90 Kan. 725 | Kan. | 1913
The opinion of the court was delivered by
The action in the district court was one to foreclose mechanic’s liens for labor and material furnished to, improve the property of Charles Riley. Riley died pending the proceeding and the action was revived against his administrator, Maurice V. Perkins, and against his sole heir, Robert Riley. Liens were established in favor of the Southwestern Paint and Wall Paper Company, the McCoy Lumber Company, and F. F. Clough, subcontractors under W. G. Powell, the contractor who erected the improvements. The administrator and heir appeal.
Riley and J. H. Roberts owned adjacent lots. Each one erected a building on his own lot, the two structures, however, having a common wall. Powell acted as the contractor of both owners and worked on both buildings at the same time. He purchased material for both buildings from the paint company and from the lumber company. Each one charged the material it furnished to an account on its books designated as “Roberts & Riley Job.” After the last material ordered from the paint company had been furnished, it made a complete and accurate segregation of the items used- in the Riley building. The account thus prepared was approved by Powell and by the foreman of the work. Powell gave an order on Riley for its payment and a copy of it was attached to the lien statement. The lumber company, with the assistance of 'Powell and Roberts, made an apportionment of the material
It is argued that the paint company and the lumber company are not entitled to liens because of a confusion of accounts and because the Tien statements were indefinite.
It may be premised that the mechanic’s-lien law of this state is not, like similar laws in some other states, construed strictly because in supposed derogation of the common law. The law is framed on broad principles of justice and equity which would call for a liberal interpretation in the absence of a statutory rule governing the matter. (Deatherage v. Henderson, 43 Kan. 684, 690, 23 Pac. 1050; Lumber Co. v. McCurley, 84 Kan. 751, 115 Pac. 590; Lumber Co. v. Douglas, 89 Kan. 308, 316, 131 Pac. 563.) But besides this, the legislature has prescribed a rule which reads as follows:
“The rule of the common law, that statutes in derogation thereof shall be strictly construed, shall not be applicable to any general statute of this state, but all such statutes shall be liberally construed to promote their object.” (Gen. Stat. 1909, § 9850.)
A confusion of accounts destroys the basis of a lien only when confusion actually results. The items furnished- by the paint company for the Riley building were separable and were in fact separated from those furnished for the Roberts building and were specified in the lien statement. While the items furnished by the lumber company to the Riley building could not be
“Any person who shall furnish any such material or perform such labor under a sub-contract with the contractor . . . may obtain a lien ... by filing- . . . a statement, verified by affidavit, setting forth the amount due from the contractor to the claimant, and the items thereof as nearly as practicable.” (Civ. Code, § 651.)
Under the circumstances the items of the amount due the lumber company from the contractor were set forth as nearly as practicable. In the beginning it would have been possible for the contractor to give separate orders for each building, but it was much simpler and therefore good business to give orders in bulk for all material of the same kind needed for both. The final result was an account showing all items furnished and all credits, including pay for the portion assigned to Roberts. The remainder was chargeable to the Riley building and the lien statement so claimed. If the lien statement had recited all the facts there would have been no indefiniteness or uncertainty and the statement would have been unimpeachable. Since the statute only requires “items” as nearly as practicable and since these were given as nearly as practicable the statement was sufficient to support a lien.
The appellants cite the case of Nixon v. Cydon Lodge,
“ ‘Items:
“ ‘To contract price as per agreement. . $28,800.00
“ ‘Value and amount of material furnished and labor performed up to the abandonment of contract and building by the owner.......... $23,523.60
“ ‘By cash paid..................... 12,423.17
“Balance ...................... $11,100.43’”
(p. 302.)
The court said:
“As will be seen, this is no more than a lumping of the items included in the whole contract price, another including the estimated value and amount of material furnished and labor performed, and another giving .a credit for the amount which had been paid. . . . That is was not itemized as nearly as practicable is readily seen, since they do not separate the labor from the materials, they do not give the amount of the subcontracts, nor do they separate the amounts expended for excavation, for stone, for brick, for iron, for terracotta, and for wood, and the labor upon each, as might have been done. From the record, it appears that the work was largely divided up and sublet to others, and a detailed statement to that extent was practicable and might have been readily made.” (pp. 302, 303.)
Other cases are cited in which one lien was sought for the aggregate amount of material furnished under distinct contracts, in which the confusion was such that no separation was possible, and in which apportionment was attemped to be made by guess. Manifestly none of these decisions is applicable to the present controversy.
Written notice of one of the liens was served on Eiley himself by registered mail. The statute provides that notice in writing shall be served on the owner without prescribing the method. Any method which' effectually accomplishes the statutory purpose is sufficient.
It is said that the judgment makes the owner liable beyond the contract price of the building. In the beginning the contractor had only a pencil sketch of a one-story building one hundred and ten feet long which he agreed to erect for a certain sum. Then a second story was added fifty feet long. Then the second story was extended to one hundred and ten feet and a third story was added fifty feet long. After the building had been completed and a portion- of it had been leased a settlement was made between the owner and the contractor, in which estimates were made with reference to the second and third stories, and separate contracts were then signed relating to them. The sum of the three contracts was much less than the actual cost of .the building. From this and other evidence the court rightly concluded as a matter of fact that there was no “contract price” until after the building was finished, and rightly concluded as a matter of law that a contract price fixed in that way did not limit the liability of the owner to subcontractors.
There was ample proof that Powell was really the agent of Riley in purchasing material and employing labor for the erection of the building, and not simply a contractor, within the meaning of the mechanic’s-lien law. Amendments to the pleadings to conform to this proof were properly allowed, and judgment was prop
The judgment of the district court is affirmed.