213 Mo. 218 | Mo. | 1908
The foregoing causes having been reconsidered and argued in the Court in Banc, the opinion of Woodson, J., in Division No. One; reversing the judgment and remanding the cause, is adopted as opinion of the Court in Banc. Gantt, G. J., and Burgess and Valliant, JJ., concur; Fox, J., expresses no opinion; Lmvm and Graves, JJ., dissent.
These appeals result from an action brought by J. H. Sparks against Jasper county to recover judgment for balances claimed to be due on three separate contracts for the construction of
The lower court found against plaintiff on the first count of his petition and for him on the second and third counts of his petition; found against defendant as to its various defenses, except on the first count of the petition; found against defendant on all its counterclaims except twenty-two dollars over-payment, and rendered a judgment in favor of plaintiff for the balance of--dollars.
A concise showing of the issues made by the pleadings is as follows:
The amended petition is in three counts:
Is* Count on contract for Blackberry Bridge............................$2,895.00
With credit for $1,400.00; balance claimed ...........................1,495.00'
2nd. Count on contract for Tuckahoe or Turkey Creek Bridge and moving and rebuilding bridge on Jones Creek........ 2,990.00
For extra, concrete pillars at Jones Creek............................. 65.00
Credits $1,100 paid, and claims balance ■of ................................ 1,955.00
3rd. Count on contract for three steel bridges, 1 Turkey Creek range line bridge, secs. 32 and 33; span south end of Terry’s Ford bridge; 1 bridge across Center Creek at Reeds Station........ 9,650.00
Credits $5,400, and claims balance of.. 4,250.00
1st. Denies right to recover $1,495 on Blackberry bridge or part for reason contract was not let as provided by law. Advertised to be let at bridge site and! if let at all was let one-half mile or more from site, and?, contract sued on was obtained by fraud committed by' plaintiff and G-rieb, Bridge Commissioner, on county' and county court.
2nd. Denies right to recover $65 for concrete pillars at Jones Creek bridge. No contract for same and! no- order of county court for same. The payment of $1,100 by county court was on contract for Tuckahoe and Jones Creek bridge and not on extra. Plaintiff has no right to apply any part on this extra concrete pillar work.
3rd. Defense as to $2,900 by virtue of order of Sparks to David Miller for $3,500 upon which county has paid $600 to Central National Bank, assignee of order with plaintiff’s approval, and after completion of bridge contracts paid said bank $2,600, for which defendant is entitled to credit.
COUNTERCLAIMS AND OFFSETS BY DEFENDANT.
1st. Claim for $1,400 paid on Blackberry.Bridge for the same reasons for defending against first count for balance claimed on said bridge.
2nd. Claim for $2,471 — $22 being amount overpaid as shown by contracts and payments on Carl Junction, Belleville and Rucker’s Ford bridges. The-contract being $13,678, and the payment being $13,-700. $2,449 of claim being for amount paid for extra, span on Carl Junction bridge. Said span being built without any contract upon an order-of the county court without any compensation being fixed.
3rd. Claim for $15,935 — $4,850 for Terry’s Ford bridge; $2,645 for Duenweg bridge; $4,745 for Hille’s
There is little or no dispute about the facts when you get into the evidence. So the questions before the court are mainly questions óf law.
OPINION.
I. The plaintiff insists that the finding of the court against him on the first count of the petition was error, and that the judgment rendered thereon should be reversed.
The plaintiff’s evidence upon this count of the petition tended to prove that the contract for building the bridge was advertised to be let by public outcry at the site of the proposed bridge, and that on the day designated for letting the contract, the road and bridge commissioner of the county, accompanied by plaintiff and three other prospective bidders for said bridge, went by rail to Carl Junction, and from there drove in a hack to a point about one-half mile from the site of said proposed bridge, and in plain view thereof; that they looked at the site from that distance, but saw no one there; that said bridge commissioner announced then that he would then and there let the bridge contract by public outcry to the lowest bidder; that in good faith he proceeded to let the contract by outcry, and received several bids from the various parties who accompanied him, among whom was the plaintiff, who bid $2,895, which was the lowest bid made; and that the contract was then and there awarded to the plaintiff for said sum, which was afterwards approved by the county court, and, in pursuance thereof, the contract sued on was executed.
The defendant’s evidence tended to prove that when the parties got to within about one-half mile of the site of the proposed bridge, they realized that they could not drive on to the site and return in time to
The court gave an instruction for the plaintiff and defendant, presenting their respective theories of the case. Under the evidence and the instructions the court found the facts for the defendant and rendered judgment accordingly. This action of the court is assigned as error.
The law requires public notice to be given of the proposed letting of contracts for building bridges, stating the time and place the contract will be let. The object of the notice is to inform prospective bidders of the proposed letting so that they may meet there and make competitive bids for their construction.
The court found, and justly so, we believe, that, the bridge commissioner and the bidders who accompanied him did not know nor could they testify positively that there were no prospective bidders at the site of the proposed bridge on the day the contract was advertised to be let. These parties may have been in full view of the site, and they may not have seen any one at or near there, yet that does not signify that there was no one there in fact, for they may have been there and still not observable from the point where plaintiff claims the contract was let, which was a half mile or more from the site. Prospective bidders might have been there, down in the creek, the banks of which might have obstructed the view. At any rate, this was a matter the trial court had a perfect right to take into consideration in passing upon the weight to be given to their testimony.
In addition to what has just been said, the positive testimony of one of the party who drove out to the point where the contract was said to have been let, is to the effect that the country between that point and the bridge site was rough and uneven, and for that rea
To view this evidence in the most favorable light possible to plaintiff, • still it cannot be sincerely contended that there is no evidence to support the finding of the court upon that issue. In fact, there was a direct and sharp conflict between the testimony introduced by plaintiff and defendant which presented a proper question of fact to be determined by the court.
The law is that where the evidence introduced by the respective parties is conflicting and of a substantial nature, the findings of the trial court or jury will not be disturbed by this court. [Everman v. Eggers, 106 Mo. App. 732; Culbertson v. Hill, 87 Mo. 553; Blanton v. Dold, 109 Mo. l. c. 69; Weller v. Wagner, 181 Mo. 151.] The reason for that rule is obvious. The triers of the facts have before them the witnesses who testify in the case; and they have the opportunity of observing their demeanor while upon the witness stand and their manner in testifying*. They are in a much better position to judge as to the credibility of the witnesses and the weight to be given to their testimony. This rule is usually followed even in equity cases where this court has the unquestioned right to review and weigh anew the evidence of the ease, and if the findings of the chancellor are based upon substantial evidence, this court will refuse to reverse a decree of the lower court on the ground that the findings were against the weight of the evidence. [Johnson v. Realty Co., 177 Mo. 595-597.]
Counsel have cited no authority sustaining the proposition that a letting of the contract a half mile from the site of the proposed' bridge was a compliance with the requirements of the statute; while, upon the ether hand, this court has many times held that a sale under a deed of trust if held at a place different from
The principle underlying the cases just cited is applicable to the facts of this ease; and by a parity of reasoning there is no escape from the conclusion that the contract sued on in the first count of the petition was not properly let, and for that reason the court properly held the plaintiff was not entitled to recover thereon. [Boeder v. Robertson, 202 Mo. 1. e. 537.]
II. The second count of the petition is based upon a contract to construct a bridge across Tuckahoe or Turkey Creek, and for moving and rebuilding a bridge across Jones Creek. The contract price for both was $2,990.
By a subsequent and separate oral agreement, the defendant employed plaintiff to construct some concrete pillars for the Jones Creek bridge, and agreed to pay him $65.00 therefor.
During the progress of this work the county court issued to plaintiff a county warrant for the sum of $1,100 as part payment on several bridges he was building for the county, designating the bridges and the sum to be applied to each, and one of the items stated therein, and among them, is the following:
“Tuckahoe Bridge $1,100.00”
Had plaintiff credited that sum upon the amount ■due him on the Tuckahoe Bridge, there would have been a balance due him of $1,890; but instead of doing that he applied $65 of it in payment of the concrete pillars built for the Jones Creek bridge, which left $1,035 to be credited on the Tuckahoe account. He then credited the latter account with said sum, which left a balance of $1,955 due him on that account.
If the first objection is valid, the second is immaterial in so far as this suit is concerned, for the reason he has not sued for the $65, but claims it has been paid.
As to the first objection presented, concede for the sake of agreement, without deciding it, that both of said contracts are valid — that is, the contract for constructing-the Tuckahoe bridge and the contract for building the concrete pillars, yet that would not have authorized the plaintiff to make the application of payment as he attempted to do, crediting $65’ of the $1,100 on the concrete pillars account, and the balance on the Tuckahoe Bridge account, for the reason that the defendant made the application of payment at the time the $1,100 was paid by it, which is shown by the warrant before mentioned.
The law of this State is well and firmly settled, that when a debtor owes two accounts and both are due he has the right to designate the one upon which payments made by him shall be applied, and if he make the application, then the creditor has no power to make the application, or to change the application so made by the debtor; but if the debtor fails or refuses to make the application of payment, then the creditor
It follows from what has been said that the trial court erred in permitting the plaintiff to make the application of payment after the county had previously done so. There are no other objections urged against the judgment rendered in favor of the plaintiff on the second count of the petition.
III. The third count of the petition is based upon the contract to construct three steel bridges — one across Turkey Creek, on range line, sections 32 and 33; one at Terry’s Ford; and the third across Center Creek at Reeds Station. The contract price was $9,650. The county court has paid on this account the sum of $5,400, leaving a balance of $4,250, claimed by plaintiff to he due him, less the sum of $600 paid by the' defendant to David Miller, or for his use and benefit, under the following circumstances:
The record discloses the fact that plaintiff had been constructing bridges in Jasper county for several years prior to the beginning of this litigation, and that said Miller was a subcontractor in constructing those bridges, including the three last mentioned. That on September 29th, 1903, the plaintiff gave to said Miller the following order upon the countv court of said county, to-wit:
“St. Joseph, Mo., Sept. 29, 1903.
“Hon. County Court Jasper County, Carthage, Mo.
“Gentlemen: Please pay to David Miller the sum of thirty-five hundred dollars for building all bridges for which I now have contracts for in Jasper Co. excepting Jones Creek Bridge, payable when work is*234 completed and accepted by T. Y. G-reib, Co. Surveyor, and charge same to account of me on my contracts.
“Respectfully,
“J. H. Sparks.”
Indorsed on the back thereof is the following:
“For value received I assign the within order to the Central National Bank of Carthage, Mo.
“David Miller.”
The record discloses the facts that Miller was a subcontractor under plaintiff, and furnished much of the labor and materials used in the construction of those bridges; that he borrowed money from the Central National Bank of Carthage, with which he carried put his subcontracts, and turned over to the bank orders issued by plaintiff to him on the county court of Jasper county similar to the one before mentioned, in payment of the money so borrowed by him. At the time plaintiff issued the order before set out, Miller was indebted to said bank in a sum in excess of $3,500 therein mentioned. At the time Miller indorsed the order over to the bank, it gave him $400 in cash, and credited his account with $3,100, the balance thereof. Sometime thereafter the county court of said county paid to the bank on the order $600. Plaintiff does not object to the action of the court in so paying that $600, because it was paid before he countermanded the order.
About this time.Miller abandoned his contracts with plaintiff to build the bridges, and left them in an unfinished condition. When Miller threw up his contracts and refused to complete the bridges, the plaintiff served written notice on the county court not to pay the order issued by him to Miller for $3,500, dated September 29, 1903. The plaintiff was then required under his contracts with the county court to complete the bridges, which he did at a cost of something over
It is thus seen that the only controversy between the plaintiff and defendant on the third count of the petition is over this $2,900 paid by the connty court to the Central National Bank.
The defendant’s position regarding that matter is this. It contends that the course of dealing between the plaintiff and said Miller created some kind of an agreement or understanding between plaintiff and the bank by which it was to furnish the necessary money to Miller with which to purchase material and employ labor used in the construction of the bridges by him under his subcontract, and that plaintiff was to issue orders to Miller on the county for money due or to become due him for work and materials done and furnished on said bridges, which the hank was to receive in payment of the money só furnished by it to Miller.
While the record shows that was the course of dealing between the parties, yet the record is perfectly silent as to any agreement or understanding on the part of plaintiff by which he bound himself to pay to the hank or to any one else any sum of money except as stated in the orders issued; and that he in no manner authorized the bank or any one else to furnish Miller money on account of said orders. The mere
We are, therefore, of the opinion that the action of the court in holding the county liable to him for that .sum was proper.
IV. The defendant sets up in its answer divers counterclaims and setoffs, aggregating about $15,000, for money paid by the county to plaintiff for bridges constructed by him in years gone by, under various contracts, which defendant alleges were illegally let to plaintiff.
Under those circumstances, conceding for argument’s sake the contracts were illegal in their inception, yet it would be unjust and inequitable to permit the county to retain the bridges and at the same time recover back the money paid therefor. That principle of equity should apply here which requires persons who seek equity to do equity before their prayer will be heard.
This is no novel question to the jurisprudence of this country. The law is that where there has been a¡' complete performance of the contract on both sides and it is fair and reasonable in fact, there can be no recovery of the consideration by the municipal corporation where it retains and enjoys the benefits of the contract, and where it cannot or will not restore the property acquired by the contract, eve'n though the contract be one which the law denounces as illegal and which could not be enforced on that account. [Frick v. Town of Brinkley, 61 Ark. 397, 33 S. W. 527; 20 Am. and Eng. Ency. Law (2 Ed.), 1180; Riverside Co. v. Yawman & Erbe Mfg. Co. (Cal.), 86 Pac. 900; Long
In Frick v. Town of Brinkley, supra, a member of the city council (prohibited by law from making contracts with the city) sold the city a lot of tiling and received payment therefor. Subsequently an action was brought to recover the purchase price without returning the tiling. The court say: “We think it [the town] cannot, in good conscience, be allowed to receive the value back, while at the same time it is enjoying the benefits of its purchase — at all events when it does not even offer to restore that which it claims could not have been its property, and, consequently, is not now its own. This is not the assertion of any right which the appellant has, nor any obligation resting upon the appellee, under the contract of purchase, but it is a rule of justice and right growing out of an implied contract and obligation of every one, whether a natural or artificial person, to restore to another that which belongs to him, and that is in the possession of the former or in his power to restore; and when the power to restore does not exist, or when a restoration in the nature of things becomes impracticable, then to be precluded from recovering back the fair price paid. In such cases as this, the sole duty of the courts seems to be to see that the public corporation suffers no material loss or injustice, but further than this they could but inflict burdens upon others more or less disastrous, where no resulting good can follow — a thing courts of justice ought not to'indulge in.”
In Riverside County v. Yawman & Erbe Mfg. Co., supra, the court says: “It affirmatively appears from the complaint that the board of supervisors has purchased, paid for, and retained the use of certain personal property, and a court is asked to compel restitution with penalty in favor of such purchasers. The Legislature never contemplated conferring such power
In Long v. Boone County, 36 Iowa 60, quoted with approval in King v. Mahaska County, 75 Iowa 336, it was held: “When the legally constituted agent of the county contracts for work in respect to which he has no power unless authorized by a special vote of the people, and executes a warrant for the amount thereof to the treasurer of the county, which is voluntarily paid by the latter officer, the county cannot recover back the amount so voluntarily paid.”
While some of the expressions in the ease of King v. Mahaska County, 75 Iowa 329, seem at first blush to support defendant’s contention, when critically considered it will be seen that it distinguishes that case from the case of Long v. Boone County, 36 Iowa 60, by using the following language, on page 336: “When all the pleadings are considered the defendant was not in the attitude of seeking to recover back money paid to the plaintiff on these illegal contracts.”
The Supreme Court of the United States and courts of last resort of -many of the States go much further in the adjustment of the rights of parties growing out of illegal contracts than this court has. In
The Supreme Court of the United States, in the case of Chapman v. County of Douglas, 107 U. S. l. c. 357, in discussing this question, used this language: “This doctrine was fully recognized by the Supreme Court of Nebraska as the law of that State in the case of Clark v. Saline County, 9 Neb. 516, in which it adopts from the decision of the Supreme Court of California the following language: ‘The city is not exempted from the common obligation to do' justice which binds individuals. ' Such obligations rest upon all persons, whether natural or artificial.' If the city obtain the money of another by mistake, or without authority of law, it is her duty to refund it, from this general obligation. If she obtain other property which does not belong to her, it is her duty to restore it, or, if used, to render an equivalent therefor, from the like obligation. [Argenti v. San Francisco, 16 Cal. 282.] The legal liability springs from the moral duty to make restitution.’ ”
The same rule is announced in the following cases: Louisiana v. Wood, 102 U. S. 294; Marsh v. Fulton Co., 77 U. S. l. c. 684; Hitchcock v. Galveston, 96 U. S. l. c. 351; McBrian v. Grand Rapids, 56 Mich. 103; 1 Beach on Pub. Corp., sec. 227.
These cases are but samples of the overwhelming authorities which hold that where a moral duty exists to make satisfaction, a legal liability springs therefrom. And as said by the Supreme Court of the United States in the case of Hitchcock v. Galveston, supra: “There may be a difference between the case of an engagement made by a corporation to do an act expressly prohibited by its charter, or some other law, and a case of where legislative power to do the act has not been
The same is true .of the case at bar. Jasper county was not prohibited by statute from building bridges; but, upon the other hand, the statute expressly grants to the county that power.
Conceding the contracts for building the bridges were illegal, yet the execution of those contracts was, at most, a defective exercise of the power granted; and
The conclusions reached in these cases are correct and rest upon sound reason. They were suits based upon contracts not in writing, etc., which were prohibited by statute, and the court in those cases simply enforced the statute as it found it, and, to have done otherwise would have given force and effect to contracts which were prohibited by statute from being made. [Roeder v. Robertson, 202 Mo. l. c. 537.]
But that is not the question involved in this case. Here the plaintiff is not asking this court to enforce these alleged illegal contracts. They were years ago fully performed on both sides; and the defendant is now here by way of counterclaim, in the nature of a cross-bill, seeking to recover back the money she paid for those bridges without an. offer to return them to the plaintiff. This she cannot do without she first returns or offers to return them to him; and the reason therefor is this. If the contracts were void, then the title to the bridges never passed thereby from plaintiff to the defendant and became her property; but they remained his property the same as though the contracts had never been entered into. That being true, then when the county acquired the possession of the bridges under those,void, yet colorable, contracts, she was morally bound to pay for them, as she did; and conceding, as before stated, without deciding it, that after accepting the bridges and paying for them, she had the right to repudiate the contracts and sue for the recovery of the money paid by her for them, she would
Tbis same principle underlies tbe case of Roeder v. Robertson, 202 Mo. 522, and on page 535, tbis language is used: ‘ ‘ The act is .prohibitive in its operation. It seeks to prevent foreign corporations from doing business in tbis State until they have complied with tbe provisions of tbe act by filing a copy of their charter or articles of incorporation with tbe Secretary of State and by appointing an agent in tbis State to represent them. If such corporations, in violation of tbe act, do business in tbis State, all such transactions are, by tbe courts, declared null and void, and' all contracts made by them with citizens of tbis State for tbe sale of goods, wares and merchandise are nullities, and tbe title to tbe property sought to be transferred thereby does not pass to and vest in tbe vendee, but remains in tbe vendor, tbe same as if the pretended contract, had not been executed.....For under tbe facts of this ease a citizen of this State would not be permitted to recover tbe possession of tbe property sold to tbe respondents, nor its value, in case of its conversion, without first refunding or paying back to tbe respondents tbe consideration paid by them under tbe void contract, and received by A. W. Stevens & Son. He would' be estopped from claiming tbe property until tbe purchase price bad been returned.” [Simpson v. Stoddard Co., 173 Mo. 421.]
And there is another reason equally valid why tbe defendant should not be permitted to recover upon her counterclaims, which is well expressed by Judge Fox, in tbe case of Simpson v. Stoddard Co., 173 Mo. l. c. 466, in the following language: ‘ ‘ Tbe principle is that, where a county court is charged by law with tbe performance of certain duties in reference to a particular
We are, therefore, of the opinion that the ruling of the trial court in disallowing all of the counterclaims was proper.
Because of the error of the trial court, pointed out in the second paragraph of this opinion, regarding the application of payments, the judgment is reversed, and the cause remanded with directions to disallow plaintiff’s claim of $65' for the concrete pillars constructed for the Jones Creek bridge, without prejudice, and to affirm the judgment in all other particulars.