51 P. 408 | Idaho | 1897
The appellant, the Coeur D'Alene Eailway and Navigation Company (a corporation), entered in
1. The first is that the court erred in finding that the contract was as set forth in the third finding of fact. The point made is that the contract had certain specifications attached to it, which constituted an essential part of it, and were not included in said finding. The error is harmless. If the contract-had been omitted from the finding of facts altogether, the case
2. The second error specified is as follows: “The court erred in its finding that defendant’s failure to furnish relief under a November estimate was not due to the fault, negligence, or connivance of plaintiff.” This finding is clearly sustained by the evidence. The evidence also shows that defendant’s failure to furnish.said estimates, and to make payment thereunder, resulted very disastrously to the plaintiff. The plaintiff in no manner prevented the defendant from performing the matters and things it had stipulated to do.
3. “The court erred in finding the total estimates and classifications made by plaintiff’s engineers are right.” We have reviewed the evidence upon the points involved in this finding, and think the finding fully sustained. The engineers who made the estimates are shown to be very competent in their line of work, and plaintiff should not be required to suffer because there was some conflict of testimony touching the ability of the engineers to make accurate estimates. If the estimates were not correct, the defendant should have shown it. If its engineers had made accurate estimates of the work done by the respondent — and it is reasonable to presume they did — it certainly was in a position to show with accuracy the amount of the various classes of material removed, the fills made, and the other work done by the appellant. Instead of putting their engineers on the witness-stand for that purpose, its main effort appears to have been directed to show that work had been done on the road after plaintiff quit the job, and, because of such work having been done, respondent’s engineers could not estimate to a certainty the exact number of yards of grading done by respondent. The rule is well established that if the party possesses peculiar knowledge of evidentiary facts, which the other party claims would, if brought forward, tend to sustain his' claim, and if the party so possessed fails to bring forward the facts which it is shown can be produced by him alone, a presumption arises in favor of his adversary’s claim. (5 Am. & Eng. Eney. of Law, 2d ed., 41, and authorities there cited.)
5. “It was error to allow respondent seventy cents per cubic yard for the removal of hard-pan.” The contract contained no specifications providing for a hard-pan classification, and the rate which should be allowed plaintiff for the removal of hard-pan. Shortly after the plaintiff began work under said contract, he encountered hard-pan. The evidence shows that respondent had a conversation with Mr. Corbin, the president of the corporation defendant, and Mr. Olmsted, its chief engineer, in which he told them that he was bable to strike hard-pan, and asked them if they would give a hard-pan classification, and they informed him they would do what was fair about it. Mr. Corbin testified in regard to a conversation he had with Spaulding in regard to a hard-pan classification as follows: “Spaulding spoke to me about that. I recollect it distinctly. I told him that he should have an entirely fair classification, under the contract, as to hard-pan.” The witness afterward testified that he did not mean anything when he told Spaulding that he should have “an entirely fair classification under the contract, as to hard-pan.” When the presi
As no error has been found in the five specifications of error passed upon, the sixth and last specification, to wit, “It was error to overrule defendant’s motion for a new trial,” is without merit.
The persistent failure and refusal of the appellant company to perform the obligations imposed upon it by the contract are disclosed by the evidence, in this, to wit, to furnish estimates and make payments; to clear the right of way of timber, brush, logs, and stumps; to furnish finishing stakes — and in other matters set forth in the finding of facts. Such failure and refusal of the appellant company to perform its contract greatly retarded the work of the contractor, and placed him in a position, without fault on his part, to not complete the road in the time stipulated in said contract. The further fact is that the estimates of rock and earth work to be done in the construction of said road were, as made by appellant’s engineer, greatly under the amount of work required to be done to complete said road. That fact alone would have some bearing on that part of the contract which requires the road to be completed by the 15th of October, 1886. The estimated cost of