon the owner, as shown by the pleadings and the agreed statement of facts.
Reversed and remanded.
The counsel for appellees filed a suggestion of error, to which the court responded as follows:
delivered tbe opinion of tbe court in response to the suggestion of error.
The case made by the record is briefly this: A. P. Cameron contracted with J. H. Jaffray, who was doing business under the firm name of J. Ii. Jaffray Construction Company, to build him a residence in the city of Canton, Miss. Jaffray proceeded to carry out his contract. When he completed the foundations, he executed the following assignment to appellants, A. & S. Spengler, of Vicksburg, Miss.: “In consideration of the sum of $1,000 heretofore advanced us by A. & S. Spengler, of Vicksburg, Miss., and further consideration that the said A. & S. Spengler have agreed to advance us certain materials in their line' for the construction of the house, or residence, we are building for A. P. Cameron, at Canton, Miss., and the further consideration that they have agreed to extend us a cash credit, not exceeding at any one time, of fifteen hundred dollars, for labor, we, the undersigned, J. H. Jaffray, composing the firm of' J. H. Jaffray Construction Company, do hereby transfer and assign, to secure said sum of $1,000, the amount of said material, and said cash advances, unto the said A. & S. Spengler the balance due us under said contract with the said A. P'. Cameron for the construction of said building as aforesaid, and direct the said Cameron to pay over the said balance to the said A. & 8. Spengler as the payments become due; the duplicate of said contract being herewith attached. Any balance, after paying what may be due the said A. & S. Spengler, shall be paid over tó us. Witness our signature on this the 13th day of December, 1906. [Signed] J. H. Jaffray Construction Company.” . Notice of the assignment was given by appellants to Cameron, the owner, on the day of the assignment. Appellants continued to advance Jaffray material and cash money under said assignment'for use in the construction of said building, and Cameron made payments under his contract from time to time' to appellants. When the residence was completed, appellants
Appellees, who are various subcontractors or material men, not knowing of the assignment to appellants by Jaffray, furnished material and labor to Jaffray in the construction of said buildings, and, not receiving payment therefor, served “stop” notices on Cameron under Code 1906, § 3074, but long after the assignment. It is agreed, for the purpose of this appeal, that the notices are all in proper form, and served in conformity with the provisions of said section. It is also agreed that Jaffray remained throughout in the possession of the work as contractor, and that all the “stop” notices were served upon Cameron, the owner, by appellees subsequently to the execution of said assignment by Jaffray to appellants, and subsequently to the service upon Cameron by appellants of notice of said assignment. When said building was completed, Cameron owed a balance of $5,210.62 under his said.contract with Jaffray. Appellants claimed $3,600 or $3,700 of this amount under their assignment, and appellees’ claims on said fund aggregate $3,600, so that Jaffray’s total indebtedness to appellants and appellees reached a sum total of about $7,200 or $7,300, not enough to pay all in full. Hence this lawsuit, in which appellants contend that they should first be paid in full.
The Stiles-Tull Lumber Company and others filed their suits in the circuit coiirt of Madison county for the purpose of enforcing their rights under Code 1906, § 3074. A. P. Cameron answered, and paid over into court what he claimed to be due under his contract, $5,210.62, and asked that all parties in interest be brought in as parties to the said proceedings. The cases were thereupon all consolidated, and an issue made up between appellants and appellees. A jury was waived, and thecade heard by the court. It was further agreed that there was more due appellants by Jaffray under said assignment than the difference of w-hat wras due the other appellees and the amount.
When the appellants sought to introduce said assignment in evidence, appellee's objected to its introduction on the following grounds: (a) Because “said assignment is no more nor less than .a mortgage, which has neyer been acknowledged or filed for record in Madison county, or anywhere else, as required by la-w.” (b) Because “no notice was given to the other parties (appellees) of appellants’ assignment.” (c) Because “it is irrelevant incompetent, and immaterial, so far as it may affect any rights or interests of appellees to the funds in controversy.” (d) Because “no claim can be made thereunder, by virtue of the lien they claim, under the mechanic’s lien law of the state.” (e) Because “it is not signed and acknowledged, and has not been filed for record.” (f) Because “none of the appellees had any knowledge of it.” (g) Because “it is purely and simply a mortgage, and, in order to have been valid should have been recorded, or other actual notice given the other creditors.” (h) Because “the action of appellants in allowing Jaffray to stay in possession of the job and contract bills, after all improvements were made, prevents them from contesting the claims of appellees.”
Upon the foregoing exceptions the court made the following ruling: “The court holds, on the motion to exclude the assignment, that the assignee is entitled to whatever was due on the building to the builder at the time the assignment was made; that after that time the assignee stood in the shoes of the builder, and was only entitled under the assignment to such additional amount as might have been earned by the builder under his contract. The court, however, is of the opinion, further, that the assignment shown to have been served on the owner was sufficient notice of an indebtedness of $1,000, and as to whatever sum the evidence may show was earned by the builder at the time of the execution of the assignment Spengler would be en
Appellants then and there excepted to the ruling of the'court.. Appellants next admitted that there were no profits in said contract at the time of said assignment, or at the completion of the job. Appellees thereupon moved the court for a judgment for the amount of their claims, to be paid in their priority, with six per cent, interest, to the exclusion of the claim of appellants, and admitted, for the purpose of the motion, that the balance-was not sufficient to pay appellants’ claim under said assignment in full. The court, sustained the motion and gave judgment accordingly.
The purpose of both parties in making the agreed statement of facts, which was made in an irregular, sort of way, from time to time, in the course of the trial below, was manifestly that, after such agreed statement of facts had been made further testimony would be adduced by appellants and appellees. But the court’s ruling on the effect of the assignment to the appellants had the practical effect of destroying entirely the contention off ■appellants as to their prior right to the funds in court, and made, of course, the introduction of further testimony unnecessary, especially, when it was admitted that there was more due appellants by Jaffray under said assignment than the difference between what was due the other appellees and the amount paid by Cameron into court. Beally the ruling of the court left nothing to be determined in the case except to settle the correctness-of the ruling in construction of the assignment, and accordingly the appellant’s appeal to this court was taken, the object of the appeal being plainly to have this assignment construed, since,.
If will be noticed, from the objections made by appellants to the introduction of said assignment, that almost their solé ground of objection was that this instrument was not an assignment, but a mortgage; and, indeed, the chief contention made by learned counsel for appellees in this court, in the oral argument and in their briefs, is that the instrument must be held to be a mortgage, and that consequently, since it was not recorded as mortgages must be to affect the rights of third parties, the appellees here must prevail over this so-called unrecorded mortgage, of which the appellees never had any actual or any constructive notice. This is a totally erroneous view of this instrument. It is plainly nothing else than an ordinary simple assignment. Learned counsel for appellees segregate from the assignment one particular clause in it, to wit, “The balance due us under said contract with the said A. P. Cameron for the construction of said building as aforsaid,” without looking to the -other provisions of the assignment. Of course, this is not the proper way in which to construe the assignment. All its provisions must be taken in one view, and the purpose of the assignment worked out from the whole instrument, and not a part of it. Counsel for the appellants well say: “The fact that appellants were to continue furnishing material and money for labor; the fact that Mr. Cameron was directed to pay over to appellants the balance ‘as the payments became due;’ the fact that the balance, after paying what might be due appellants, should be paid over to Mr. Jaffray; the fact that no particular payments were-assigned, and others reserved, and many other features about the assignment might be cited to show that the intention of the parties was not to transfer only what was then due, but what was to become due.”
Again, it is a well-settled canon of construction that the contemporaneous construction placed upon an instrument by the parties thereto is entitled to very great weight in reaching the
So far as any equities are concerned as to the real merit of these claims, one is just as meritorious, in all respects, as the other, and all that is so earnestly insisted on by - the learned
First of all, let it be noted that, in determining any question
There then follows in this text a very careful consideration of the laws of the different states and the changes made, it being pointed out that in California the Pennsylvania system was first adopted in 1858, but that in 1862 that system was repealed and the New York system adopted, and that this New York system was in turn repealed in 1868,.'and the Pennsylvania system restored, and that finally the present California statute (Code Civ. Proc. § 1188 et seq.) restored again the salient features of the New York system. It will thus be seen that this court must determine this case, not by the statutes of other states, but by the statutes of its own state. Now, what is that statute ? It is contained in Code 1906, § 3014, so far as this'ease is concerned, which is as follows: “When any contractor or master workman shall not pay any person who may have furnished materials used in the erection, construction, alteration, or repairing of any house, building, structure, fixture, boat, watercraft, • railroad, railroad embankment, or the amount due by him to any subcontractor therein, or the wages of any journeyman or laborer employed by him therein, such person, subcontractor, journeyman or laborer may give notice, in writing, to the owner thereof of the amount due; and thereupon the amount that may be due by such owner to the contractor or master workman shall be bound and liable in the hands of such owner for the payment of
The mere reading of this statute shows that the New York system, and not the Pennsylvania system, is the one which this state has adopted, and which is now in force in this state. See 27 Cyc. p. 101, upon the New York system. The courts of New York have made their .system perfectly clear. Under that system it is only the original contractor who has any absolute lien. The subcontractor and the material men have no lien, except from the date on which they give written notices of their claims to the owner, from which date the owner is required to retain
The same doctrine precisely is laid down in the case of Bates v. Salt Springs National Bank of Syracuse, 157 N. Y. 322, 51 N. E. 1033, in which case the facts are in all respects practically the same as in this case, with the additional fact that there was a clause in the contract by, which the contractor was required to obtain a certificate from the county clex’L that no liens were unsatisfied of record, etc. The supreme court held that this clause was a protection to the subcontractors, and
Identically the same doctrine is announced with great clearness in the case of Binns v. Slingerland, 55 N. J. Eq. 55, 36 Atl. 277. In that case the contractor gave orders or assignments to the various creditors, and the owner did not accept them. Slingerland, a subcontractor, afterwards served “stop” notices upon the owners, and the court said. “It was not seriously contended but that the drawing of the orders worked an equitable assignment of so much of the last payment as they covered,/ and that they thereby gained, in equity, a priority over the notice served by the defendant herein. Superintendent, etc., v. Heath, 15 N. J. Eq. 22; Lanigan’s Adm’r v. Bradley, 50 N. J. Eq. 201, 24 Atl. 505. And it is equally dear that the rights of such equitable assignees could have been enforced in this court. And if the complainants herein had, as soon as the building was completed and the payment of $1,400 became due 'from them, deposited the same in this court, and filed a bill of interpleader against the several parties, the holders of those orders would have prevailed over the defendant, Slingerland, claiming under his stop notice of September 12th. They were first in time, and therefore prior in right. . ■. . The practice of contractors making such preferences by giving orders to materialmen has become so thoroughly familiar to everybody, and has been so frequently before the courts, and their right so to do so thoroughly established, that I must conclude that if the legislature had intended to restrict this right on the part of contractors, they would have done so by qxpress language.” So in
Indeed, this view is announced by 27 Cyc. p. 231, as the generally accepted doctrine. At page 231 of 27 Cyc. it is said: '■'It has been held that if, before the notice or claim of lien is served on the owmer or filed, the contractor assigns his claim •against the owner, the assignee has the prior right to the fund, and an order given by the contractor on the owner, payable out of what is due or to become due under the contract, operates as an assignment pro ianto of the fund, even without any acceptance of the order by the owner.” Authorities are cited in support of this view from California, Iow7a, New Jersey, New York, Ohio, and Wisconsin, an overwhelming array of authorities. We will not burden this opinion by citing .them in detail, as they are set out in 27 Cyc. p. 231, note 98. We have verified these citations, and they fully support the text. On page 232, at the end of this citation of authorities, the editors of Cyc. cite as contra, Carter v. Brady, 51 Fla. 404, 41 South. 539; Beardsley v. Brown, 71 Ill. App. 199; Simpson v. New Orleans, 109 La. 897, 33 South. 912, and Bourget v. Donaldson, 83 Mich. 478, 47 N. W. 326; and we remark, in passing, that these authorities cited as contra on this page 232 of Cyc. are the very cases cited by learned counsel for appellees, and on which they rely chiefly for support of their view.
Let us look carefully at these authoifities a moment. In the case in 83 Mich. 478, 47 N. W. 326, it very clearly appears that the materialmen under that law had a lien equal to the contract- or’s lien, and it is expressly set out on page 482, 83 Mich., and page 328, 47 N. W., that the statute provided that the material-man or subcontractor had to file his written lien for record in the office of the register of deeds. That case of course, has no application here, where the materialman has no lien, and where the claim for the lien is not required to be recorded. In the
Surely it ought to be accepted after this citation of authorities, and this analysis of those cited as holding contra, which do not hold contra, but only hold that, where a lien is given the materialman by the statute, such materialman would prevail over an assignee, that under our statute, which does not give any such lien, the assignee must of necessity prevail over the materialman, who has acquired no lien until after the assignment has been executed and delivered. Out of great deference to the very learned counsel for appellees, and their extreme earnestness in urging their view, an examination will be -made now, wholly unnecessary, however, of other authorities cited by them. One of these cases is Newport Wharf & Lumber Co. v. Drew, 125 Cal. 585, 58 Pac. 187. What was held there? Just this: “If the contractor is still entitled to demand payment of installments already matured at the time of the notice (that is, notice by the materialman), payment to him is intercepted by the notice; but, if he has already assigned them to a third party,' the notice will be inoperative to prevent their payment to such party.” - This is a direct authority for the appellants. Another case cited by appellees is Board of Education v. Duparquet, 50 N. J. Eq. 234, 24 Atl. 922. What does that case hold ? “An assignment, in language operating in pressenti, of money due and to grow due from a third person, effects, an immediate and present transfer to the assignee of a right to demand and receive the money assigned without notice to the debtor; and after such assignment the debtor no longer owes the assignor, but does owe and will owe to the assignee what he would otherwise owe to the assignor.” Another direct authority for appellants, and, let it be noted, holding that these appellees were not entitled to any notice of this assignment, a thoroughly well settled proposition. Learned counsel for appellees say that in
In several cases cited by learned counsel for appellees, to wit, to group them and dismiss them, Wimberly v. Mayberry, 94 Ala. 240, 10 South. 157, 14 L. R. A. 305; Glass v. Freeborg, 50 Minn. 386, 52 N. W. 900, 16 L. R. A. 335, and Farmers’ Loan & Trust Company v. Canada R. R. Co., 127 Ind. 250, 26 N. E. 784, 11 L. R. A. (O. S.) 740, the common principle is announced—all these cases being mortgage cases, and not cases of an assignment at all—that where no railroad is in existence, •or where no house is in existence, and a mortgage is given on the railroad or on the land, and the labor, materials, and money of the materialmen and subcontractors gave all there was of value to the property claimed under the mortgage, the mortgagee ought to show a clear and strong superior right in order to defeat the claims of those who in reality brought the claims into existence; the principle being that the mortgage on the railroad in one case, and the mortgage on the land in the other, could not prevail over mechanics and materialmen whose money created in one case the railroad, and in the other the house on the land. In the case of Bohn Mfg. Co. v. Kountze, 12 L. R. A. 33 (30 Neb. 719, 46 N. W. 1123), the holding was, as set out at page 36, bottom of second column: “Where a vendee, owing the equitable title, contracts for the erection of a building, upon the express authority of the owner of the legal title, it is but just that the lien of the mechanic should attach to the interest of both vendor and vendee in the premises and be paramount to (he lien of the vendor.” That is obviously correct, because of ihe agreelment of the owner of the legal title, the vendor. But, besides, the case is from the state of Nebraska, in which as shown in this very opinion, section 1 of the mechanic’s lien law pro
Apjly to the situation our Code 1906, § 3074, and the general principle of law as to the right to make a common-law assignment, and what do we have ? Why, manifestly the assignees here, and appellees, were, prior to the assignment, mere creditors at large, without any lien under this statute given to either.. That being the situation, and our statute giving the materiahnan a lien only»from the service of the stop notices, as expressly held in Herrin v. Warren & Mobley, 61 Miss. 509, what was therein the law to prevent the contractor from assigning the balance due and to become due to him to the appellants? Why, most manifestly, he had the common-law right to make the assignment, and, if that assignment was duly executed and delivered to the appellants prior' to the time when these appellees secured' any lien by the service of the stop notices, it is too clear for ¿rgument that the assignees must prevail over these appellees, because of the universal equitable doctrine that he who is first in time is first in right. That is this whole case, stripped of all the confusion which has been thrown around it, growing out of the misconception that in some way, or somehow, or somehow else, these materialmen should be preferred to these assignees— exactly why, no one can tell. They had no lien until they served the stop notices. Long prior to that the appellants had the assignment. Both were general creditors, and he who, in the race of diligence to secure himself, first got a claim by their assignment, being first in. time, is first in right. That absolutely is this whole case, stripped of all the clouds and darkness, which have been thrown about it.
We will, however, because we desire as far as possible to satisfy the learned counsel for appellees of their erroneous view, notice a few other of their contentions. It is complained that the assignees gave these appellees no notice of their assignment. None was necessary. The doctrine is stated thus in Hall v.
There are a great many inaccuracies, inadvertent, of course, in the statement of facts by learned counsel for appellees. Eor example, to run hastily over them, the amount for extras was not $2,300, but $1,463.85; the $9,000 paid by Cameron before any notices were served was paid directly to the Spenglers, not by Jaffray, and by him to the Spenglers. Cameron was notified of this assignment the very day it was made. There is no dear evidence in this record that appellees furnished material with the knowledge and consent of appellants. This is sought to be worked at in a very vague way, from certain checks; but, if it had been clearly proven, it would make no sort of difference as'to the rights of appellants. It was the business of the appellees to give notice themselves to Cameron, and not negligently and supinely furnish these materials without the exercise of any sort of diligence on their part. They have only themselves to blame for what they may lose. There is nothing
Another proposition of learned counsel for appellees is that Cameron did not assent to this assignment. We think the fact is shown otherwise by the record; it is agreed that Cameron had paid appellants, since the assignment and under the assignment, $14,000. This $14,000 was for money and materials; but what if Cameron had not assented to the assignment by Jaffray to the appellants? Such assent of the debtor, Cameron, was not necessary to give effect to the assignment executed and delivered by Jaffray to the appellants. Knapp v. Eldridge, 33 Kan. 106, 5 Pac. 372; Newbry v. Hill, 59 Ky. 530; Roger Williams Ins. Co. v. Carrington, 43 Mich. 525, 5 N. W. 303; Garland v. Harrington, 51 N. H. 409; Mourton v. Robertson, 3 La. 439.
We have thus most patiently, carefully, and in detail gone over this case, both as to the facts and law applicable thereto. Out of the very great deference we feel for all the very learned counsel for appellees, it certainly ought to be dear to them, after this review, that they have fallen into what is, perhaps, a popular misconception of the effect of section 3074 of our Code, under our decisions. This section might have provided, if the legislature had preferred the Pennsylvania system, that no assignment should be made by the contractor which would
It follows that the judgment of the court below was erroneous, and the suggestion of error is overruled.