206 Ct. Cl. 857 | Ct. Cl. | 1975
Contracts; interpretation; trade practice; necessity to seek clarification. — Plaintiff seeks additional compensation under a small business contract with the Navy Department for construction of 32 mechanized landing craft. Plaintiff contends that it bid on and accepted the contract under the warranted assumption that it would be able to build the craft in an economically efficient manner in two segments, stern and front, and then weld them together in a continuous circumferential weld, but that the Navy ordered it to build the craft with side and bottom plates so sized and located as to require staggered welds and thereby make two-piece construction economically unfeasible, which it claims is a constructive change. The Armed Services Board of Contract Appeals denied the claim on the ground that the Navy’s requirement did not constitute a change but was always in the contract. Plaintiff urges here that there was an established trade practice permitting the building of the craft with a continuous circumferential seam amidships so as to allow two-piece construction. In a recommended opinion filed June 27,1974 (reported in full at 20 CCF para. 83,157), Trial Judge Philip ft. Miller concluded that the Board properly found that plaintiff had no reasonable basis for the belief that defendant had waived the contract requirements for the staggered welded seams. Plaintiff had never previously held a contract for the production of the craft, and therefore could not have relied on an established course of dealings in submitting its bid; the record does not reflect that the Government held out landing craft of prior boatbuilders as a standard for plaintiff to follow; plaintiff’s examination of the incompleted and yet unaccepted two-piece craft of prior builders hardly warranted its reliance that it was entitled to do likewise under the specifications on which it bid, since it had neither examined the contract specifications of the other builders nor did it know at the time it submitted its