Speedy Gonzalez Landscaping, Inc. v. O.C.A. Construction, Inc.Speedy Gonzalez Landscaping, Inc. v. O.C.A. Construction, Inc.
delivered the opinion of the court:
Plaintiff, Speedy Gonzalez Landscaping, Inc., appeals the order of the circuit court dismissing count I of its complaint against defendants, O.C.A. Construction, Inc. (O.C.A.), North American Specialty Insurance Co., and the Public Building Commission of Chicago (PBC). Count I sought the grant of a lien and an accounting of funds due pursuant to plaintiffs work as a subcontractor regarding the improvement of real property for the New Westinghouse High School. The primary issue on appeal is whether the plaintiffs lien claim on public funds terminated because the plaintiff failed to timely deliver to the PBC a copy of its complaint in accordance with section 23(b) of the Mechanics Lien Act (
The PBC is a municipal corporation that contracted with O.C.A. to perform site preparation work on “the New Westinghouse High School (Phase 1)” project. O.C.A., which served as general contractor on the project, then entered into a subcontract agreement with plaintiff to provide certain labor and services such as the hauling, disposal, and replacement of rock and gravel at the site.
On December 20, 2006, plaintiff served notice on defendants of its mechanic’s lien claim, in which plaintiff claimed a lien on public funds held by the PBC that were allegedly remaining unpaid to O.C.A. in the amount of $1,338,957.29. Plaintiff later reduced its claim to $697,382.53.
On March 20, 2007, plaintiff filed its complaint in the circuit court of Cook County. Count I, the count relevant in
Dismissal of a cause of action pursuant to
Plaintiff contends that the trial court erred in dismissing count I of its cause of action for failing to deliver a copy of the complaint to the PBC within 90 days of plaintiffs giving notice of the lien. Plaintiff contends that the trial court misconstrued
“It shall be the duty of any such clerk or secretary [of the municipal corporation] *** upon receipt of the first notice herein provided for to cause to be withheld a sufficient amount to pay such claim for the period limited for the filing of suit, unless otherwise notified by the person claiming the lien. Upon the expiration of this period the money, bonds or warrants so withheld shall be released for payment to the contractor unless the person claiming the lien shall have instituted proceedings and delivered to the clerk or secretary, as the case may be, of the *** municipal corporation a copy of the complaint as herein provided, in which case, the amount claimed shall be withheld until the final adjudication of the suit is had.” (Emphasis added.)770 ILCS 60/23(b) (West 2000).
In the present case, plaintiff filed its complaint within 90 days of giving notice of its mechanic’s lien, but did not deliver a copy of the complaint to the municipal corporation, PBC, within that same 90-day period. The trial court ruled that the failure to deliver a copy of the complaint to the PBC terminated the lien. Plaintiff contends that the trial court erred, as
Plaintiff’s argument is without merit. As discussed, when interpreting a statute, the court must “give effect to every word, clause, and sentence and may not read a statute so as to render any part inoperative, superfluous, or insignificant.” Newland,
Therefore, the clerk or secretary of the municipal corporation must withhold funds sufficient to pay a lien claim for 90 days upon receipt of notice of the lien. However, if the party claiming the lien does not institute proceedings and deliver to the clerk or secretary a copy of the complaint within that 90-day period,
Since plaintiff admits that it did not deliver a copy of the complaint to the municipal corporation (the PBC) within 90 days of giving notice of the lien claim, the trial court properly granted the contractor’s, O.C.A.’s,
Plaintiff contends that its delivery of the complaint to the PBC should relate back to the date of its filing of the lawsuit because “the failure to deliver a copy of the suit to the governmental unit within the 90 day period is a minor formal deficiency rather than a critical step in the creation or enforcement of a lien against
Plaintiff cites cases construing other sections of the Mechanics Lien Act. See Petroline Co. v. Advanced Environmental Contractors, Inc.,
For the foregoing reasons, the judgment of the circuit court is affirmed.
Affirmed.
GALLAGHER and NEVILLE, JJ., concur.