OPINION
The only issues we address in this case concern the trial court’s charge to the jury on intentional interference with contract.
The City of Houston notified Southwestern Bell Telephone Company in January 1984 that it intended to widen Fountain-view Drive between Westheimer and Highway 59. A City Ordinance provided:
The telephone company shall, upon the written request of the City, relocate its facilities situated within any street at no expense to the City where reasonable and necessary to accommodate street widening or improvement projects of the City.
Before contracting for the proposed work, the City inquired when Bell’s facilities (consisting of aerial cables, poles, and buried cables) could be moved to accommodate the project. Bell informed the City that it could relocate its facilities by the end of December. .Several weeks later, on March 23, the City signed a contract with John Carlo Texas, Inc. for the street widening project. The contract required commencement of the project in April and completion within 210 working days. Bell relocated its aerial poles in phases, completing the work in April 1985. Carlo finished the project four months later. The City did not complain that Bell failed to comply with the Ordinance, and also did not assess contractual liquidated damages against Carlo for failing to complete the project on time. However, Carlo claims to have been damaged by Bell’s failure to move its facilities in a timely manner. Carlo sued the City for breach of their contract and Bell for intentional interference with that contract.
The jury failed to find that the City breached its contract with John Carlo with respect to the relocation of Bell’s facilities, and the trial court rendered judgment on the verdict in favor of the City. The jury did find, however, “that Bell knowingly and intentionally failed, without justification to
*472
timely relocate its facilities”, and that this failure proximately caused Carlo $171,-155.80 actual damages. The jury also assessed $500,000 punitive damages against Bell. The trial court rendered judgment for Carlo against Bell for the damages found by the jury. Carlo did not appeal the judgment in favor of the City. The court of appeals affirmed the award of actual damages but reversed the award of punitive damages.
Interference with contract is tor-tious only if it is intentional.
Victoria Bank & Trust Co. v. Brady,
Moreover, the trial court improperly refused Bell’s request to define “justification” for the jury. “Interference with contractual relations is privileged where it results from the exercise of a party’s own rights or where the party possesses an equal or superior interest to that of the plaintiff in the subject matter.”
Black Lake Pipe Line Co. v. Union Constr. Co.,
Carlo and Bell raise several other issues which we do not address. Our action should not, of course, be taken for approval of the court of appeals’ disposition of such issues. The judgment of the court of appeals is reversed, and the case is remanded to the trial court for a new trial. The trial court’s judgment as to the City remains final and undisturbed.
